8.3 Construction Cost Management

Key Takeaways

  • Estimate at completion equals incurred cost plus the forecast cost of all remaining work. The remaining forecast includes the open part of commitments and any work still to be bought.

  • For purchases at a single comparable rate, price variance is the unit price difference times actual quantity. Quantity variance is the quantity difference times budget unit price. Their sum equals actual cost minus budget for the compared work.

  • With earned value of $120,000 and actual cost of $150,000, CPI is 0.80. Actual cost exceeded the budget for that work by $30,000, or 25%. With planned value of $100,000, SPI is 1.20.

  • BAC divided by CPI forecasts $500,000 from a $400,000 budget if cumulative cost efficiency persists. A TCPI of 1.12 against the original budget is the efficiency needed to finish within $400,000.

  • For a typical taxable Michigan purchase of materials incorporated into another person’s real property, the contractor pays sales or use tax as applicable. Carry it as job cost and price the improvement without charging the customer a separate sales tax on it.

Last updated: November 2026

An estimate forecasts the cost of a defined scope. The job cost report records costs incurred and forecasts the cost to finish. Estimate project profit by subtracting projected total costs on the stated basis from projected contract revenue.

Job cost accounting structure

A cost code groups costs by work scope. CSI MasterFormat’s divisions, such as 03 Concrete, 06 Wood, Plastics, and Composites, and 09 Finishes, can inform a contractor’s own code list. Map the estimating and job cost systems so charges and quantities can be compared at a common work-package level. The report below uses example company codes.

Separate cost types such as labor and labor burden, material, equipment and subcontracts. Code payroll, purchase orders, invoices and accruals consistently. If the crew’s labor is charged to general carpentry but the estimate budgets it under wall framing, remap those costs before interpreting any variance.

Committed, actual, forecast, and estimate at completion

  • Budget at completion (BAC) is the approved budget for the defined scope.
  • Committed cost records obligations under issued purchase orders or subcontracts. Show whether the column is the full commitment or only its open balance.
  • Actual cost (AC) is the incurred cost to date. Include appropriate accruals for work performed and items received when applicable, even before invoice or payment.
  • Estimate to complete (ETC) is the forecast for the remaining work. Include the unperformed part of existing commitments and remaining costs outside those commitments.
  • Estimate at completion (EAC) = AC + ETC. Variance at completion (VAC) = BAC − EAC. A negative VAC indicates a forecast overrun.
Company cost codeBudgetTotal committedActual to dateETCEACVAC
03-3000 Cast-in-place concrete$42,000$41,500$39,800$3,400$43,200−$1,200
06-1000 Rough carpentry$58,000$52,000$49,100$11,900$61,000−$3,000
09-2500 Gypsum board$26,000$24,500$0$25,200$25,200+$800
Total$126,000$118,000$88,900$40,500$129,400−$3,400

The gypsum board subcontract has been signed, but no cost has been incurred. Its ETC already includes the $24,500 still owed for the future work plus $700 of other remaining costs. The EAC is $25,200 and the package is forecast $800 under budget. Adding the commitment again would count the subcontract twice.

Cost to complete and percent complete

Actual cost divided by EAC shows the share of forecast cost incurred. That share can lead physical progress when costs include stored materials or lag when lower-cost work is completed before a major expense. Missing accruals can also distort the measure. Track units installed or completed milestones alongside the cost figures. Follow the contract’s billing terms, including any conditions for billing stored materials. Financial reporting uses its applicable criteria for measuring progress and recognizes revenue on its own basis.

Use a bottom-up ETC when you can reprice the remaining work. If remaining work is expected at its budgeted cost, EAC = AC + (BAC − EV). If cumulative cost efficiency is expected to persist, EAC = AC + (BAC − EV) ÷ CPI, which equals BAC ÷ CPI when CPI is EV ÷ AC and both are positive. State which assumption drives the forecast and compare it with current production, purchases and risks.

Variance analysis

For material, split the cost difference into quantity and unit price effects. For labor, split it into hours and hourly rate effects. Compare like scope and compatible units and keep the same treatment of burden in actual and budget rates.

  • Price variance = (actual unit price − budget unit price) × actual quantity
  • Quantity variance = (actual quantity − budget quantity) × budget unit price
  • Labor rate variance = (actual rate − budget rate) × actual hours
  • Labor efficiency variance = (actual hours − budget hours) × budget rate

Worked material example. The budget allows 5,000 board feet of framing lumber at $1.20 per board foot, or $6,000. The job used 5,400 board feet at $1.35, or $7,290.

  • Price variance = ($1.35 − $1.20) × 5,400 = $810 unfavorable
  • Quantity variance = (5,400 − 5,000) × $1.20 = $480 unfavorable
  • Total = $1,290, which matches $7,290 − $6,000 exactly

Investigate why the price and quantity differed. Compare purchase orders and receipts for the price change, then review takeoffs, scope changes, cuts and returns for the quantity difference. The arithmetic identifies where to look. It does not assign responsibility.

Worked labor example. The crew installs the same 12,000 square feet used for the drywall budget. At 0.02 budgeted hours per square foot, the allowance is 240 hours at $42 per hour, or $10,080. Actual cost is 275 hours at $46 per hour, or $12,650. Use comparable burdened rates and compare hours for the quantity actually installed.

  • Efficiency variance = (275 − 240) × $42 = $1,470 unfavorable
  • Rate variance = ($46 − $42) × 275 = $1,100 unfavorable
  • Total = $2,570 unfavorable, matching the difference between $12,650 and $10,080

Check timecards and installed units for the hours variance, then review crew mix, overtime and burden assumptions for the rate variance. Site conditions, learning time and the original budget can influence both.

