25.2 Federal Hazardous Materials in Demolition

Key Takeaways

  • The federal Asbestos NESHAP generally excludes a stand-alone residential building with four or fewer units. Prior regulated use, mixed use or inclusion in a covered installation can change the answer. Evaluate Michigan worker-protection, licensing and notification requirements separately.

  • EGLE uses MiEnviro for NESHAP notices. The ordinary federal clock is 10 working days before asbestos disturbance for threshold-level work, or before demolition for a covered demolition below the thresholds. An imminent-collapse order has a different timeline.

  • The ordinary work-practice rule calls for early RACM removal, controls on emissions and a trained on-site representative with biennial refresher training. Check the specific provisions before allowing material to remain or changing wetting procedures.

  • For asbestos waste covered by the shipment-record rule, trace a missing signed record at 35 days and report it at 45 days after acceptance by the initial transporter. Retain shipment records for at least two years.

  • Michigan's MIOSHA Asbestos Program administers a separate notice generally due 10 calendar days before nonemergency abatement exceeding 10 linear feet or 15 square feet of friable material. MDHHS administers lead abatement certification.

Last updated: November 2026

What the asbestos rule covers, and what facility leaves out

In demolition, start with the facility definition in 40 CFR 61.141. It covers institutional, commercial, public, industrial and qualifying residential buildings, including condominium and cooperative buildings. A separate residential building with four or fewer dwelling units is generally excluded. A mixed-use building or a building containing a loft used as a dwelling does not qualify as an exclusively residential building for this rule. A facility previously subject to Subpart M remains covered even if its use changes. A group of small buildings under common control at a single project site can constitute a covered installation.

A demolition removes a load-supporting member or intentionally burns a facility. Other alterations of a facility or its components, including stripping asbestos, are generally renovations. Regulated asbestos-containing material (RACM) includes friable asbestos material (more than 1% asbestos and capable of being crumbled by hand pressure when dry), Category I nonfriable ACM that has become friable or will be sanded, ground, cut or abraded, and Category II nonfriable ACM likely to be crumbled or pulverized by the expected forces of the work. The planned method can change which material counts toward the threshold.

The small-building exclusion applies to the federal emission rule. Review Michigan asbestos licensing and accreditation, MIOSHA employee exposure, and applicable waste provisions on their own terms.

The inspection comes before the plan

Before the demolition or renovation begins, the owner or operator must thoroughly inspect the affected facility for asbestos, including Category I and Category II nonfriable material. The inspection drives three decisions: what asbestos is present, how much qualifies as RACM and what must be addressed before demolition or renovation. Facility coverage depends on the building and project scope.

Use a Michigan-accredited asbestos inspector as applicable and document sampling, laboratory results and any material assumed to contain asbestos. The state worker-protection assessment includes the location and quantity of known and presumed ACM. EGLE's thorough-inspection guidance explains documentation and when a visual assessment alone can suffice. Typical residential hits: 9-inch by 9-inch floor tile and black mastic, sheet vinyl backing, joint compound and texture coats in older work, boiler and pipe insulation, vermiculite attic insulation, cement-asbestos siding and flue pipe, and window glazing compound.

How much RACM changes the requirements

Combined RACM in the facility being demolishedWhat Subpart M requires
At least 260 linear feet on pipes, or 160 square feet on other components, or 35 cubic feet off components when the length or area could not be measured before removalFull requirements: notification plus the work-practice and waste-disposal rules
Less than those amounts, or no asbestos at allGive notice 10 working days before ordinary demolition
Demolition ordered by a state or local agency because the structure is structurally unsound and in danger of imminent collapseLimited notification and work practices; notice as early as possible and no later than the next working day, with the issuing authority, order date and ordered start date identified and a copy of the order attached

The zero-asbestos row applies to a covered demolition. A below-threshold renovation is a different case. For renovations, also check the aggregation rule for planned nonscheduled operations and the special notice timing for emergency renovations.

The notification and its clock

The federal notice deadline is 10 working days before stripping, removal or other disturbance for ordinary work at or above a RACM threshold, or before demolition starts for an ordinary covered demolition below the thresholds. The federal definition counts Monday through Friday, including holidays on those days. Michigan's delegated EGLE program currently receives notices and revisions through MiEnviro. Keep the portal confirmation.

The notice is not a postcard. Subpart M lists what it must contain: whether it is original or revised; names, addresses and phone numbers of the facility owner and operator and of the abatement contractor; whether the job is demolition or renovation; the facility's size, number of floors, age and present and prior use; the method used to detect RACM; an estimate of RACM in linear feet, square feet or cubic feet plus the nonfriable material that will remain; the street address, city, county and state; scheduled start and completion dates for both abatement and demolition; the demolition methods; the work practices and engineering controls; the waste disposal site; a certification that a trained person will supervise; the procedures for unexpected RACM; and the waste transporter.

