33.4 Shoring Suspended Concrete
Key Takeaways
Trace wet-concrete, form and construction loads through the temporary supports to bearing that can carry them. Include the capacity and age of any supporting floor.
Check the governing shore reaction and supporting system. Dividing the total load by a single-post rating cannot establish shore spacing or approve a layout.
Inspect shoring as required before erection, before placement, during placement and immediately afterward. Obtain qualified-person approval before releasing shoring, bracing or guying.
In a conventional reshore sequence, the slab takes its own weight when original shores are released, and reshores provide support for subsequent construction loading as designed.
Temporary Support for a Suspended Placement
During casting, concrete has little capacity to bridge a span. Loads travel from the form face to joists or beams, into shores and bracing, and then to the ground or floors below. When the permanent system uses steel deck or another stay-in-place form, verify the deck’s construction span and required support. Some designed systems span without temporary shores.
Before, During and After Placement
- Review the load path. Include wet concrete, formwork, reinforcement and construction loads. Check concentrated loads such as stacked material and forces from placing equipment. A lower floor receiving shore reactions also carries its own loads. The employer uses information from a person qualified in structural design before allowing construction loads on it.
- Match the installation to the plans. MIOSHA Part 25 requires adequate vertical and lateral capacity and the applicable drawings at the site. Check supporting sills or plates, soil bearing, firm contact at the shore ends, bracing in both directions and any specified camber. Where a single-post shore is used in more than one tier, R 408.42527(5) requires design by a registered engineer and inspection by a qualified person.
- Inspect and document. Under R 408.42524, a qualified person inspects equipment before erection and documents the installed system before the pour. That person also inspects erected shoring during and immediately after placement. Damaged or weakened shoring must be reinforced or reshored as required.
- Control the pour and staging. Place in the planned sequence to avoid overloading one area. Monitor from the designated safe positions. Only designated employees may be on the first floor immediately under the forms during placement.
Worked Check — Construction Loading and Shore Reaction
Use the 16 × 24 ft garage deck from the suspended-slab quantity example. Its 6-inch slab contributes 75 psf of fresh concrete. For this illustration, the other uniform dead load is 8 psf, the construction live load is 50 psf, and there are no motorized carts. The uniform load is 75 + 8 + 50 = 133 psf, totaling 133 × 384 = 51,072 lb.
Suppose an interior shore has a 4 × 6 ft tributary area under a simplified uniform-load model. Its vertical reaction from that load is 133 × 24 = 3,192 lb. A 4,000 lb working rating at the actual extension exceeds this illustrative reaction. A different bay or a concentrated load can produce a higher reaction. Check every governing condition, including shore extension and bracing, bearing, form bending and support by any lower floors. Dividing 51,072 by 4,000 gives a numerical capacity floor of 13 equally loaded posts. It supplies no post locations or approved layout.
Now assume a proposed equipment move adds 1,000 lb of reaction at that shore after analysis of how the load reaches the supports. Its reaction would increase to 4,192 lb, above the 4,000 lb rating. Hold the move and have the load location or support plan reviewed. An unchanged average across the other posts cannot relieve that local overload. A similarly important change can occur at the shore base. If rain weakens the soil under a sill, recheck its bearing capacity before placement. Part 25 requires inspection after events that can affect soil support. Verify that the sill and base plate remain firmly supported and that the proposed bearing repair can carry the reaction.
Stripping, Reshoring and Backshoring
Follow the temporary-work drawings. Original shores carry the placement loads. In a conventional reshoring sequence, the original shores are released in a planned area, the slab takes its own weight, and reshores are then installed snugly for the planned future loads. A backshoring sequence keeps the slab supported during that stage, for example by retaining or replacing support in small areas under the plan. The sequence and the number of supported levels change the forces in young slabs and temporary supports.
Release Criteria
Check each stage separately. Follow R 408.42522 for complete form removal, R 408.42524 for qualified-person release of shoring and bracing, and the rule requiring reshoring where needed. If the plan specifies an in-place strength at release, check that result against the required strength and stage loads. Field-cured specimens or a properly correlated and approved in-place method can help establish strength under the specified procedure. If the in-place result is short, hold release and keep the approved support in place.
The approved shoring plan for a suspended slab requires a stated in-place strength before the original shores are released. The current approved test result is below that strength. How should the crew proceed?
Keep the approved supports in place and defer release until the plan criteria are satisfied and release is authorized.
Release the shores after 24 hours because the soffit looks firm.
Place reshores wherever the slab looks low and remove the original shores.
Release the original shores at seven days regardless of current strength.