Earned value basics

Planned value (PV) is the budget assigned to work planned by the status date. Earned value (EV) is the budget assigned to work performed by that date. Actual cost (AC) measures the cost incurred for that work. Use the same scope and date cutoffs, and give EV according to a defined progress measure such as installed units or completed milestones.

MeasureFormulaReading
Cost variance (CV)EV − ACPositive means cost below the budget for accomplished work
Schedule variance (SV)EV − PVPositive means more budgeted work was accomplished than planned
Cost performance index (CPI)EV ÷ ACBudgeted work value earned per dollar of actual cost
Schedule performance index (SPI)EV ÷ PVEarned budget value relative to plan, with positive PV
Forecast at sustained cost efficiencyBAC ÷ CPIConditional final cost forecast when cumulative CPI is positive and is expected to persist
To-complete performance index against BAC(BAC − EV) ÷ (BAC − AC)Efficiency needed to meet the approved budget, given a positive remaining budget

Worked example. A project reports EV of $120,000, AC of $150,000, and PV of $100,000, against a budget at completion of $400,000.

  • CV = $120,000 − $150,000 = −$30,000, or a 25% overrun relative to the $120,000 budget for the work performed.
  • SV = $120,000 − $100,000 = +$20,000 of budgeted work above plan.
  • CPI = $120,000 ÷ $150,000 = 0.80.
  • SPI = $120,000 ÷ $100,000 = 1.20.
  • If cumulative CPI persists, EAC = $400,000 ÷ 0.80 = $500,000, so VAC = −$100,000.
  • To finish within BAC, TCPI = ($400,000 − $120,000) ÷ ($400,000 − $150,000) = $280,000 ÷ $250,000 = 1.12.

The job earned $0.80 in budget value per dollar incurred and accomplished 20% more budgeted work than planned to date. Use the schedule network to interpret the finish date and the cost records to investigate the overrun. To meet the original budget the remaining work must earn $1.12 of budget value per dollar incurred. Using the $500,000 forecast as the target instead gives $280,000 ÷ $350,000 = 0.80.

Once all baseline work is complete and the planned finish date has arrived or passed, EV and PV both equal BAC and SPI is 1.00. Review the actual finish date and the schedule logic to find a late completion even when that measure has returned to 1.00.

Change orders, Michigan tax, overhead, and profit

Price changes using the contract’s rules for direct costs, permitted overhead and profit, and any applicable bond or insurance charges. Include the materials, labor and equipment needed for the changed scope and document any time impact. If the contract authorizes time and material, obtain the required approvals and maintain contemporaneous tickets. Identify change costs separately from base work so the report can distinguish scope growth from base cost variance.

Michigan sales and use tax. Michigan Treasury RAB 2025-18 explains the rules for construction contractors other than manufacturer/contractors. A contractor acquiring materials to improve another person’s real property generally pays 6% Michigan sales tax on taxable in-state purchases or accounts for Michigan use tax where due. Determine any applicable exemption or credit for qualifying tax already paid. Include the tax as material cost in pricing the work, without separately charging sales tax on the real-property construction contract. A separate retail sale of tangible personal property follows the retail rules.

Overhead can include job costs such as field supervision and temporary facilities, plus business overhead such as office operations. Choose a consistent allocation base and avoid charging the same cost both directly and through the rate. If total business overhead is $180,000 on $1.2 million of annual revenue, it consumes 15% of revenue. Revenue must also cover direct and other costs before the business earns a profit.

Profit fade is a decline in expected profit as the revenue or cost forecast changes. Update the EAC and reconcile approved changes as well as pending exposures. On the work-in-progress schedule, compare cumulative billings with revenue recognized under the applicable accounting method. Billings ahead of recognized revenue can represent a contract liability. Recognized revenue ahead of billing can represent unbilled work. Check cash receipts separately, and use budget-based EV for performance analysis.

Cost control cadence

Weekly, reconcile crew hours, quantities and receiving records with current work packages and changes. At each cost reporting cutoff, review costs, commitments, remaining forecast, EAC, job cash and the work-in-progress schedule. Document why the forecast moved and what decision the variance requires.

Test Your Knowledge

A report shows $120,000 of earned value, $150,000 of actual cost, and $100,000 of planned value for the same scope and status date. What do the indices and costs show?

A

CPI is 1.25 and SPI is 0.80, so the job has favorable cost performance and less completed work than planned

B

CPI is 0.80 and SPI is 0.83, so cost exceeds the budget for completed work and completed work is below plan

C

CPI is 0.80 and SPI is 1.20. Cost is 25% above the budget for completed work, and budgeted work accomplished is 20% above plan

D

CPI is 1.20 and SPI is 0.80, so cost is favorable and completed work is below plan

Test Your Knowledge

A drywall package has a $26,000 budget and zero incurred cost. Its $25,200 forecast to complete includes the full $24,500 signed subcontract. What does the cost report show?

A

A package precisely on budget because the ledger shows zero actual cost

B

A $25,200 estimate at completion and a forecast $800 under budget

C

A $49,700 estimate at completion because the signed subcontract must be added to the forecast

D

A $24,500 actual cost posted as soon as the subcontract is signed

Test Your Knowledge

A Michigan contractor agrees to build a $250,000 room addition. The contractor buys $40,000 of ordinary taxable materials from a Michigan supplier, pays 6% sales tax and incorporates all the materials into the owner’s real property. How should the contractor handle the tax?

A

Carry $2,400 as material job cost without charging the owner sales tax on the $250,000 construction contract

B

Collect 6% sales tax from the owner on the entire $250,000 contract

C

Buy these materials using a resale certificate and collect sales tax from the owner at closing

D

Exclude material sales tax because only installation labor is taxable