46.4 Reroofing
Key Takeaways
In the 2015 MRC, reroofing lives in Section R908 (R907 covers rooftop-mounted photovoltaics): roof replacement means removing existing layers down to the roof deck (R908.3), while roof re-cover installs a new covering over the existing one (R908.3.1).
R908.3.1.1 prohibits re-cover over a water-soaked roof or covering, a base made inadequate by deterioration, slate or the listed tile types, or two or more existing applications. One sound asphalt layer still needs an applicable R908.3.1 route and a compliant assembly.
R908.3's exception lets an ice-barrier membrane already adhered to the deck remain in place under a new membrane during replacement; all reroof flashings must be reconstructed per approved manufacturer's instructions, and metal flashing that will receive bituminous materials must be primed first (R908.6).
R908.2 requires adequate structural capacity for the covering and installation loads. If re-covering wood shingles or shakes creates a combustible concealed space, R908.4 requires an approved, securely fastened protective covering over the entire existing surface.
Ordinary repairs are permit-exempt under MCL 125.1510(7) and R105.2.2. Verify the permit for the planned reroof with the enforcing agency. Check the separate energy-code exceptions in Michigan N1101.3.1.
The 2015 MRC puts roof replacement and roof re-cover under R908. The choice begins with the condition and number of existing coverings, the structural loads, and an approved installation detail. R908.1 opens with the baseline — materials and methods used for re-covering or replacing an existing roof covering must comply with all of Chapter 9 — with two reroof-specific exceptions: roofs that provide positive drainage need not meet the 1/4:12 minimum design slope of Section R905, and such roofs need not have secondary (emergency overflow) drains or scuppers added.
The Two Operations (R908.3 and R908.3.1)
Roof replacement is the tear-off: removal of existing layers of roof coverings down to the roof deck. Its exception is narrowly practical — where the existing assembly includes an ice-barrier membrane adhered to the deck, that membrane may remain in place and receive a new membrane over it, rather than being scraped off the sheathing. Roof re-cover is the overlay: a new roof covering installed over the existing one. R908.3.1 permits it in four situations: where the new covering is installed per the roof covering manufacturer's approved instructions; where a complete and separate roofing system (a standing-seam metal system, for example) transmits loads directly to the structure without relying on the old roof; where metal panel, metal shingle or concrete/clay tile goes over an existing wood shake roof per R908.4; and where a new protective coating is applied over spray polyurethane foam roofing.
The Re-Cover Prohibitions (R908.3.1.1) — Learn All Three
R908.3.1.1 forbids a re-cover where any of these exists:
- The existing roof or covering is water-soaked, or deterioration makes it an inadequate base for another covering.
- The existing roof covering is slate, clay, cement or asbestos-cement tile.
- The existing roof has two or more applications of any type of roof covering.
For a conventional shingle overlay, two existing applications end the re-cover inquiry. One sound layer can be evaluated against R908.3.1 and the rest of the assembly requirements. Suspected asbestos-cement requires evaluation under applicable worker-protection and environmental rules before disturbance.
Decision Table: Tear-Off or Overlay?
| Condition found at inspection | Correct operation | Code basis |
|---|---|---|
| One adequate asphalt-shingle layer | Evaluate manufacturer-approved re-cover, structure and all new-assembly details | R908.2, R908.3.1 and R908.3.1.1 |
| Two or more existing applications | Tear-off mandatory | R908.3.1.1(3) |
| Water-soaked roof or covering, or deterioration that makes the base inadequate | Re-cover prohibited | R908.3.1.1(1) |
| Existing slate, clay, cement or asbestos-cement tile | Tear-off mandatory (environmental handling for ACM) | R908.3.1.1(2) |
| Structural capacity is inadequate or unknown | Establish and restore capacity as needed before loading or covering the roof | R908.2 |
| Wood shakes proposed as the base for eligible metal or clay/concrete tile | Check R908.3.1(3). Protect the entire old surface with an approved lining if a combustible concealed space is created. | R908.3.1(3), R908.4 |
| Required ice barrier cannot be provided in the proposed overlay detail | Redesign the work so the required barrier has a compliant substrate, extent and laps. Replacement can expose a suitable deck. | R904.1, R905.1.2, R908.1 and R908.3 |
| Slate, clay or cement tile removed for reuse | Reinstall sound pieces only. Replace rusted, damaged or deteriorated flashings, edgings and similar devices. Do not reinstall aggregate surfacing. | R908.5 |
An overlay proposal still has to show how the eaves, valleys, flashings and fasteners will comply. Check the roof covering instructions and the actual warranty terms before offering re-cover as an option. Replacement exposes the deck for inspection and makes it possible to install a new barrier at the deck. R908.3 also permits a qualifying adhered membrane to remain beneath a new one.
What a Compliant Reroof Includes
- Deck inspection and repair. Replacement exposes the deck: sheathing is checked for rot, delamination and nail withdrawal, and deteriorated panels are replaced before underlayment. Before re-cover, verify the base and the roof structure, including concealed conditions using records, underside access or openings as needed. An inadequate base rules out re-cover. Address unsafe decking before access or staging.
