20.3 Survey Plans & Symbols
Key Takeaways
A survey sheet is read from its legend, north arrow, and scale; symbols are not universal, so the legend on that drawing - not memory - defines each mark and the north arrow may reference true, magnetic, or assumed north.
Contour interval is the vertical distance between contour lines; closely spaced contours mean a steep slope, and a 2-foot interval over 25 feet of horizontal distance is an 8 percent slope.
A benchmark is an identified mark of known elevation, referenced to the stated project or geodetic datum. Use that vertical reference for grades and a confirmed boundary monument for parcel layout.
Read easement terms and required clearances from the governing documents, the survey and applicable ordinances. A property line, zoning setback and utility easement answer different layout questions.
MCL 460.725 sets the ordinary MISS DIG notice window at least 72 hours and at most 14 calendar days before excavation, with statutory business-hour rules. Check positive response and use soft excavation in the statutory caution zone as required.
20.3 Survey Plans & Symbols
Identify what the drawing establishes before using it. A certified boundary survey identifies surveyed lines and monuments. A design plot plan uses the boundary information and shows proposed work. The easement instrument establishes the terms of the right, and the legend tells the crew how to read the marks and features on the sheet.
The drawings you will actually use
| Drawing | What it establishes | Typical use on a residential job |
|---|---|---|
| Boundary survey | Property lines, corners, monuments, area, encroachments | Verify lot lines and setbacks before layout |
| Topographic survey | Existing ground elevations, drainage, vegetation, utilities | Grading, drainage, cut and fill, septic siting |
| Plot plan / site plan | House, driveway, well, septic, reserve area, setbacks, easements | Permit submittal and construction layout |
| ALTA/NSPS land title survey | Boundary and evidence of improvements, easements, access and other title-related features under the ALTA/NSPS standard, effective February 23, 2026 for the current edition | Commercial and lender work; more detail than a residential plot plan |
| As-built survey | What was actually built, with elevations and distances | Closeout, future permits, well and septic records |
| Mortgage inspection | A rough sketch prepared for a lender | Not a boundary survey; never rely on it for layout |
Reading the frame of the sheet
Start with the title block, date, revision, property identification, surveyor details and scales. A Michigan certified survey map under MCL 54.213 carries the surveyor’s seal and signature, written and graphic scales, a legal description and oriented north arrow. Then find the north arrow and read the note beside it - true, magnetic, or assumed north changes how you rotate the plan onto the ground. A graphic scale can still be read on a proportionally reduced or enlarged view because the bar is reproduced along with the geometry. The original numeric ratio no longer applies after resizing. The legend defines every symbol on that sheet, and symbols are not universal. A circle on one plan is a manhole; on another it is a well; on a third it is a valve.
Elevations, contours, and benchmarks
- Spot elevation: a point with a known elevation, printed as a number such as 812.4 beside a small cross or dot. It describes one point only.
- Contour line: a line connecting points of equal elevation. The contour interval is the vertical distance between adjacent contours - commonly 1, 2, or 5 feet - and is stated in the legend or a note.
- Index contour: a heavier labeled contour, often every fifth line under a particular mapping convention, so you can count up or down without tracing every line.
- Hachures: short tick marks on the inside of a closed contour indicate a depression rather than a hill.
- Drainage: contours bend into a V pointing uphill along a swale or stream, and water flows the other way.
- Benchmark (BM): an identified physical mark of known elevation on a project or geodetic datum such as NAVD 88, shown with its elevation (BM 800.00). A benchmark establishes vertical control. A corner monument establishes a boundary location. If a monument serves both roles, the respective boundary and elevation information must be documented.
Slope comes directly from contour spacing. If the contour interval is 2 feet and two contours are 25 feet apart on the ground, the slope is 2 / 25 = 0.08, or 8 percent. Contours packed tightly mean a steep slope; widely spaced contours mean a flat area.
Property lines, easements, and setbacks
- Property line: the boundary of the legal parcel, usually a solid or heavy line with bearings and distances, curve data for curved frontages, and monument calls at the corners (for example, a 5/8-inch rebar with a cap). On a platted lot the plan may show only lot and block dimensions tied to the recorded plat.
