24.3 Submittals & Construction Documentation

Key Takeaways

  • 2015 MRC R106.1.2 requires code-required manufacturer installation instructions to be available at the worksite at inspection.

  • Under Michigan Rule 506 a truss design data sheet may substitute at permit application. The building official must approve the full truss design drawings before installation, and the drawings must accompany delivery.

  • R106.4 requires resubmission of changes that depart from approved construction documents. Under R106.5 the building official retains an approved set for the stated post-completion period, subject to applicable law.

  • Follow the project’s defined review dispositions. Verify submittal details and deviations, and obtain the applicable authorization for a substitution or change before releasing affected work.

  • Maintain linked records of submissions, decisions, actual work and closeout. Daily logs may help prove dates but the applicable notices, claims and payment steps are separate.

Last updated: November 2026

24.3 Submittals & Construction Documentation

A permit submittal enables the enforcing agency to review code compliance. A contractor’s shop drawing, product sheet or sample shows how the contractor proposes to meet part of the contract. A project may require both, with separate recipients and approvals. Retain the approved version used for procurement and the actual installed record.

Where the code requires documents

For the current residential setting, check the adopted construction document provisions with the Michigan amendments.

  • R106.1 and R106.1.1. Submit the construction documents and other requested data with the permit application, subject to permitted waivers. Drawings must show the nature, location and extent of the work and enough detail for code review. Apply the jurisdiction’s requirements and applicable law for a registered design professional.
  • R106.1.2. Make code-required manufacturer installation instructions available at the worksite at inspection. Keep the revision for the actual product accessible to the crew and inspector.
  • Michigan Rule 506. Under amended R106.1.4 an applicant may submit the truss design data sheet in Figure R802.10.1 with the permit documents instead of full truss design drawings at that stage. Under amended R802.10.1 the building official must approve the drawings before installation, and the drawings must accompany the shipment to the site. Check the required geometry, bearing widths, applicable design loads, reactions, connectors, lumber and permanent member restraint information.
  • R106.3.1, R106.4 and R106.5. Keep the approved construction documents available at the jobsite. Resubmit changes that depart from them as amended construction documents for approval. The building official’s retention period for an approved set is generally at least 180 days after completion of the permitted work, or as required by state or local law.

What actually needs a submittal

Read the contract, the approved permit set and applicable rules to determine what to submit and who reviews it. The following are common categories. The required package varies with the job.

  • Structural. Truss design drawings, product data or details for engineered joists and beams, connector identification and an approved repair detail for any proposed structural repair.
  • Envelope. Window schedules and NFRC data, egress and safety glazing evidence where applicable, roofing and siding instructions, flashings and compatibility data.
  • Mechanical and energy. Equipment model data, matched system ratings where required, and load, equipment selection, duct or ventilation documents as specified or required.
  • Finishes. Tile and setting material data, paint and finish selections, flooring instructions, cabinetry dimensions and samples. Include the emissions or environmental documentation if specified.
  • Voluntary programs. Submit the checklists, product information and verification records the applicable program requires.

Product data identifies the proposed model, ratings and installation limits. Shop drawings communicate project-specific fabrication, dimensions and interfaces. Samples show the proposed finish, and a mock-up demonstrates a detail or workmanship. A mock-up sets an acceptance benchmark when the contract makes it one. None of these replaces the installer’s check of substrate, dimensions and adjacent work.

A sample submittal register

A register tracks the spec or drawing reference, current revision, responsible party, review duration, needed response, procurement lead time and status. The entries below illustrate project-specific release targets and review periods in working days. Dependencies for permit approval or installation still apply.

ItemSubmittalNeeded release or responseReview allowanceCurrent disposition
Roof trussesShop drawings, design drawings and supporting dataBefore committed fabrication release10 daysApproved as noted
Wood I-joists and LVLLayout and product dataBefore framing stock release10 daysApproved
Windows and sliderProduct data, rough openings and NFRC ratingsWorking day 50 to meet day 80 installation7 daysRevise and resubmit
Asphalt roofingProduct data and installation instructionsBefore material procurement5 daysApproved
Furnace and heat pumpSpecified system data and equipment selectionBefore mechanical rough-in procurement7 daysApproved as noted
Housewrap and flashingsCompatible product data and transition detailsBefore envelope work3 daysApproved
Interior coatingProduct and specified emissions evidenceBefore finish procurement3 daysRevise and resubmit
CountertopsTemplate verification and samplesBefore fabrication7 daysApproved

If window lead time is 30 working days and installation starts on day 80, release by day 50. One seven-day review requires submission by day 43. Allowing a first review of seven days, two days to revise and seven more to review moves the first submission to day 34. An unexpected product change or slower response shifts these dates unless another dependency can change.

Review statuses, responsibility and changes

Example dispositionAction under the project’s stated procedure
ApprovedRelease only after satisfying applicable procurement and installation holds. Keep the reviewed version.
Approved as notedIncorporate the notes and proceed only as the disposition authorizes. Return a corrected record or resubmit for review if the project procedure or review requires it.
Revise and resubmitCorrect and return for the required review. Hold the affected release.
RejectedCorrect the nonconforming proposal or submit an authorized alternate through the required process.
Submit specified itemProvide the specified item or separately request approval for a substitution.

