8.1 Quality Assurance & Quality Control

Key Takeaways

  • Quality assurance establishes controls such as training, readiness reviews and inspection plans. Quality control applies the checks and records the results.

  • The inspection and test plan identifies who releases a hold point and how to give notice for a witness point. A contract release and a required building inspection are separate approvals.

  • Michigan requires approval of applicable trade rough-ins before the frame inspection. Check project-specific reviews and documentation before each next operation conceals work.

  • Contain and document nonconforming work, obtain an authorized disposition, verify the result and check whether the corrective action addressed the cause.

  • Use punch lists and warranty records to find recurring defects and improve future inspection criteria and training.

Last updated: November 2026

A basement wall can pass a dimensional check and later show moisture or movement. A residential quality plan identifies what to check, when the evidence will still be visible, and who has authority to release the next operation.

Quality assurance and quality control

Quality assurance (QA) creates confidence that work will meet requirements. Before installing a foundation membrane, for example, review the current drawings and product instructions with the crew, choose the inspection points, and assign someone to review and release the installation before concealment.

Quality control (QC) checks whether the work meets the stated criteria. For the membrane, the verifier checks substrate preparation, seams, terminations and penetrations against the approved detail, records the result, and reports any deviations for correction.

QuestionQuality assuranceQuality control
FocusDesign and maintain a process that can meet the requirementsConfirm the materials and work meet the requirements
PeopleRoles assigned in the project quality planSuperintendent, trade lead, inspector or testing agency as assigned
Typical evidenceReadiness review, inspection plan, qualified crew and approved benchmarkChecklist, measurements, test results and nonconformance records
Foundation exampleSet the pre-backfill membrane hold point and assign release authorityFind an open membrane seam and confirm its correction

The same person can help plan a check and then perform it. On projects using the U.S. Army Corps of Engineers construction quality management system, the contractor runs its quality control program and the Corps performs government quality assurance. The inspection roles on a Michigan home depend on its contract and the applicable code.

Verification uses objective evidence to confirm specified requirements. Validation uses evidence to confirm that requirements for the intended use are met. A cylinder report and wall dimensions can verify specified strength and geometry. Confirming the basement is suitable for the intended dry storage also requires evidence about moisture performance, such as the approved drainage and waterproofing checks.

The construction quality plan and the ITP

Before work starts, identify the contract drawings, specifications, approved submittals and revisions that define acceptance. Assign responsibility, organize the inspection and testing calendar, set the notification process, and identify records to retain. Review requirements and readiness before an activity, examine the first work with the crew, then follow up as production continues. Train the crew on the requirements before the work is released.

An inspection and test plan (ITP) lists operations, criteria, timing or sampling frequency, the responsible verifier, any release requirement and the record to file. Connect each stage to the schedule so follow-on trades can see which checks govern their start.

  • A hold point requires the designated party’s release before work proceeds. Record authorization or any permitted written waiver in accordance with the plan. Obtain required building official approval separately.
  • A witness point gives the designated party an opportunity to observe. Give the required notice and document attendance or waiver. If the verifier does not attend, proceed only as the governing plan permits after any required wait.

The following project uses hold points for work that will soon be concealed and witness points for sampling set by the concrete specification. Confirm the permit inspection list and any separate contract inspections when preparing the plan.

OperationWhat to checkWhenResponsible party and record
Footing excavationBearing material and depth below actual grade. Rule 522 ordinarily requires 42 inches for exterior footings and foundation systems, with official modification allowed on specified evidence. Check R403.1.4.1 where applicable.After excavation and placement of required reinforcing, before concreteSuperintendent checks readiness. Obtain foundation inspection approval under R109.1.1.
Foundation reinforcementBar size, spacing, cover and laps shown on the designBefore each affected placementSuperintendent or designated verifier releases the project hold. File checklist and photos.
Concrete placementSpecified slump and strength sampling, and curing requirementsFrequency in the concrete specificationLab or designated technician records batch and sample identities and issues the reports. Superintendent logs curing.
Waterproofing and drainageSubstrate, seams, terminations, penetrations and installed drains against approved detailsBefore backfillObtain the project hold release and any applicable permit approval. Keep photos and sign-off.
Trade rough-ins, then framingApplicable rough systems before concealment. For the frame check, verify roof, framing, firestopping, draftstopping and bracing.Rough-in approvals precede the Michigan frame inspectionTrades and superintendent check readiness. Record agency approvals.
Thermal envelope and air leakageInsulation and air sealing compared with the approved energy documents. Where prescribed, verify leakage of no more than 4 ACH50.Envelope check before finishes conceal the work. Blower-door test after all penetrations are created.Record envelope verification and submit the signed leakage report where applicable. Arrange a certified independent tester if required by the code official.
FinalApplicable system approvals, visible life-safety items and closeout documentsAfter permitted work is complete and before occupancy approvalBuilding official completes final review. Keep the certificate where required.

Mock-ups and benchmarks

An accepted mock-up can establish a visual or installation benchmark for later production. For example, agree on a representative drywall finish under the intended lighting before work continues. Where the contract requires a retained mock-up, identify its approved location and record deviations separately. Any specified performance test remains an independent check.

