22.3 Permits & Inspections from the Plans
Key Takeaways
File with the enforcing agency for that work and address. R106.1 calls for two or more sets, subject to its limited waiver, and R106.1.1 allows electronic media where approved.
At issuance the official approves the documents in writing or marks them reviewed for code compliance. Keep the returned reviewed set available for inspection and the permit or a copy on site through completion (R106.3.1 and R105.7).
An issued permit becomes invalid unless work starts within 180 days after issuance or if work is suspended or abandoned for 180 days after it starts. The official may grant written extensions of up to 180 days each for demonstrated justifiable cause (R105.5).
Michigan requires framing inspection after the roof, framing, firestopping, draftstopping and bracing are in place and the rough plumbing, mechanical and electrical inspections are approved. It requires masonry inspection after base-course flashing and the water-resistive barrier are installed and masonry is complete (R 408.30509).
Coordinate the permit holder’s inspection request, written approvals and the enforcing agency’s final notice. Obtain a certificate before occupying a new dwelling, or a temporary certificate for the approved portion and term.
What Actually Goes In With the Application
Identify the enforcing agency for the property and discipline. Michigan’s Bureau of Construction Codes jurisdiction list distinguishes local, county and state administration for building, plumbing, electrical and mechanical work. When a permit is required for the work, obtain it before starting. Check the scope and exceptions under MCL 125.1510 and the amended R105.2.
- Construction documents and supporting data (R106.1 and R106.1.1). The adopted text calls for two or more sets. An official can waive documents or data that do not require a registered design professional when their review is unnecessary for compliance. Use approved electronic submittal where available. Provide enough detail to show the work and demonstrate compliance. Apply Michigan Article 20 for professional preparation and seals. See the plan-types lesson for the separate practice and seal exceptions.
- Site or plot plan (R106.2). Show new and existing construction and distances from lot lines. A demolition plan identifies the work to be removed and the structures that will remain. The official can waive or modify the site-plan requirement for alteration, repair or when otherwise warranted.
- Truss and bracing information. Rule 506 permits the truss design data sheet with the application in place of the full truss drawings. The individual roof-truss drawings must still be approved before installation and accompany the shipment. Identify the braced wall design, methods, panel locations and lengths, and their foundation requirements where R106.1.3 applies.
- Manufacturer’s instructions and energy details. Keep required installation instructions available at inspection (R106.1.2). Provide proposed insulation, fenestration and other applicable energy information in the construction documents (IECC R103.2). The enforcing agency can identify the worksheet or compliance documents it accepts. The permanent energy certificate records installed values later in the process.
- Fees (R108.1, Michigan Rule 508). Pay the prescribed fees before issuance. Pay any required additional fee before approval of an amendment that incurs one.
MCL 125.1510 governs the permit application and its required information. A property owner building for the owner’s own use and occupancy may qualify for the Article 24 exemption in MCL 339.2403(b). Check any hired party’s applicable license and exemptions separately. MCL 339.2412 addresses proof of licensure during performance when collecting compensation for licensed work in court or imposing a lien.
Review, Stamp and Issuance
The building official examines or arranges examination of the documents for code compliance (R106.3). On approval, the plans are approved in writing or by a stamp reading REVIEWED FOR CODE COMPLIANCE. The official retains one set and returns the other to the applicant. Keep the returned set on site and available to the official or an authorized representative (R106.3.1). The permit itself, or a copy, is kept on the site until the project is complete (R105.7).
The official can require correction of document errors after issuance (R105.4). Resubmit changes that depart from the approved documents as an amended set for approval (R106.4). A phased permit for foundations or another part of the work may be issued on adequate information before the full set is submitted. The permit holder proceeds at their own risk because full approval can depend on the remaining documents (R106.3.3).
If the review identifies an incomplete braced wall layout, an unverified foundation design or a window schedule that disagrees with the energy documents, resolve the item in the affected sheets. Track each accepted revision in the site set.
