9.3 Scheduling & Critical Path Method
Key Takeaways
With finish-to-start relationships, zero lag and a shared calendar, take the maximum predecessor early finish during the forward pass and the minimum successor late start during the backward pass.
Total float is LS minus ES, or LF minus EF. In the worked network free float is the earliest successor ES minus the current EF. Identify the driving path and evaluate additional constraints separately.
Calculate incremental crash cost per day and retest the finish after each change. Tied paths may require a shared activity or simultaneous reductions.
Check the approved footing and backfill details and the actual inspection and weather windows. Michigan’s standard exterior footing depth can be modified by the official under Rule 522.
Preserve the original baseline, update the forecast as of a stated data date, and retain the actual sequence and approved baseline revisions separately.
Two ways to show time
A Gantt chart displays activity dates and durations. A bar chart without logic links can show that an activity moved, but assessing the effect on completion requires its dependencies. Modern scheduling tools can show both logic and bars.
In an activity-on-node precedence network, nodes carry activities and arrows represent dependencies. A finish-to-start tie controls when the successor may start. Start-to-start controls the successor’s start relative to the predecessor’s start. Finish-to-finish relates the finishes. Start-to-finish links the predecessor’s start to the successor’s finish. A lag adds an offset. A lead allows overlap relative to the underlying relationship. Use explicit activities for waits or approvals that need separate tracking.
Activity-on-node notation
One way to display the six planning values on each node is:
+---------+--------+---------+
| ES | Dur | EF |
+---------+--------+---------+
| Activity name |
+---------+--------+---------+
| LS | TF | LF |
+---------+--------+---------+
ES is early start, EF early finish, LS late start, LF late finish, Dur duration, and TF total float.
Forward pass: early dates
In the worked case, use one calendar, finish-to-start ties, zero lag, no resource or date constraints and elapsed workday boundaries. Start the first activity at ES = 0 and work forward:
- EF = ES + Dur
- When several activities converge on one successor, ES of the successor = the maximum EF of its predecessors
For a successor waiting for one activity to finish at boundary 15 and another at 18, the earliest start is 18 under these assumptions.
Backward pass: late dates
For this unconstrained network, set the terminal activity’s LF equal to its EF, then work backward. If instead a required finish is earlier than the forecast, using that requirement for the backward pass can produce negative float. The forward forecast stays as calculated until the logic, dates or durations change:
- LS = LF − Dur
- When one activity feeds several successors, LF of the predecessor = the minimum LS of its successors
Worked example: a 28-day shell-to-finish sequence
Seven grouped activities illustrate the calculation. The stipulated durations assume the required inspection releases occur within the phases shown. In a field schedule, track each approval separately if it can drive subsequent work. Backfill in C assumes the wall has adequate strength and permitted support or bracing under R404.1.7, plus any required pre-backfill release.
| ID | Activity | Dur (days) | Predecessor |
|---|---|---|---|
| A | Excavate, prepare footings and obtain pre-pour release | 3 | — |
| B | Pour footings and reach the required condition for wall work | 2 | A |
| C | Foundation walls, waterproofing, drain tile, backfill | 4 | B |
| D | Frame and sheathe, set trusses, roof sheathing | 6 | C |
| E | Roof dry-in | 3 | D |
| F | Trade rough-ins and approvals | 5 | D |
| G | Frame release, insulation checks, drywall and interior finishes | 8 | E, F |
Forward pass, step by step: A starts at 0 and finishes at 3. B runs 3 to 5. C runs 5 to 9. D runs 9 to 15. E and F both start at 15; E finishes at 18, F at 20. G converges, so its ES is the maximum of 18 and 20, which is 20, and it finishes at 28. Project duration is 28 days.
Backward pass: G has LF 28 and LS 20. F has LF 20 and LS 15. E has LF 20 (the minimum of G's LS, its only successor) and LS 17. D's successors are E (LS 17) and F (LS 15), so D's LF is the minimum, 15, and its LS is 9. C runs 9 back to 5, B 5 back to 3, and A 3 back to 0.
| ID | Dur | ES | EF | LS | LF | Total float | Free float | Critical? |
|---|---|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 | 0 | Yes |
| B | 2 | 3 | 5 | 3 | 5 | 0 | 0 | Yes |
| C | 4 | 5 | 9 | 5 | 9 | 0 | 0 | Yes |
| D | 6 | 9 | 15 | 9 | 15 | 0 | 0 | Yes |
| E | 3 | 15 | 18 | 17 | 20 | 2 | 2 | No |
| F | 5 | 15 | 20 | 15 | 20 | 0 | 0 | Yes |
| G | 8 | 20 | 28 | 20 | 28 | 0 | 0 | Yes |
The critical path is A → B → C → D → F → G, 3 + 2 + 4 + 6 + 5 + 8 = 28 days. Each activity on it has zero total float in this case. With the rest of the network unchanged, a one-day slip on the path moves completion from 28 to 29. The path through roofing, A → B → C → D → E → G, totals 26 days. Set terminal free float to zero here by treating the project finish at boundary 28 as G’s successor milestone.