The contract governs the labels and authority. For example, under AIA A201–2017 §§3.12.4–.9 and 4.2.7, the contractor reviews and approves the submission before forwarding it. The contractor verifies field measurements, materials and coordination under the contract, and the architect’s review addresses conformance with the design information and concept. Required work waits for the required approval. The contractor remains responsible for its own errors or omissions and retains its means, methods and safety duties. Where delegated design is required, follow the stated performance criteria and licensed design requirements under §3.12.10.

Identify a proposed substitution or deviation openly. In the A201 example, the contractor specifically identifies a deviation when submitting. For a substitution under §3.4.2, obtain the owner’s consent after the architect’s evaluation and use the change order or construction change directive procedure, subject to the architect’s minor-change authority under §7.4. A deviation still needs the written authorization applicable to it under §3.12.8. Approval of the submittal alone creates no adjustment to price or time. Disclose additional changes on a resubmission. Separately obtain any necessary permit amendment for a change to the approved code documents.

RFIs: what qualifies and how to write one

Use a request for information (RFI) to seek a written clarification or interpretation of a discrepancy or missing detail. Examples include a mismatch between header information on the plan and in the schedule, missing roof-wall flashing at an addition, or a field dimension that conflicts with the drawing. Report concealed or differing conditions through the separate notice process when required. Use the substitution and change procedures when asking to depart from the contract.

Number and date the request, identify the drawing or specification and actual field condition, ask one clear question and show the response date required by the schedule. If proposing an option, identify it and any known impact. Log the response and confirm the applicable authorization before proceeding. The effect of a written interpretation depends on the contract. If the response changes scope or creates a price or time issue, give any required notice and use the applicable change procedure.

Logs, minutes and change documentation

Record dates, workers and work areas, weather, deliveries, inspections, relevant conditions, direction received, delays and linked photos in a contemporaneous log. These records help establish facts for change and delay matters, or dates relevant to a lien. They do not by themselves establish entitlement. Keep proof of the separate required notices and filings. Michigan notice-of-furnishing and claim-of-lien requirements have different triggers, recipients and exceptions under MCL 570.1109 and .1111.

Record meeting decisions, responsible parties and due dates. Distribute minutes promptly and flag errors or disputed instructions in writing. Use the contract’s authority and notice requirements to determine the effect of an entry.

Link the RFI or site condition, scoped proposal, schedule and price effects, applicable written authorization and current drawing. Check the contract’s distinction between signed change orders, directives and minor changes. Michigan residential work can also carry separate written-contract and written-change requirements. Keep RFIs, approvals and change records with the current documents so the field can identify the authorized scope.

As-builts, O&M and warranties

Record drawings show what was actually built, especially concealed work such as routed services, shutoffs, framing changes and insulation details. Distinguish an authorized revision from an observed deviation. Submit the record drawings required by the contract while the details can still be verified.

Provide required operating and maintenance information, warranties, equipment identifiers and finish care documentation. Record warranty registration if the applicable warranty calls for it. Identify any requested spare shingles, tile, siding or paint by product and location. Check the handoff requirements before promising a particular warranty or supply of materials.

Confirm the applicable closeout requirements. A project may call for final inspections and any occupancy certificate, record documents, approved submittals, O&M manuals, warranties, spare materials and payment documentation. Use the correct sworn statement and payment-based waiver procedures when applicable. Keep the retained project records separate from the enforcing agency’s code retention duty.

Exam traps

  • At truss delivery, check the required drawing package. Hold installation until building-official approval.
  • Read review notes and disposition before procurement. Track the time to correct and resubmit.
  • Identify changed assumptions in writing and separate a clarification from a change authorization.
  • Record dates and approvals for concealed work while they can be checked.
  • Preserve required drawings, warranty conditions and payment records for closeout.
Test Your Knowledge

At permit application the builder submitted Michigan’s permitted truss design data sheet. Trusses arrive before the building official approves the full truss design drawings. What must the builder verify?

A

The permit data sheet is enough to install the trusses.

B

The manufacturer’s delivery ticket substitutes for the design drawings.

C

The full design drawings accompany the shipment. Obtain building-official approval of those drawings before installing the trusses.

D

The builder can install the trusses if a site supervisor approves the layout.

Test Your Knowledge

The project’s written procedure says “approved as noted” authorizes release with the stated corrections and requires resubmission only when specifically requested. A window package has that status. The notes clarify the specified finish, with no change to price, time or permit documents, no resubmission direction and no other release hold. What may the contractor do?

A

Order the windows exactly as first submitted without applying the notes.

B

Incorporate the finish notes and order the matching windows under the stated procedure. Keep the reviewed version for the record.

C

Treat the review as a rejection and order an alternate manufacturer.

D

Issue a price change based solely on the review stamp.