The notice gets updated when the amount of asbestos changes by at least 20 percent, and start-date changes have their own rules: a later start requires a phone call as soon as possible before the original date plus written notice by that date, while an earlier start requires written notice at least 10 working days before the new regulated start. Work may not begin on a date different from the one in the revised notice.

Work practices that keep the material intact

Under §61.145(c), schedule removal of all RACM before an operation can break it up or block access. The rule has case-specific exceptions for sound Category I material that is still nonfriable, material encased in concrete or similarly hard material and kept wet when exposed, RACM inaccessible for testing, discovered only after demolition starts, and unsafe to remove because of the demolition, and Category II material unlikely to crumble. EGLE's guidance also calls for a licensed asbestos abatement contractor to be available on site when sound Category I nonfriable material is left in place. Intentional burning follows a different rule: remove all ACM before burning a covered facility. For inaccessible RACM discovered during demolition, keep the exposed RACM and contaminated debris adequately wet and handle them as asbestos-containing waste.

  • Apply the prescribed wetting and emission controls. Visible emissions indicate inadequate wetting, and their absence alone cannot show the material is adequately wet.

  • Lower material carefully. When material removed or stripped more than 50 ft above ground was not removed as units or sections, use leak-tight chutes or containers.

  • Keep removed material wet through collection and containment as required. The rule has specific exceptions, including for material removed in qualifying leak-tight wrapping.

  • Have a trained representative present during regulated stripping, removal or handling. Training evidence is posted and made available for inspection, and the representative refreshes training every two years.

  • Below 32°F at the point of wetting, specific cut-point and stripping wetting provisions may be suspended under §61.145(c)(7). Remove components as units or sections to the maximum extent possible, measure the wetting-point temperature at the beginning, middle and end of each workday, and keep those records at least two years.

Asbestos waste: containers, labels and paperwork

Under the ordinary wet-containment method in 40 CFR 61.150(a), asbestos waste is adequately wet, sealed while wet in leak-tight containers or wrapping, and labeled with the OSHA asbestos warning required by 29 CFR 1910.1001(j)(4) or 1926.1101(k)(8). For material transported off site, the containers or wrapped materials carry the name of the waste generator and the location where the waste was generated. Vehicles are marked during loading and unloading. For waste subject to §61.150(b), use a covered disposal site or an EPA-approved conversion site as soon as practical. Confirm acceptance before hauling.

The waste shipment record carries the generator's name, address and phone; the administering agency; the approximate quantity in cubic meters or cubic yards; the disposal site operator and site location; the transport date; the transporter; and a certification that the load is properly described, packed, marked and labeled. The signed copy from the landfill comes back to the generator. If it has not arrived 35 days after the transporter accepted the waste, the generator contacts the transporter, the disposal site operator or both to trace it; if it is still missing at 45 days, the generator files a written report with the administering agency including a copy of the record and a signed cover letter describing the tracing efforts and their results. Records are kept at least two years. Section 61.150(a)(5) excepts Category I nonfriable waste and qualifying uncrushed Category II nonfriable waste from paragraph (a). Category I nonfriable material that is not RACM also has the separate federal disposal-site exception in paragraph (b)(3). Determine the applicable Michigan disposal route even if a federal exception applies.

Michigan's second layer: licensing and its own notice

Michigan's Asbestos Abatement Contractors Licensing Act (1986 PA 135) generally requires a license for covered friable asbestos removal and encapsulation. MCL 338.3207 provides a limited incidental-work exemption for specified licensed trades and qualifying employees, including the statutory size and accreditation conditions. Audit that exemption separately from the notification threshold. Under MCL 338.3220(2), a qualifying exempt trade that discovers threshold-exceeding work after contracting must notify before removal and provide written notice within 10 days after discovery. For a qualifying emergency due to equipment failure or malfunction, MCL 338.3220(8) requires prompt telephone contact with MIOSHA and written notice within 48 hours after work starts. Follow MIOSHA's instructions before starting.

Ordinary Michigan submissionRegulated triggerTiming
EGLE MiEnviro for NESHAPOrdinary covered demolition, or a covered renovation meeting the RACM threshold10 working days before the applicable start
MIOSHA Asbestos Notification SystemNonemergency abatement exceeding 10 linear feet or 15 square feet of friable materialAt least 10 calendar days before the project begins

The 10-day notices run independently. The same job may require both.

