20.1 Private Water Wells
Key Takeaways
Michigan private wells are governed by Part 127 of the Public Health Code (MCL 333.12701 to 333.12715) and the Water Well Construction and Pump Installation Code (R 325.1601 to R 325.1781); the county or district health department issues the well construction permit before drilling.
R 325.1632 requires permanent casing to extend at least 25 feet below grade and terminate at least 12 inches above it; a well with less than 26 feet of casing cannot be used without written approval from the health officer.
Michigan R 325.1622 normally requires 50 feet horizontally from a private well to a septic tank or subsurface disposal field and 10 feet to a qualifying watertight gravity sewer or a surface water body. Different rules apply to public water supply wells and a local rule or written deviation may affect the site.
Plan for the tested yield, pumping level and household demand. For routine private well testing, MDHHS recommends annual coliform, E. coli, nitrate and nitrite testing. Commissioning samples after disinfection are a separate code requirement.
The well owner generally sees that an abandoned well is plugged. Michigan allows an owner to plug an eligible well under the same code, and requires a registered well drilling contractor in the situations specified by R 325.1662. The person doing the plugging submits the report within 60 days.
20.1 Private Water Wells
When a lot has no municipal water, the private well becomes the single point on the site where the entire house depends on groundwater quality and quantity. A well in the wrong location can hold up approvals or require relocation, and a poor seal gives contamination a path into groundwater. Michigan regulates private wells under Part 127 of the Public Health Code, 1978 PA 368 (MCL 333.12701 to 333.12715), implemented through the Water Well Construction and Pump Installation Code, R 325.1601 to R 325.1781. EGLE administers the program statewide, but the county or district health department issues the well construction permit, reviews the site, and enforces the code locally. A local rule may be stricter than the state minimum, so the plot plan gets checked against both.
Who drills, who permits, who records
- Well drilling contractor: must be registered to engage in the business. MCL 333.12706 requires the registration number, including the county code, on both sides of the drilling machine in figures at least 2 inches high, with the current seal and required identification next to it. MCL 333.12703(2) allows a person to construct a well or install a pump on property they own or lease for their own permanent single-family residence or their own farm use, within the limits of that subsection. Record, construction and applicable permit requirements still apply.
- Well construction permit: obtained from the local health department before the rig moves onto the lot. Drilling before the permit exists is a violation no matter how good the well turns out.
- Pump installer: a separately registered trade. A registered pump installer may install and service the pumping equipment. Pump installer registration does not authorize well drilling activities (R 325.1608). A licensed master plumber may do the pump work allowed by MCL 333.12703(3) without a separate pump installer registration.
- Well log (water well record): under MCL 333.12707 the contractor must deliver the record not later than 60 days after completion - one copy to the owner and two copies to the state or local health department. It records owner name, well location, total depth, geologic materials and thicknesses, amount of casing, and static water levels. That log is the as-built document you attach to the plot plan and hand to the next owner.
Well types you will see in Michigan
| Type | How it is made | What the builder must know |
|---|---|---|
| Drilled (rotary or air) | A rotating bit cuts a borehole through overburden and usually into bedrock or a sand-and-gravel aquifer; permanent casing and grout are installed | Allows a buried aquifer to be accessed and cased. Confirm rig access and a suitable setup area. |
| Driven well point | A screened steel point and pipe are driven into shallow saturated sand | Steel casing for a driven point must be at least 1-1/4 inch inside diameter, and a driven point may not serve as a water supply well without the written approval of the health officer (R 325.1632a) |
| Dug or crock well | Large-diameter hand or machine excavation lined with tile, brick, stone, or concrete crock | Mostly legacy wells; the current code addresses them chiefly through plugging rules (R 325.1665) |
| Bored or augered | A large-diameter boring advanced without drilling fluid | Grouting requirements are specific to rotary-bored and augered wells (R 325.1634a) |
Casing, grout, and seal: three barriers against contamination
Casing holds the borehole open and keeps shallow water, soil, and surface runoff out of the aquifer. Permanent steel casing must be at least 2 inches inside diameter; PVC permanent casing must be at least 5 inches inside diameter unless installed as liner pipe, and PVC well casing may only be installed in an oversized borehole - never driven. A casing must extend at least 25 feet below the ground surface and terminate at least 12 inches above it (R 325.1632). A well with less than 26 feet of casing cannot be used without written approval from the health officer. In a paved area the health officer may approve in writing a termination at least 2 inches above the surface where the area does not flood, every connection is threaded or welded and watertight, and venting is acceptable.