- Fastening through the existing layer. On the overlay path, new fasteners must still meet R905.2.5 — through the new shingles and at least 3/4 inch into the sheathing, or through thin sheathing entirely — which over an existing layer means longer nails per the manufacturer's approved instructions. Short nails that seat in the old shingle, not the deck, are the classic overlay failure.
- Ice barrier upgrade. Provide the required R905.1.2 eave protection and the separate specified valley lining. For replacement, a qualifying adhered ice-barrier membrane may stay beneath the new membrane under R908.3. Review the eave substrate and laps on any re-cover proposal.
- Drip edge and flashings. R908.6: reconstruct flashings per approved manufacturer’s instructions and prime metal before applying an adhering bituminous material. R908.5 requires replacing deteriorated flashing and edging. Apply the R905.2.8.5 edge details to the new shingle assembly.
- Ventilation adequacy. The reroof is the moment to verify attic net free ventilating area against R806 (see Section 47.3 for the 1:150 rule and the two qualifying 1:300 layouts) and to cut in intake or exhaust where bath fans, additions or prior re-roofs left the attic unbalanced — ice-dam prevention depends on it.
- Weight. An asphalt-shingle layer adds a meaningful dead load (commonly in the low pounds per square foot, rising with heavier architectural lines); doubling the shingle layers roughly doubles that share of the roof load, and R908.2 requires the structure to carry the finished system plus the installation loads before the first bundle lands.
- Permits. MCL 125.1510(7) and R105.2.2 exempt ordinary repairs. Check whether the planned scope requires a permit with the enforcing jurisdiction. Grand Rapids, for example, requires a residential reroof permit. MCL 339.2403(f) is a separate license provision for an undertaking with an aggregate contract price below $600, counting labor, materials and other items. Determine permit requirements independently.
Energy and Waste Scope
Michigan’s amended N1101.3.1 covers the altered work. If energy use does not increase, it exempts reroofing outside the thermal envelope and reroofing within it where neither the sheathing nor insulation is exposed. Verify the thermal boundary before pricing roof insulation. These energy exceptions do not change Chapter 9 roof-covering requirements.
Estimate removed material by weight, plus fasteners, flashing and damaged deck material. Confirm the container limit and where the hauler can accept the waste. Screen suspected asbestos-containing materials before disturbing them and use the appropriate handling and disposal route. Protect walls and landscaping, contain removed material and collect loose fasteners.
Worked Scope Comparison: Tear-Off vs Overlay (15-Square Job)
Compare the same 1,500 ft² of roof surface on both bids. The existing assembly has one asphalt layer, and the deck appears sound. The selected shingle can be used for a re-cover only after confirming the required eave barrier, substrate, edge details, flashings, fasteners and structural capacity.
| Quantity or check | Replacement | Re-cover if eligible |
|---|---|---|
| New shingles at an assumed 10 percent field allowance | 1,650 ft², or 16.5 squares before package rounding | Same assumed field quantity |
| Existing shingles removed | 15 squares. At a measured or documented 220 lb per square for this example, allow 3,300 lb of old shingles plus other debris. | No full field removal. Include preparation and locally removed material. |
| Deck and attachment | Expose deck, verify condition, price needed repairs and confirm deck penetration | Verify deck condition and size fasteners to penetrate through both coverings into or through the sheathing as required |
| Eave and valley protection | Measure from the approved barrier and lining details | Verify the approved detail can provide the required protection before accepting re-cover |
| Staging loads | Check the complete new system and installation loads | Include the retained layer and new system plus installation loads |
The saving on eligible re-cover comes mainly from avoiding full removal and related handling. Quote product-specific underlayment, accessory and warranty terms for each method. If the approved eave, base or load checks cannot be satisfied for re-cover, revise the scope before pricing it as eligible.
Exam Traps
- Citing R907 for reroofing. In the 2015 MRC, R908 is Reroofing; R907 is rooftop photovoltaics.
- For a conventional shingle re-cover, two existing applications bar a third under R908.3.1.1(3). Added fasteners or a favorable dead-load check do not satisfy that rule.
- Re-covering over slate, clay, cement or asbestos-cement tile — prohibited by R908.3.1.1(2) regardless of condition.
- "Overlay lets you skip the deck check." The base-adequacy prohibition (R908.3.1.1(1)) and the structural-load rule (R908.2) apply before any overlay is bid.
- Forgetting R908.6's priming requirement for metal flashing that will receive bituminous materials, or assuming old flashing may simply be relapped.
- Mixing up the $600 MCL 339.2403(f) licensure exemption with a permit exemption — different statutes, different questions.
A bid proposes installing a new layer of asphalt shingles over a roof that already carries two applications of roof covering. Under MRC R908.3.1.1, the re-cover —
is not permitted: an existing roof with two or more applications of any type of roof covering must not receive another, so tear-off to the deck is required
is permitted once the building official approves the added dead load in writing
is permitted if six fasteners are used per shingle
is permitted when the new shingles are heavier architectural laminates
During a tear-off replacement the crew cleans the old sidewall flashing and plans to relap it. What does the 2015 MRC require instead?
The flashing may be reused as long as it shows no visible rust
Only counterflashing must be replaced; step flashing is grandfathered
Flashings must be reconstructed in accordance with approved manufacturer's installation instructions, and metal that bituminous materials will adhere to must be primed before installation
A second layer of metal must be soldered over the existing flashing