18.3 Lien Foreclosure & Homeowner Protections
Key Takeaways
Commence lien foreclosure within one year of recording the claim. Record the lis pendens when the action starts under MCL 570.1117.
Foreclosure is equitable in circuit court. Join persons whose interests may be impaired. The court determines amounts and priorities and may award reasonable fees under §118’s prevailing-party rules.
2010 PA 147 repealed the Homeowner Construction Lien Recovery Fund effective August 23, 2010. The former fund offers no reimbursement for current claims.
Under §118a, the owner or lessee’s court affidavit supported by the contract, change orders and available proof protects the residential structure to the extent of qualifying payments.
Check Article 24 licensure during performance where required. An unlicensed contractor cannot use a lien to collect for work requiring that license. A noncontracting owner or lessee is protected from a deficiency judgment under §107(5).
Foreclosure: one year, one courthouse, one deadline
Commence lien foreclosure within one year after recording the claim under MCL 570.1117(1). A residential claim recorded July 9, 2026 has a July 9, 2027 filing deadline on the facts given. The earlier 90-day period runs from last qualifying furnishing and governs recording of the claim.
Procedural requirements
- Lis pendens. Record this notice with the applicable county’s register of deeds when starting foreclosure (§117(2)).
- Court and character. Bring this equitable action in circuit court where the property lies. When the property spans counties or circuits, any county containing part of the property can serve as the venue. A timely cross-claim or counterclaim can also enforce a lien in a pending title, mortgage or encumbrance action (§118(1)).
- Parties. Join everyone whose property interest at filing can be divested or impaired. A joined lien claimant can timely assert its own lien and the owner or lessee can timely add other or potential claimants (§117(4), (6)).
- Contract claim. The claimant may pursue the underlying contract in the same action or separately (§117(5), §1302(2)).
- Sworn statement. The contractor’s or subcontractor’s complaint, cross-claim or counterclaim must show that the owner or lessee got the statement when requested or required (§117(7)).
- Fees. The court may award reasonable fees to a prevailing lien claimant. It may award them to a prevailing defendant if the lien enforcement was vexatious (§118(2)).
What the court does, and what it cannot do
The court determines the amount due and priorities (§118(2)). For an unpaid amount adjudged due, it may order the sale of the interest or improvement that the lien reaches, or satisfaction from rents, profits or income. In a sale order the court sets a redemption period of no more than four months and distributes proceeds according to priorities (§121). A deficiency judgment cannot run against a noncontracting owner, co-owner, lessee or co-lessee (§107(5)). A subcontractor’s or supplier’s residential lien can include contract-authorized interest, finance charges or time-price differential only through 90 days after the claim is recorded (§107(7)). This limits the lien amount. Evaluate an independent contract claim separately.
If the enforcement period passes without an action, an interested person can present an affidavit to the county clerk under §128 and record the resulting certificate to clear the recorded claim. An approved bond is a separate discharge route under §116. File the bond with the county clerk and give a copy to the claimant. Its statutory amount is twice the claimed amount, subject to the court’s power to order relief. Recording the clerk’s certificate discharges that claim and any associated lis pendens. The claimant can pursue recovery on the bond.
Enforcement timeline
| Step | Timing | Statute |
|---|---|---|
| Record claim of lien | Within 90 days after last qualifying furnishing | 570.1111(1) |
| Serve copy and any recorded proof | Within 15 days after recording | 570.1111(5) |
| Record lis pendens | When starting foreclosure | 570.1117(2) |
| Commence foreclosure in circuit court | Within one year after recording | 570.1117(1), 570.1118(1) |
| Determine amounts and priority and order sale when warranted | Court judgment | 570.1118(2), 570.1121 |
Two dates, one case
A supplier records a claim of lien on February 3, 2026. It must serve a copy on the designee by February 18, 2026 and must file its foreclosure complaint, with a lis pendens recorded at commencement, by February 3, 2027. If it records the lien on the last permissible day after last furnishing — say the 90th day, July 9 — the foreclosure year still starts on July 9, not on the date of last furnishing. Every deadline in this chapter starts from its own triggering event, and no deadline borrows the clock of another.
The recovery fund story, and what replaced it
Under former MCL 570.1203, an eligible recorded lien claimant defeated by the owner or lessee’s statutory proof of payment could seek payment from the fund. The former law required proof of claimant eligibility and a court judgment. The owner’s affidavit supported the payment defense to the lien.
2010 PA 147 repealed the fund effective August 23, 2010. Sections 570.1201–570.1207 no longer authorize fund payments or a claim process. The current residential payment defense is in §118a.
What the 2010 legislation put in its place: MCL 570.1118a
The same act added MCL 570.1118a. To protect the residential structure to the extent payments were made, the owner or lessee files a court affidavit stating the amount paid to the contractor according to the contract. Attach copies of the contract, any change orders and available payment evidence, such as canceled checks or credit-card receipts (§118a(1)). If there was no written contract required by §114, filing the affidavit creates a rebuttable presumption of payment that can be overcome by clear and convincing evidence (§118a(2)).