Grout seals the annular space between the borehole wall and the casing, which is the path surface water would otherwise follow straight down the outside of the pipe. Neat cement or bentonite grout must be placed through the casing or a grout pipe from the bottom of the annulus upward to the ground surface in one continuous operation, with the density of grout returning at the surface matching the density being pumped in. Shale traps, cementing baskets, packers, or similar devices may not be used to suspend grout above an open annular space.
The well head is the third barrier. Caps and seals must be weathertight, vermin-proof, and tightly secured, and vents must be screened with 20- to 30-mesh screen without reducing open area by more than half (R 325.1657, R 325.1657a). A pitless adapter carries the service line through the casing below frost without a pit; it must be a department-approved device, and clamp-on saddle types must have both gaskets pressurized by pump water so any leak flows outward rather than inward. Ground immediately around the casing must be graded to divert surface water, and a well may not be placed in an area subject to flooding unless the health officer approves protection in writing.
Isolation distances: the table that decides the layout
R 325.1622 sets these minimum horizontal distances for the private well. Place it as far from contamination sources as practical and upgradient where possible. Public water supply wells use the isolation rules referenced in R 325.1622(3) under the Safe Drinking Water Act.
| Minimum distance | Sources of contamination |
|---|---|
| 800 feet | Active work area of a landfill; land surface application of septage waste |
| 300 feet | Land application or subsurface injection of municipal wastewater treatment effluent or digested sludge; oil and gas wells; petroleum product processing or storage facilities; regulated storage tanks of 1,100 gallons or more without secondary containment |
| 150 feet | Fertilizer, agricultural chemical, or other chemical preparation and storage areas |
| 50 feet | Septic tank; subsurface disposal field; dry well; sewage pump chamber; grease trap; seepage pit; cesspool; outhouse; animal or poultry yard; buried sewer other than the watertight gravity sewer described below; pressurized sewer; other wastewater handling or liquid waste disposal sites; regulated storage tank systems of at least 1,100 gallons with secondary containment; smaller tanks storing motor or heating fuel for noncommercial purposes or use on the premises |
| 10 feet | Buried gravity-flow sewer with watertight joints and service-weight or heavier ductile iron, Schedule 40 PVC, or material and joints approved in writing by the director; a sump, pit, or unfilled below-grade space (a crawl space is excepted); a surface water body such as a lake, pond, river, or stream |
Two rules sit on top of that table. First, the well must be at least 3 feet horizontally from a building, pump room, or any projection of them, and it must remain accessible for a drilling machine (R 325.1624). Second, the health officer may prescribe a different distance for an individual installation under R 325.1613, using the grounds and conditions in that rule. A constrained lot by itself is insufficient. The well owner maintains the required distances on property the owner owns. Take horizontal measurements on the plan.
Yield: how much water, and who decides
R 325.1621 requires the well to be adequate for its intended use. The general well code sets no fixed production rate. Covered land divisions and subdivisions have a separate rule, R 560.411, with a sustained pumping test of at least 10 gallons per minute and at least 4 hours at a rate meeting peak demand. If the well cannot sustain peak demand, the rule requires demonstrating usable yield plus storage that meets peak demand. Check any applicable local and project requirements as well.
- Static water level is measured after the well has recovered from pumping.
- Pumping water level is measured while the pump runs. The difference from static level is drawdown.
- A yield test records discharge rate, duration and drawdown. Recovery readings after shutdown help show how the well replenishes. A short test at high flow can draw on water already stored in the casing.
- For a low-yield well, have the installer evaluate the sustainable rate, usable storage and peak demand together. Where added storage is proposed, use its usable volume and the intended refill rate. The pressure tank’s nominal volume is different from its usable drawdown.
Record and share the test results and the well log. Use the measured pumping level and the well construction record to select and place the pump with the installer.
