17.2 Builders' Risk Insurance
Key Takeaways
Builders risk covers specified property during construction against covered loss. A completed-value policy sets a limit based on projected finished value.
The construction contract assigns procurement and deductible responsibilities. Check insured parties, existing structures, offsite storage, transit and the lender’s interest under the actual policy.
Read the faulty work exclusion and any ensuing-loss exception together. The exception can restore coverage for a distinct covered resulting loss.
Project acceptance, transfer, occupancy, permanent insurance and other milestones can affect coverage before the scheduled expiration. Forms differ.
CGL responds to qualifying liability claims. An effective property waiver of subrogation can limit recovery from protected trades for an insured loss.
What builders' risk actually insures
Builders risk, or course-of-construction insurance, is first-party coverage for described property during construction or renovation. When a fire damages new framing, the policy asks whether the framing, location and cause are covered and whether coverage was in force. CGL asks separately whether the contractor owes damages and the liability form covers the claim.
A completed-value form sets the limit by the projected finished value of the insured work. It still measures the covered loss under the policy’s valuation provision. Check for a requirement to insure to value, how change orders and profit enter the value, and whether soft-cost coverage is included or endorsed. A reporting form instead requires accurate statements of values at the specified intervals. Reporting errors can limit recovery under that form.
Who buys it
Read the signed contract for which party buys the coverage, who bears the deductible, required coverages and how long they must remain in place. An owner or builder can be the buyer. Confirm that the policy actually covers the interests of the owner, contractor and subcontractors required by the contract. Check how the lender’s interest is listed. A named insured, a party whose interest is insured by the form and a lender designated as loss payee can have different rights.
AIA A201–2017 illustrates the distinction between a contract obligation and the policy terms. Article 11 refers to insurance requirements in the agreement and elsewhere in the contract documents. Section 11.3 waives specified rights among covered project participants to the extent of covered property loss, subject to stated exceptions. Confirm the contract language with the issued form and any endorsement before relying on a waiver or assuming who can adjust a loss.
Covered property
Check whether the form covers the building work, foundations and building materials intended for permanent installation. Temporary forms, shoring, scaffolding, offsite storage and transit can have separate limits or require added coverage. On a renovation, verify coverage and valuation for the existing building as well as the new work. Do the same for tools and equipment the contractor will remove after the job. An equipment floater often addresses that separate exposure.
Perils and exclusions
Some builders risk forms insure against direct physical loss unless the cause or property is excluded or limited. Other forms specify covered causes. Match the actual exclusions and endorsements to the project.
| Loss or exposure | Policy question |
|---|---|
| Theft or dishonesty | Is theft covered at that location? Does an employee dishonesty, unexplained disappearance or security provision apply? |
| Faulty construction, design or materials | What does the exclusion remove, and does an ensuing-loss provision restore coverage for a distinct covered cause? |
| Wear, corrosion or mechanical breakdown | Are the condition and any ensuing damage treated separately, and is testing covered? |
| Flood, earth movement or water | Which definitions, limits, deductibles and endorsements apply to this cause? |
| Fire or wind | Does the cause qualify under the form and any location, catastrophe or vacancy conditions? |
| Delay and penalties | Are covered delay-related soft costs or other time-element losses insured? Check for exclusions and waiting periods. |
Suppose the policy excludes the cost of correcting faulty electrical work and has an ensuing-loss exception for a separate covered fire. A contractor must correct miswired connections even if a fire never occurs. If the miswiring starts a fire that damages otherwise covered framing, the ensuing fire damage can qualify under the stated exception. Read the actual wording before classifying any damaged item. A faulty work exclusion without that exception can produce a different result.
Valuation and soft costs
The projected finished value is a limit-setting measure. Actual loss valuation may use covered repair or replacement cost, an actual cash value provision or other stated terms. Check whether profit and change orders are included. Review soft-cost coverage for covered delay, scheduled expense types, amounts and waiting periods. Additional financing interest, professional fees, permit fees or temporary rent are payable only to the extent the form covers those costs and the delay.
Termination, subrogation, and the CGL gap
When coverage begins and ends
Check the effective date, when the insured becomes responsible for the property and when each location is covered. The Zurich 40471 form described by its program administrator begins while the policy is effective once the insured is legally responsible and the other conditions are met. Compare the earliest applicable termination events. Depending on the form, these can include expiration, abandonment, permanent insurance, transfer, acceptance plus payment, or a period after completion or use.
