48.2 Faced vs Unfaced Batts

Key Takeaways

  • An unfaced batt has no integral facing. Use the facing’s tested permeance or the applicable code example to identify vapor-retarder class.

  • Michigan follows R601.3 as amended. Interior Class I or II is the general frame-wall rule in Zones 5 through 8 and Marine 4. Check the listed exceptions.

  • Recheck drying and material permeance before adding a layer. Select floor, roof and below-grade details for their specific settings.

  • A compliant standalone vapor-control layer can be combined with unfaced batts. Use an unfaced attic overlay where vapor control is already in place below.

  • Fit the batt around obstructions and preserve the separate air barrier. Follow the facing exposure and installation instructions.

Last updated: November 2026

Faced Batts and Vapor Control

A faced batt has a bonded surface layer. Kraft and foil-based facings are common. Some have side flanges for attachment. Identify the facing, its tested permeance and the intended exposure from the label or approved assembly. An unfaced batt supplies thermal resistance without that separate facing. The facing and the air barrier perform different functions. Continuity at air-barrier joints and openings still needs its own detail.

Under R202, vapor-retarder classes are based on the desiccant procedure of ASTM E96. R702.7.2 allows the manufacturer's certified test or a tested assembly and identifies these materials by class.

ClassWater vapor permeanceCode examples
I0.1 perm or lessSheet polyethylene or unperforated aluminum foil
IIGreater than 0.1 through 1.0 permKraft-faced fiberglass batts
IIIGreater than 1.0 through 10 permsLatex or enamel paint

Michigan enforces R601.3 as amended by Rule 522a. Interior Class I or II is the general rule for frame walls in Zones 5 through 8 and Marine 4. If the design uses kraft as that Class II layer, the kraft faces the interior. Table R702.7.1 provides assembly-specific alternatives. Below grade, the rule permits interior Class III or no interior retarder and allows interior Class I or II when the assembly has no air-permeable insulation. The rule also excepts construction where moisture or freezing will not damage the materials.

How to Decide

In cold weather, outward diffusion can carry vapor toward cold sheathing. Interior vapor control can reduce that movement. Air leakage and bulk water need separate control details. Several layers can affect drying, including sheathing, continuous insulation, membranes and coatings. Decide from their permeance and arrangement before adding kraft, foil or polyethylene. A low-permeance exterior layer can reduce outward drying. An interior low-permeance layer can then limit inward drying too.

Select Faced or Unfaced for the Assembly

SituationSelection to verifyReason
2×4 exterior frame wall, Zone 5A, interior Class II chosenA kraft-faced batt may provide Class II, facing inside. For the R-13 cavity path, include the separate R-5 continuous layer or qualifying insulated siding.Confirm the vapor design and the energy component value separately.
Wall with a separate compliant variable-permeance membraneUnfaced batts sized to the cavity, with the membrane installed as specifiedChoose the membrane from its tested class and intended drying behavior.
Second attic layer where vapor control already existsAn unfaced layer over the joists where the design permits itThe added layer can cover bridging and seams without introducing another facing.
Below-grade framed wallApply Rule 522a for the entire assemblyClass III or no interior retarder is permitted. Class I or II has the stated air-permeable-insulation restriction.
Floor above a vented crawl space or garage, or a vented sloped ceilingSelect the facing under the approved floor or roof moisture detailThe frame-wall facing rule does not decide these details. Check contact or ventilation and fire separation as appropriate.

Worked Choice in Zone 7

A 2×6 above-grade wall has unfaced R-21 insulation and no interior retarder. Assume no exception applies and that the wall design can dry outward. An interior coating certified Class II, installed as tested, can satisfy vapor control without replacing the insulation. Kraft-faced batts oriented inward could also provide the Class II layer. Ordinary latex paint is a Class III example. If the wall instead uses the continuous-insulation branch of Table R702.7.1 for a Class III interior, the ordinary Zone 7 threshold over 2×6 framing is R-15, subject to the table footnote. That class decision is separate from the energy-code calculation.

Installation Checks

  • Cut batts around electrical boxes and split the material around wiring where needed to fill the thermal cavity, following Michigan Table N1102.4.1.1. Seal penetrations at the air barrier separately.
  • Keep the facing in the location shown in the design and fasten or support it as the product instructions require. Repair tears with the facing system's compatible method.
  • Follow the exposure rating. For example, Owens Corning's EcoTouch R-38C instructions require the combustible kraft facing to be covered and in substantial contact with the finish. Observe equipment, flue and lighting clearances applicable to that assembly.
Test Your Knowledge

Under the 2015 MRC R202 definitions, what perm range makes a material a Class II vapor retarder?

A

0.1 perm or less

B

Greater than 0.1 up to 1.0 perm

C

Greater than 1.0 up to 10 perms

D

Anything above 10 perms

Test Your Knowledge

A crew is adding a second batt layer over an attic floor with its vapor control already in place below. Which option adds insulation without introducing another facing?

A

Kraft-faced batts laid flat with the facing down on the old insulation

B

Foil-faced batts rolled out with the facing up

C

Facing direction is irrelevant in attic floors, so use whatever is cheapest

D

Unfaced batts laid perpendicular to the joists

Test Your Knowledge

A Michigan above-grade frame wall uses kraft facing to provide its required interior Class II vapor retarder. How should the batt be installed?

A

Facing toward the interior, attached as directed by the batt manufacturer

B

Facing toward the exterior sheathing

C

Either direction, since the facing is only manufacturer packaging

D

Facing torn off and the batt installed unfaced

Sections you finish are checked off in the contents.