9.2 Project Inspections
Key Takeaways
The permit holder or agent gives notice when work is ready. The requester provides access and the means to inspect under R109.3.
R 408.30509 gives separate readiness rules for frame and masonry work. Coordinate rough approvals and the visibility of flashing with the enforcing agency.
Under amended R109.4 obtain approval before advancing. Correct cited noncompliance and keep that work exposed until cover is authorized.
Approved outside reports need the qualifications and certification addressed by R104.4 and R109.2. The building official determines whether to accept them.
Apply the agency’s inspection request procedure and MCL 125.1513’s separate final-inspection notice. Follow the approved certificate or temporary certificate for occupancy.
Who inspects, and under what authority
The enforcing agency periodically inspects permitted construction under MCL 125.1512. Michigan’s 2015 Residential Code and amendments remain in effect under LARA’s stated court-order status. Rule 500 excludes the model R109.1 introduction. Use the individual inspection provisions and Michigan’s amendments.
Under R109.3, the permit holder or agent requests an inspection when the work is ready. The requester provides access and the means to inspect. Michigan Rule 509a replaces R109.4. Obtain approval before advancing beyond the inspection point. If the official finds noncompliance, the notice identifies the code chapter and section in writing. Correct the cited condition and keep the affected work exposed until the official authorizes cover.
The inspection sequence
Use the approved plans to identify the inspection points. Work backwards from the next activity that would conceal the work or depend on its approval.
| Hold point | Evidence to have ready | Release needed before |
|---|---|---|
| Foundation under R109.1.1 | Excavation or set poles or piers, required forms and supported reinforcement, including applicable thickened slab work | Placing concrete |
| Pre-backfill or under-slab check if required | Expose the applicable drainage, protection, reinforcement or rough services required for that check | Concealment by fill or concrete |
| Plumbing, mechanical, gas and electrical rough-ins under R109.1.2 | Required rough work and applicable tests | Concealment, fixture or appliance installation, and framing inspection. See the tested ground-source loop exception. |
| Frame check under Rule 509 | Roof, framing, firestopping, draftstopping and bracing in place, with rough plumbing, mechanical and electrical approvals | Advancing beyond the frame inspection and covering work |
| Masonry check under Rule 509 | Base-course flashing, R703.2 water-resistive barrier and completed masonry | Release of the applicable masonry inspection |
| Energy checks | Applicable installed insulation, fenestration, air controls and supporting documents | Application of interior finishes for the envelope inspection |
| Final under R109.1.6 | Completed permitted work and applicable equipment tests and sign-offs | Occupancy, subject to the certificate rules |
Rule 509 retains the older flashing citation R703.7.5. Use R703.8.5 for the anchored veneer flashing details in the 2015 code. Coordinate any needed verification of visible work with the agency. For example, Macomb Township’s new-residence list calls for 24 hours’ notice and separately lists basement backfill, concealed insulation and brick flashing and weeps. Record these agency-specific requirements separately from the code’s general inspection rules.
Third-party and special inspections
R104.4 authorizes the building official to accept reports by approved agencies or individuals. Such a report must be written and certified by a responsible officer of the agency or the responsible individual. R109.2 addresses the qualifications and reliability of an approved inspection agency. Arrange acceptance before relying on outside evidence. File the report and confirm the permit inspection has actually been released before covering the work.
If an engineered residential element needs an additional check, review the approved plans, applicable code or design standard and permit requirements, including the official’s R109.1.5 authority. An approved outside report under the MRC is a different process from building-code Chapter 17 special inspections and tests. For a project governed by the Michigan Building Code, check its Chapter 17 scope and exceptions, the required statement where applicable and the approved agency’s reporting duties.
Certificates of occupancy
Michigan Rule 510 and MCL 125.1513 require the applicable certificate before occupancy of a new home. The statute permits an existing use that continued during alteration to continue for 30 days after completion. Under amended R110.3, the certificate records the permit, address, portion covered, inspection for code compliance, official, code edition and special conditions. When the building is entitled to the certificate, the agency issues it within five business days after receiving the prescribed written application and fee. For the final inspection pursuant to that application, the enforcing agency gives the owner or agent at least 12 hours’ notice. The permit holder’s call to request the inspection follows the separate R109.3 and local scheduling process.
Under R110.4 and MCL 125.1513, the holder can request a temporary certificate for compliant, safely occupiable portions and the official sets its duration. Under R110.5 the official suspends or revokes a certificate in writing if it was issued in error or based on incorrect information, or where a violation is found. Under R111.1 the building official must approve regulated service connections for which a permit is required, subject to temporary connection authority in R111.2.
Scheduling inspections without losing days
Schedule the agency’s request lead time, inspection and release as separate dependencies. Stage access. Keep the permit or copy and the reviewed site set available under R105.7 and R106.3.1. Keep code-required installation instructions available at inspection under R106.1.2. If an issued permit approaches 180 days without start or after suspension or abandonment, consult R105.5 and request a justified extension in writing before relying on the permit.
Correcting failed inspections
For example, the frame inspector finds required draftstopping missing over a dropped ceiling. Keep the work open, review the cited details and code, complete the correction, and request reinspection. Avoid committing drywall labor until the official’s approval. Record the notice, correction, photographs and release in the inspection file.
Check the applicable agency fee schedule under MCL 125.1522. For instance, Macomb Township’s posted schedule distinguishes a visit for work that is unready, the first reinspection of a cited violation and additional visits. An agency fee and the parties’ allocation of correction costs under the subcontract are separate questions. No single fee or cost allocation follows automatically from Rule 509a.
Documenting inspections for draws and disputes
Keep three checks in the project file. First, the enforcing agency checks compliance for the permitted work. Second, the contractor checks contract quality and readiness, including details that may later be concealed. Third, a lender’s draw review, when required by the financing agreement, verifies payment milestones under that agreement. Retain dates, sign-offs, photographs, correction and reinspection records, accepted outside reports and occupancy documentation. Link each draw to its own contract milestone and the applicable sworn statements and waivers.
Under the Michigan amendment at R 408.30509, when is the work ready for the frame inspection?
As soon as the wall framing is standing, before trusses are set, so corrections cost less
Only after drywall is hung, because the inspector must see the finished assemblies
After the roof, all framing, firestopping, draftstopping, and bracing are in place and after the plumbing, mechanical, and electrical rough inspections are approved
After the final electrical inspection, because rough trade approvals are not a precondition for framing approval
A frame inspector cites missing required draftstopping above a dropped ceiling. What does Michigan’s amended R109.4 require?
Correct the item, leave it exposed, and obtain authorization before proceeding beyond that inspection point or covering the work
Cover the area and disclose the correction on the next permit application
Appeal to the local board of appeals before making any correction
Continue with insulation and drywall, because a failed inspection only affects the final certificate