Early occupancy can affect the end date even with no certificate of occupancy. For example, Zurich form 40660 has a 60-day provision after whole or partial occupancy or intended use for specified builders risk coverage, subject to earlier termination events. Do not apply that time to a different form. Coordinate an approved occupancy arrangement and the replacement property coverage before the owner moves in.
Interaction with the owner's policy and the CGL
Use the loss facts and the actual forms to identify the coverage that may apply.
| Policy | Coverage question | Terms to check |
|---|---|---|
| Builders risk | Is there covered physical damage to insured construction property? | Property, locations, valuation, exclusions and duration. |
| Owner’s homeowners or permanent property policy | Does it insure the dwelling, renovation or existing building for this loss? | Construction, occupancy and vacancy terms, valuation and endorsements. |
| Contractor’s CGL | Does the insured face liability for covered damage or injury to another party? | Occurrence, property and work exclusions, and completed-operations terms. |
An unendorsed CGL form can exclude damage to the particular part being worked on during active operations. A separate exclusion applies to certain damage to the insured’s work after completion and has a subcontractor exception in the base form. Damage outside the contractor’s work may involve different facts and terms. As explained in 15.1, the mere fact that a house is under construction does not decide liability coverage.
Waiver of subrogation
When a property insurer pays a covered loss, it may seek recovery using rights held by its insured. A valid waiver can limit those rights for specified parties, loss and amounts. Check the actual contract and whether the property policy permits a pre-loss waiver or needs an endorsement. An AIA-style waiver for insured loss does not settle uninsured loss or establish that a particular trade is protected on a different contract.
Residential custom building: owner's policy vs installation floater
If the contract assigns builders risk to the owner, confirm the issued policy and the contractor’s insured interest. If the contractor must insure an entire project, a materials-only installation floater may be insufficient. An installation floater can insure specified materials in transit, stored or being installed as its terms allow. On an occupied renovation, coordinate it with the policy responsible for the existing building.
Worked scenario: the same fire, two answers
A general contractor is framing a $600,000 custom home. A subcontractor’s torch ignites a fire that damages framing, trusses and stored materials. All damaged items are scheduled at the site. The insurer determines the covered repair loss is $240,000. Assume no insurance-to-value penalty or sublimit applies.
With builders risk: the $600,000 completed-value limit exceeds the covered repair loss. Subtract the $2,500 deductible from $240,000 to get $237,500. If the contract and policy together give the subcontractor a valid waiver for this insured loss, the carrier’s recovery rights against that trade are limited accordingly.
Without that coverage: the same $240,000 remains a project loss. Review the permanent property form, the allocation of loss and insurance duties in the contract, and any potentially covered liability arising from the fire. Determine the affected property and exclusion language before drawing a CGL conclusion. An unsatisfied obligation to insure and a claim against the party that caused the fire are separate questions.
Exam traps
- Distinguish a completed-value limit from repair valuation and any insurance-to-value requirement.
- Confirm any insurer consent needed before occupancy and check events that can end coverage early.
- Check offsite materials, the existing building, contractor tools and resulting damage separately.
- Read the signed waiver with the property policy and distinguish it from liability additional-insured status.
A delivery driver trips over an improperly placed brace at a house under construction. The builder is legally liable for the driver’s bodily injury and damaged watch. A standard CGL Coverage A form applies in the policy period and no exclusion applies to that loss. Which item belongs in the Coverage A analysis?
The cost to replace the contractor’s defective flashing simply to meet the contract.
The insured’s own cost to rebuild its unfinished work after a fire, with no liability claim.
The contractor’s own materials awaiting installation at its yard, with no liability claim.
Damages owed for the delivery driver’s injury and watch.
A construction contract requires protection for the framing subcontractor against the owner’s property insurer pursuing recovery for a covered fire. Which provision addresses that objective if the property policy permits it or is endorsed to allow it?
A valid pre-loss waiver of subrogation expressly covering that subcontractor and insured loss.
An additional insured endorsement on the subcontractor’s own CGL.
A completed-operations endorsement on the owner’s policy.
A valuation clause tied to the completed value.
A $600,000 custom home is about 40% complete when a fire causes $240,000 of covered damage. The builders' risk policy is written on a completed-value basis with a $2,500 deductible, and no coinsurance or margin clause applies. What does the policy pay?
Nothing, because the structure was not complete when the loss occurred
$237,500, because the completed-value limit exceeds the loss and the deductible is subtracted
$240,000, because builders' risk never applies a deductible to a total loss of the structure
$96,000, because payment is prorated to the percentage of construction completed
Sections you finish are checked off in the contents.