Document control

The submittal register identifies reviewed products and their revisions. The request-for-information log records design clarifications and who authorized changes. Cross-reference tests, photos of concealed work, inspection approvals and corrective work to the location and current drawing. File the record drawings and closeout documents required by the contract and applicable rules.

Jurisdictional and third-party inspections

Under adopted R109.3 the permit holder or agent requests required inspections and provides access. Michigan’s amended R109.4 requires approval before proceeding past the indicated inspection point. Correct cited work and keep it exposed until the building official authorizes concealment. Rule 509 also requires approved plumbing, mechanical and electrical rough inspections before the framing inspection.

R104.4 allows the building official to accept written and certified inspection reports by approved agencies or individuals. R109.2 addresses approval of inspection agencies and their qualifications. A private test commissioned for a contract can inform acceptance, while release of a required permit stage still follows R109.4. Record both where required. A permit approval does not establish that a stricter project specification was met.

Nonconformance, punch list, and warranty callbacks

A nonconformance report (NCR) records the location, condition, governing requirement, immediate protection, person responsible for disposition, and verification needed for closure. Typical dispositions include rework to the original requirement, an approved repair, authorized acceptance as-is, or rejection and replacement. Obtain design review where the proposed disposition affects the design or performance, and obtain any required official approval before proceeding.

Correction addresses the immediate defect. Corrective action addresses its cause and checks whether the changed process works. Repairing a defective membrane seam corrects that seam. Requiring a pre-backfill checklist and checking completed releases on later placements can address a missed inspection step.

Track punch-list items by trade, location, time open and repeat type. Keep a comparable warranty log for the date reported, evidence, cause if established, resolution and cost. A series of recurring window leaks is a reason to review the approved flashing detail, installation records and next project’s first-work check.

Worked scenario: the cracked foundation at the framing walk-through

A two-story home has 8-inch poured basement walls. At the pre-drywall walk-through the superintendent finds a vertical crack near mid-span of the rear wall, a 3/16-inch lateral offset, efflorescence, and damp concrete on the inside face.

  1. Contain and document. Protect the area, photograph and measure the crack, and hold dependent work that would cover it.
  2. Check the records. The batch ticket identifies the specified 4,000 psi mix. It gives no measured in-place strength at the time of backfill. The contract called for slump and cylinder sampling at this placement and a minimum seven-day cure before backfill. Neither test is documented, backfill began at 36 hours, and the required membrane checklist lacks a release.
  3. Report the findings. Open NCR-14 and notify the owner and design professional under the contract. The offset and moisture require evaluation. The missing records and early backfill are independent findings, and the cause of the movement is still open. Check the schedule for the impact of holding insulation and drywall.
  4. Obtain a disposition. Have the design professional evaluate loading, wall strength and support at backfill, drainage, and the observed movement. R404.1.7 addresses sufficient strength and lateral support before backfill, with an exception to bracing for walls supporting less than 4 feet of unbalanced backfill. The seven days in this case come from the project specification. Obtain the written technical disposition and coordinate any required amended documents and official approval.
  5. Control subsequent work. Assign and verify pre-backfill release for strength and support, the specified cure interval and membrane inspection. Confirm the required sampling at the next placement and retain the reports.
  6. Verify and close. Record the approved work and verify it against the disposition before covering. Attach any required permit reinspection authorization, corrective-action follow-up and relevant schedule and cost records. Determine payment responsibility under the contract.
  7. Carry the record into closeout. Let the warranty team know what performance to monitor and which inspection and repair records belong with the wall.

Finding the offset and checking it against project criteria are quality control. Assigning authority for the backfill release and checking that the new process is used are quality assurance. Use both to keep the next crew from concealing an unresolved condition.

Test Your Knowledge

A contractor writes a quality plan that requires the superintendent to review foundation waterproofing and authorize backfill. What is the act of establishing that project hold point?

A

Quality assurance, because it establishes a planned control before concealment

B

Quality control, because the superintendent is performing the seam inspection

C

Validation, because the resulting basement has already been tested for its intended use

D

Warranty administration, because the contractor is resolving a defect reported after turnover

Test Your Knowledge

Under a project inspection plan that recognizes both hold and witness points, which statement correctly describes the two?

A

A witness point always requires authorization before proceeding, while a hold point only requires notification

B

A hold point may be skipped whenever the verifier is late

C

A hold point requires the designated release. A witness point requires proper notice and an opportunity to observe, with continuation governed by the plan

D

The superintendent may verbally waive both permit inspections and project hold points

Test Your Knowledge

At a framing walk-through the superintendent finds an offset crack in a poured basement wall. The contract called for sampling at the placement, a minimum seven-day cure before backfill, and a waterproofing release. The testing and release records are missing, and backfill began at 36 hours. Which response best closes the quality loop?

A

Patch the crack from inside and proceed with insulation and drywall

B

Assign all repair costs to the owner as soon as the crack is photographed

C

Continue work and leave the crack for the final occupancy inspection

D

Hold work that would cover the wall, open a nonconformance report, obtain a written design disposition, verify the authorized work and improve the pre-backfill checks