Lead-based paint in a pre-1978 building

The federal Renovation, Repair and Painting (RRP) rule applies to covered paid renovations disturbing paint in pre-1978 target housing and qualifying child-occupied facilities, subject to the exclusions in 40 CFR 745.82–.83. EPA administers RRP in Michigan. Covered work requires a certified firm, an assigned certified renovator and applicable lead-safe work practices. EPA distinguishes demolition of an entire free-standing structure from removal of an attached part during a renovation.

Lead abatement is work designed to eliminate lead-based paint hazards permanently and is separately regulated and certified through MDHHS under Part 54A of the Public Health Code. The employer separately evaluates worker exposure under MIOSHA Part 603. The eight-hour action level is 30 µg/m³ and the eight-hour permissible exposure limit is 50 µg/m³. Manual demolition of lead-painted structures is among the tasks that require interim protection until the employer determines exposure. The standard governs respirators, hygiene and biological monitoring according to the task and exposure.

For lead waste, determine the setting, waste stream and receiving facility. If a nonexcluded waste leachate contains 5.0 mg/L or more lead under the toxicity characteristic test (TCLP), it is hazardous waste D008. EPA recognizes a household waste exclusion for lead debris from qualifying residential renovation or abatement even when a contractor generates it. Verify applicable Michigan requirements and facility acceptance before shipment.

Other hazards found mid-job

Separate these streams before committing to a disposal route:

  • Mercury-containing lamps and equipment. Separate intact lamps, thermostats and similar devices and check Michigan universal waste requirements for handling, labeling and delivery to a handler or destination facility.
  • PCBs. Older fluorescent light ballasts and some caulk and glazing from buildings constructed or renovated around 1950–1979 can contain PCBs. Characterize the material and use the applicable disposal route under 40 CFR Part 761. Manufactured products with at least 50 ppm PCBs are managed as PCB bulk product waste under §761.62; separate rules cover remediation waste and certain ballasts.
  • Refrigerant-containing equipment. Arrange compliant refrigerant recovery. Equipment normally dismantled on site has recovery requirements before dismantling. For appliances normally discarded intact, the final disposer must ensure recovery or obtain the required verification under 40 CFR Part 82, Subpart F.
  • Buried tanks. For regulated underground tanks, LARA's Bureau of Fire Services administers Part 211, including advance closure notice under R 29.2153. For ordinary permanent closure, notify BFS at least 30 days in advance unless the agency waives or changes that period, and confirm the actual work at least two working days ahead as required. The rule also requires a site assessment for ordinary closure. A release invokes separate reporting and corrective-action requirements, including Part 213 for regulated leaking tanks. A tank storing heating oil for use on the premises is excluded from Part 211's underground tank system definition; check the separate fire prevention and closure requirements.
  • Unknown containers. Stop work near unknown containers and obtain qualified waste characterization. Michigan's Part 111 governs hazardous-waste generation and disposal in its authorized program. Identify the generator category, then apply the matching site-identification, accumulation, shipping and disposal rules. Michigan also regulates certain waste liquids separately under Part 121.

Documentation that survives the job

Build a single project file and keep it: the asbestos inspection report and lab results; the EGLE notice with delivery confirmation; the MIOSHA abatement notification; the abatement contractor's license and worker accreditation; required temperature logs and any additional daily control records; container labels photographed before hauling; waste shipment records with the signed landfill return; lead test results and TCLP results if any; and tank closure documentation. Apply the retention requirement to each record type, such as the two-year minimum for federal asbestos shipment records.

Test Your Knowledge

An ordinary scheduled demolition of a covered Michigan facility involves 300 linear feet of RACM on pipes. How far ahead must the owner or operator submit the NESHAP notice through EGLE's MiEnviro portal?

A

At least 24 hours before the crew arrives

B

At least 10 working days before asbestos stripping or removal, or any other activity that would disturb the material

C

At least 30 calendar days before the demolition permit is issued

D

Within 5 days after abatement begins, as long as the waste is tracked

Test Your Knowledge

Which building is generally outside the NESHAP facility definition when each is a separate, private project at its own site?

A

A 12-unit apartment building

B

A church with a small attached office

C

A three-unit building with a real estate office on the first floor

D

A detached four-unit private residential building used only as dwellings

Test Your Knowledge

The initial transporter accepted a regulated asbestos waste shipment 45 days ago. The generator still has no copy of the waste shipment record signed by the receiving site. What does 40 CFR 61.150 require?

A

Nothing, provided the records are kept for two years

B

Re-ship the load to a second landfill

C

Submit the record and a signed account of the tracing efforts and results to the administering agency.

D

Report the load as exempt Category I nonfriable material