The presumption concerns the payments described in the affidavit. It does not turn a claimed partial payment into payment in full. The absence of a required written contract also affects the contractor's own ability to claim a residential lien under §114.
Worked scenario: the homeowner who paid in full
A homeowner signs a $120,000 contract with a licensed general contractor, pays every draw as invoiced including the final $24,000, and receives a certificate of occupancy. An unpaid electrical subcontractor properly serves a notice of furnishing nine days after first furnishing, before final payment. It records an $18,000 claim in the applicable county within 90 days of its last furnishing and serves the recorded claim and proof within the statutory 15 days.
Trace it step by step:
- Procedure. The subcontractor satisfied the furnishing-notice, recording and service steps on these facts (§109, §111).
- Sworn statement. Timely notice prevents the homeowner from using a clean statement alone to avoid the claim (§110(8)).
- Payment affidavit. The homeowner files the §118a affidavit with the signed contract, any change orders and checks showing $120,000 paid according to the contract. The lien does not attach to the residential structure to that extent, which is the full contract price. On these facts the subcontractor’s lien does not attach.
- Contract remedy. The subcontractor may pursue its claim under its own contract with the general contractor if otherwise entitled. The repealed fund provides no payment.
Now assume the owner paid $102,000 of the $120,000 according to the contract and the remaining $18,000 is unpaid. The affidavit protects the structure to the extent of the $102,000. The remaining $18,000 can be subject to the subcontractor’s otherwise valid lien. If there are multiple liens, MCL 570.1107(6) separately limits their combined amount to the amended contract price less qualifying payments under a contractor’s sworn statement or waiver in accordance with the Act.
Where the fund reference still appears
When reading legacy material, distinguish the former fund mechanism from the current court affidavit. Before using an older source on mortgage priority or foreclosure, compare its statutory version to the current Act.
The unlicensed contractor: no lien, no suit, no equity
If the general contractor needed an Article 24 license and did not hold it during performance, MCL 339.2412(1), (3) bars the contractor’s compensation suit and lien. Stokes v Millen Roofing Co, 466 Mich 660 (2002), rejected using equity to obtain the compensation barred by law. The contractor’s residential writing requirement under MCL 570.1114 concerns its contract with the owner or lessee. Evaluate a subcontractor’s eligibility and any licensing requirement separately. Epps v 4 Quarters Restoration, 498 Mich 518 (2015), treats the innocent homeowner’s agreement with an unlicensed residential builder as voidable by the homeowner. That does not give the unlicensed builder an action for compensation.
The practical consequence for a homeowner is a checklist rather than a lawsuit: verify the license number with LARA before signing, insist on a written contract containing the license statement, and keep the canceled checks that support a section 1118a affidavit.
A prevention checklist for the payment file
| Risk | Control | Authority |
|---|---|---|
| Unknown subcontractor on the job | Reconcile notices of furnishing with the payments and statement | 570.1109 |
| Hidden debts behind a clean draw request | Sworn statement with every payment request | 570.1110 |
| Paying twice for the same work | Match the conditional or unconditional form and scope to actual payment | 570.1115 |
| Material supplier left unpaid | Joint check to contractor and supplier on large material packages | contract practice |
| Wrongful lien on a fully paid house | File the 570.1118a affidavit with contract, change orders, and payment proof | 570.1118a |
| Unlicensed or judgment-proof contractor | Verify the license and use a written contract with the license number if licensure is required | 339.2412; 570.1114 |
| Stale lien clouding title | Check for timely enforcement. For an expired claim use the statutory clerk certificate procedure | 570.1117(1), 570.1128 |
The three deadlines to memorize
Work from the trigger for each deadline. The usual subcontractor or supplier clock starts at first furnishing. The recording clock starts at last qualifying furnishing. Service and foreclosure are measured from recording. Keep proof of contract compliance, timely notices, direct payments, waiver verification and the amount outstanding.
A subcontractor records a valid claim of lien on a residential project. What is the deadline to file an action to enforce the lien through foreclosure?
One year after the claim of lien was recorded
90 days after the claim of lien was recorded
One year after the last date of furnishing labor or material
Six months after the claim of lien was served on the designee
What is the current status of the Michigan Homeowner Construction Lien Recovery Fund?
It pays valid residential liens up to $50,000, funded by a fee collected with each notice of commencement
It is administered by the circuit court and requires a homeowner affidavit of payments before payment
It was repealed by 2010 PA 147 effective August 23, 2010, so no fund fee, claim procedure, or state reimbursement exists today
It was replaced by a mandatory state bonding requirement for residential builders
A homeowner paid a licensed general contractor the full contract price and now faces a subcontractor's lien. How does MCL 570.1118a protect the homeowner?
It voids every lien recorded on the property after the affidavit is filed, regardless of how much was paid
Filing an affidavit with the court, with the contract, change orders, and payment evidence, prevents the lien from attaching to the residential structure to the extent the owner paid according to the contract
It transfers the lien to the contractor's own residence
It must be recorded with the register of deeds before the claim of lien is recorded to have any effect