- Easement: a right held by someone else to use part of the property - utility, drainage, or access. It is drawn as a dashed boundary or a hatched band and labeled with its width and recording reference, such as a 20-foot utility easement. Read the recorded terms and verify clearances and approvals with the holder before placing paving, structures or landscaping that could affect access.
- Building setback line: a line offset from the reference named in the zoning ordinance, such as a property or right-of-way line. Check the measurement rule for the parcel and yard.
- Right-of-way line: the edge of the public street or road corridor. The property line and the right-of-way line are often not the same line.
Utility symbols on plans
| Symbol or label | Meaning | What it tells the crew |
|---|---|---|
| Solid line with circles at intervals | Water main with valves or fittings | Water service taps; keep excavation clear of the main |
| Circle labeled MH or SS | Sanitary sewer manhole | Sewer line; rim and invert elevations govern depth |
| Line labeled with invert elevations (INV 796.2) | Sewer or storm line with flow-line elevation at each structure | Check slope from inverts and run. Use the ground elevation and bedding detail to set trench depth. |
| Line labeled STM or with catch basins | Storm sewer and drainage structures | Keep footing drains and downspouts separate from sanitary |
| Line labeled G with a valve symbol | Gas main or service | Obtain a locate and expose marked facilities by soft excavation where required |
| Line labeled E, pole symbols, or transformer boxes | Electric distribution or service | Overhead and underground clearance limits |
| Line labeled TEL, CATV, or FIBER | Communications conduit | Often shallow and easily cut during grading |
| Small circle with W and an isolation radius | Water well on a plot plan | Check state and local separation to the tank, absorption area and the actual type of sewer line |
| Rectangle labeled with gallon capacity, plus a hatched field | Septic tank, distribution box, and absorption field | Tank size, field limits, and reserve area must match the permit |
Locate marks in the field follow the APWA uniform color code that MISS DIG 811 uses: white for proposed excavation, pink for temporary survey markings, red for electric, yellow for gas, oil, steam, petroleum or gaseous materials, orange for communications, blue for potable water, green for sewers and drain lines, and purple for reclaimed water, irrigation and slurry lines. Michigan's MISS DIG Underground Facility Damage Prevention and Safety Act (2013 PA 174, MCL 460.721 et seq.) requires the ordinary dig notice at least 72 hours and no more than 14 calendar days before the work. All hours on nonbusiness days are excluded from the 72-hour period, with statutory start-time rules for early or late notices. Check positive response. The marks are approximate. The caution zone extends 48 inches on either side of the marks, and MCL 460.725 requires soft excavation to expose marked facilities there, subject to its stated procedures and exceptions.
Scale: measuring without guessing
An engineer's scale converts paper to ground. At 1 inch = 50 feet, one inch on the sheet equals 50 feet of ground, so a 150-foot lot side is 3 inches long on paper. At 1 inch = 20 feet the same lot is 7.5 inches. Most residential plot plans are drawn at 1 inch = 20, 30, 40, or 50 feet; utility and topographic sheets are often 1 inch = 100 feet or smaller.
| Scale | 1 inch equals | 2.5 inches equals | 100 feet drawn as |
|---|---|---|---|
| 1 in = 20 ft | 20 ft | 50 ft | 5.0 in |
| 1 in = 30 ft | 30 ft | 75 ft | 3.33 in |
| 1 in = 40 ft | 40 ft | 100 ft | 2.5 in |
| 1 in = 50 ft | 50 ft | 125 ft | 2.0 in |
| 1 in = 100 ft | 100 ft | 250 ft | 1.0 in |
Two habits prevent expensive mistakes. First, work from the written dimensions. If conflicting dimensions, marked locations or plan requirements affect the work, have the designer or surveyor resolve the conflict. Paper can stretch, printers rescale, and a plan may carry a do-not-scale note. Second, for approximate measurements on a reduced copy, use the graphic bar for that view after checking that known lengths in both axes confirm proportional reproduction. Request a reliable dimension if the image is stretched or the scale is uncertain.