Water quality: disinfection, sampling, and routine testing
R 325.1661 assigns disinfection of the work area in the water supply system to the well drilling contractor or pump installer. Before a new, repaired or reconditioned system enters service, collect one or more samples after flushing out the chlorine. The commissioning sample must be free of coliform organisms. R 325.1661 Table 5 specifies chlorine concentration and minimum contact time for the work.
The required sampling faucet turns downward, is at least 8 inches above the floor, and goes at the pressure tank or as near the well as possible (R 325.1658). The owner collects the sample or designates a representative, and the contractor tells the owner about that responsibility. The rule does not require redisinfection by the contractor because a sample was collected at an alternate outlet.
MDHHS recommends annual testing for coliform bacteria, E. coli, nitrate and nitrite, tests for arsenic and lead every 3 to 5 years, and testing at least once for PFAS. Contact the local health department about laboratory testing after flooding, well repairs or a change in taste, color or odor, and for guidance on unsafe results.
Abandoning an old well
An abandoned well includes one permanently out of use, uncompleted, too deteriorated to use practically, or a threat to groundwater, health or safety. Dry holes also need proper closure. Under R 325.1662(1), the owner or a registered well drilling contractor can generally plug an abandoned well or dry hole. On a property with a well serving the public or a residence other than the owner’s residence, a registered contractor must plug the abandoned well. Under R 325.1669, the owner is generally responsible for plugging unless a written contract provides otherwise or the agency determines that a registered contractor improperly located or constructed the well.
R 325.1663–.1665 govern the methods and materials. The choices depend on the bore and geology. For example, bedrock sections require neat cement or concrete grout, and dug or crock wells have a separate permitted method. The person who plugs it submits the report to the department or local health department within 60 days under R 325.1675. Document the location, depth, diameter, and procedure, materials and quantities used. A well abandoned when municipal water is installed must be plugged. Check with the utility and health department before retaining an old well for a separate approved use and protect the supplies from cross-connection.
The contractor's coordination checklist
- Draw it before you dig it. Put the well, septic tank, drain field, reserve area, easements, setbacks, and driveway on a scaled plot plan first, then measure every isolation distance. The state well code sets no well-to-property-line distance; check the local sanitary code and any applicable zoning setback separately.
- Sequence the trades. The rig needs a level pad and clear access, and it makes a mess. Drilling before foundation excavation is common, but the casing then has to be protected from every trade that follows.
- Protect the casing. Stake or flag it, keep equipment off it, keep the cap on, and never cut the casing below the 12-inch termination or use it to support a ladder, a sign, or other construction equipment.
- Close it out. Grade away from the casing, verify the pitless connection, install the sampling faucet, disinfect and sample, then record final distances on the as-built plot plan.
Worked scenario. For an existing 120-by-180-foot parcel outside the scope of the land division and subdivision rules, proposed location A is 42 feet from the tank, 57 feet from the field, 8 feet from the nearest building projection, and 6 feet from a buried Schedule 40 PVC gravity sewer with watertight joints. Apply the ordinary state rules with no deviation. A clears the field and building minima but fails the tank and sewer minima by 8 and 4 feet. A surveyed location B measures 56 feet from the tank, 63 feet from the field, 12 feet from the nearest building projection and 14 feet from that same qualifying sewer. B passes all four comparisons. Before staking B, confirm the reserve field separation, the recorded easements, other potential contamination sources, local limits, grading and drill access. If a stricter local sewer clearance applies, B still needs another revision or a formal approval allowed under the governing rules. For covered developments of less than one acre or subdivisions, R 560.410 bars reductions of minimum casing depth or isolation distances through the R 325.1613 deviation process.
Under R 325.1622, what is the ordinary minimum horizontal isolation distance from a private water well to a septic tank or subsurface disposal field, before any local increase or written deviation?
50 feet
25 feet
100 feet
10 feet
For an ordinary drilled well with no approved exception, what minimum height above the ground surface does R 325.1632 require for the casing?
2 inches
6 inches
12 inches
36 inches
A homeowner’s own residence is the only one served by the wells on the property. One of the wells is permanently abandoned. There is no applicable local restriction, written contract or agency finding about improper construction. What does Michigan’s well code allow?
Leave it in place with a loose cap
The owner can plug it in compliance with the code or arrange for a registered well drilling contractor to do so
Only the local health department can plug it
Any registered pump installer can plug it based on that registration alone