Total float versus free float
Total float = LS − ES = LF − EF. In this case it is the available delay relative to the project finish. Free float = earliest successor ES − activity EF in this finish-to-start, zero-lag network. It is the delay available before any immediate successor’s early start moves. Roofing has 2 days of each. It finishes at 18, and G’s earliest start is 20.
Activities on a path can share total float. If roofing finishes two days later while the rest of this example stays the same, both branches reach G at day 20 and both are driving. Date constraints can make the lowest-float activities differ from the actual driving sequence. Check the logic and any constraints before drawing a conclusion from a float column alone.
Compressing the schedule: crashing
Crashing shortens an activity by changing its method or adding resources at a cost. Check which path currently drives completion and calculate the extra cost for a feasible reduction. For constant marginal cost over the stated range:
Suppose D can drop from 6 days to 4 for $1,600, E from 3 to 2 for $900, F from 5 to 3 for $3,000 and G from 8 to 6 for $2,600. Assume the added costs are linear in that range. The daily slopes are D: $800, E: $900, F: $1,500 and G: $1,300.
| Cumulative reductions | Roofing path | Rough-in path | Forecast finish | Cumulative added cost |
|---|---|---|---|---|
| None | 26 days | 28 days | 28 days | $0 |
| D by 2 days | 24 days | 26 days | 26 days | $1,600 |
| Also G by 2 days | 22 days | 24 days | 24 days | $4,200 |
| Also F by 2 days | 22 days | 22 days | 22 days | $7,200 |
D and G are shared by both paths. F is the controlling branch until the paths tie at 22 days. At that point, shortening E alone cannot move completion because F still controls the merge. A further reduction would need enough compression on both branches or on a common activity. The remaining option set contains neither. Recalculate after each proposed reduction and decide whether its cost meets the project’s objective.
Fast-tracking instead changes the sequence to overlap eligible work. For example, arrange off-site fabrication while foundation work is still under way if approved dimensions and bearing details are available. For any overlap, account for rework risk, resources and regulatory hold points. Keep affected rough work visible and wait for approvals before advancing to concealment.
Resource leveling
Resource leveling resolves peaks and valleys in labor and equipment demand, sometimes at the cost of duration. Suppose the roofing crew needs a shared lift on day 15 only, and the rough-in crew must use it on day 15 and releases it by the start of day 16. Shift the roofing activity to day 16. E then finishes at 19, ahead of F at 20, and completion stays at day 28. A shift of two days in this network would consume E’s full float and bring both paths to the same duration at the merge.
Michigan weather and seasonality
Account for weather in durations and calendars. Michigan Rule 522 sets 42 inches below actual grade as the starting rule for exterior footings and foundation systems. Check applicable R403.1.4.1 requirements and any modification allowed by the official. Use the actual site and approved details to estimate production and release dates.
Confirm cold-weather protection and allowable installation conditions for concrete, masonry, coatings and roofing with the specifications and product requirements. If temporary heat or enclosure keeps work viable, put responsibility and its availability date in the subcontract and schedule. Build weather contingencies from the actual work and season.
Baseline, update, and as-built
Three schedule documents get confused, and the confusion costs claims. The baseline is the approved plan for the project: scope, logic, durations, and the completion date. Preserve the approved version for comparison. Keep any subsequently authorized revisions with their supporting decisions. An update re-forecasts remaining work from a stated data date, incorporating actual starts and finishes, approved changes, and revised durations for work not yet performed. An as-built schedule is a historical record of what actually happened, used to support delay analysis and lessons learned.
When a delay occurs, record its date, cause, duration and affected dependencies. Update the schedule from the data date and compare the previous and new driving paths. If the approved rough inspection shifts by one workday in the unchanged example, F pushes G one day. If roofing instead shifts one day while F stays on plan, roofing uses one day of free float and day 28 stays feasible. Keep dated updates and the inspection record with the baseline and the eventual as-built sequence.
In the worked network, Activity E (roof dry-in, 3 days) has ES 15, EF 18, LS 17, LF 20. Activity G starts at ES 20. What are E's total float and free float?
Total float 5 days; free float 2 days
Total float 2 days; free float 2 days
Total float 0 days; free float 0 days
Total float 3 days; free float 3 days
The owner wants the worked network to finish within 26 days. Of the two options offered, framing D can be reduced from 6 to 4 days for $1,600 and roofing E from 3 to 2 days for $900. What change achieves the target at the lower added cost?
Apply both changes for $2,500
Shorten roofing only for $900
Keep both durations unchanged
Shorten framing only for $1,600
Which statement correctly distinguishes the three schedule documents used on a construction project?
A baseline schedule is reissued monthly with actual start and finish dates
An as-built schedule is the approved plan that defines contract time
The baseline is the approved plan, an update re-forecasts remaining work from a data date, and the as-built records what actually happened
Updates replace the baseline once the project passes 50 percent completion