From survey data to excavation and utility layout
- Establish control. Verify the specified benchmark and have the surveyor resolve uncertain corners. Stake building corners using the approved layout and established control.
- Compute cut and fill. Calculate cut or fill by subtracting existing elevation from the design elevation of the same surface at the same point. If existing ground is 812.4 and the design subgrade at that point is 813.1, allow 0.7 feet of fill before adjustments for stripping or compaction. A finished floor at 814.0 provides a different reference because the slab and base intervene.
- Set utility grades from inverts. A sewer invert of 796.2 at the house and 794.2 at the main, over a 100-foot run, gives 2 feet of fall, or 2 percent - about 1/4 inch per foot. For the excavation bottom, subtract from the invert the thickness below the inside bottom of the pipe, including the wall and specified bedding. Trench depth is the ground elevation minus this excavation-bottom elevation at the same station.
- Locate before you dig. White-mark as required, place the MISS DIG notice, check positive response for the work, and follow the statutory soft-excavation procedure in each caution zone. Arrange separate verification of private service lines when they are outside the marking scope. Survey marks and locate flags are control, not scrap; protect them.
- Stop when the field disagrees with the plan. A sewer found at a different depth, a property pin out of position, or a contour that does not match the ground means a call to the surveyor before more soil moves.
Plot plan symbols for wells and septic
A residential plot plan is where well and septic requirements become geometry. Expect to see the well as a small circle or triangle labeled W, with the casing elevation; the septic tank as a rectangle labeled with capacity in gallons; a small square for the distribution box; the absorption field as a hatched or stippled rectangle with lateral lines and dimensions; the approved reserve area as a labeled dashed outline; and dimensioned or curved isolation lines from the well to the tank and field. Check that the initial and reserve systems clear applicable easements as well as health-code setbacks.
Legend-reading exercise
Read this excerpt from a hypothetical plot plan and answer the five questions before checking the explanations below the table.
| Entry | Symbol or note |
|---|---|
| A | Triangle with 812.4 beside it |
| B | BM 800.00 (brass disk, hydrant) |
| C | Dashed band, 20 ft wide, labeled UE 1234/456 |
| D | Contour note: CI = 2 ft |
| E | Rectangle 12 ft x 6 ft, labeled 1,000 GAL |
| F | Station label STA 12+50 |
- What is A? A spot elevation of 812.4 feet describing the ground at that single point.
- What is B? A benchmark at elevation 800.00 feet on the stated datum, used to set grades. The parenthetical note identifies the monument found there.
- What is C? A 20-foot utility easement recorded under the referenced document number. The recorded instrument describes the use rights and any restrictions. Verify those terms with the approved plan before staking work in the band.
- What do D and E tell a builder? D sets the contour interval at 2 feet, so adjacent regular contour lines differ by 2 feet; E is a 1,000-gallon septic tank footprint 12 feet by 6 feet that should match the approved septic permit.
- What is F? A station 1,250 feet from the baseline origin (12 full stations of 100 feet plus 50). Stations locate features along a road or utility run.
Common traps
- Assuming north is up; check the north arrow and whether it is true, magnetic, or assumed.
- Scaling a distance when a dimension is printed.
- Treating an easement as a property line, or a setback as an easement.
- Confusing a benchmark elevation with a property monument or corner.
- Missing an assumed-datum note, which makes every elevation on the sheet relative rather than absolute.
- Relying on a mortgage inspection sketch for layout; it is not a boundary survey.
- Ignoring a note that the plan is diagrammatic and not to scale.
On a topographic survey with a 2-foot contour interval, what does a series of contour lines spaced very close together indicate?
A nearly flat area with poor drainage
A steep slope
A property boundary or easement line
An underground utility corridor
What does a benchmark (BM) on a survey plan provide?
The legal boundary by itself
The location of the nearest hydrant for emergency access
The maximum building height allowed by zoning
A physical reference of known elevation on the stated datum for setting and checking grades