The Inspection Sequence the Plans Trigger
The enforcing agency periodically inspects permitted construction under MCL 125.1512. Under R109.3 the permit holder or their agent gives notice that work is ready, and the requester provides access and the means for inspection. Rule 509a requires approval before proceeding beyond an inspection. Its notice of noncompliance identifies the code chapter and section in writing. Correct the affected work and keep it visible until authorized to cover it.
| Checkpoint | Authority | Work or evidence to have ready |
|---|---|---|
| Foundation before concrete | R109.1.1 | Required excavations, or poles or piers in place, and any required forms and supported steel. Include applicable thickened slab areas. |
| Foundation before backfill, where required | R109.1.5 and applicable agency schedule | Check foundation drainage and damp- or waterproofing under R405 and R406 as applicable. For example, Livingston County calls for a separate backfill inspection with applicable anchors, drainage and foundation protection in place. |
| Trade rough-ins | R109.1.2 | Inspect plumbing, mechanical, gas and electrical rough-ins before concealment, before appliances or fixtures are set, and before frame inspection. The section has a tested ground-source loop backfill exception. |
| Lowest floor in designated flood hazard areas | R109.1.3 and R109.1.6.1 | Submit sealed elevation documentation on placement of the lowest floor and before further vertical construction. Submit the applicable R322.1.10 documentation before final inspection. |
| Frame and masonry | R109.1.4, Michigan Rule 509 | Frame after the roof, framing, firestopping, draftstopping and bracing are in place and the plumbing, mechanical and electrical rough inspections are approved. Masonry after base-course flashing, the R703.2 water-resistive barrier and masonry are complete. |
| Fire-resistance-rated construction, where required between units or by location | R109.1.5.1 | Check required lath or gypsum before plaster or before the fasteners and joints are finished. |
| Envelope inspection | IECC R104.2.1 and R104.2.2 | Verify applicable foundation insulation and, before interior finish, installed insulation, fenestration and air leakage controls against the approved documents. |
| Final | R109.1.6 and MCL 125.1513 | Complete the permitted work and the required separate sign-offs. The enforcing agency gives the owner or agent at least 12 hours’ notice of a final inspection for the occupancy certificate. |
The adopted masonry inspection rule still refers to old R703.7.5 numbering for base flashing. For the actual anchored veneer flashing detail in the 2015 code, see R703.8.5. Ask the official about checks and documentation needed while work is accessible.
Michigan’s prescriptive envelope test in N1102.4.1.2 applies a maximum of 4 ACH50. Test with a blower door at 50 pascals after all thermal-envelope penetrations are created. The tester signs the report and delivers it to the official. Use a certified independent third party when required by the official. Separately, the builder or registered design professional completes the permanent certificate under N1101.16. Post it on or in the electrical distribution panel without obscuring required labels. It records the predominant installed insulation R-values and fenestration U-factors, using the value that covers the largest area when a component has several values. It also lists the heating, cooling and service-water-heating equipment types and applicable efficiencies. Compare the certificate against installed products and the approved energy documents before final closeout.
Expiration, Extensions and the Certificate of Occupancy
Under R105.5 a permit becomes invalid unless the authorized work is commenced within 180 days of issuance, or if the work is suspended or abandoned for 180 days after it was commenced. The building official may grant, in writing, one or more extensions of not more than 180 days each, and the extension must be requested in writing with justifiable cause demonstrated. Michigan Rule 500 excludes model R105.3.2 on pending applications. Use the enforcing agency’s application procedures and apply R105.5 to permits already issued. If an issued permit lapses, resolve authorization and any fees with the enforcing agency before resuming.
For a new dwelling, obtain the applicable occupancy certificate before use or occupancy (amended R110.1 and MCL 125.1513). An existing use that continued during alteration can continue for 30 days after completion under that statute. R110.3 requires the certificate to state the permit number, the address, the portion covered by the certificate, a statement that the described portion was inspected for code compliance, the official's name, the code edition, and any special conditions. When the building is entitled to an occupancy certificate, MCL 125.1513 requires issuance within five business days after the enforcing agency receives the prescribed written application and fee. The permit holder can request a temporary certificate for a portion that complies with the permit, code and other applicable laws and can be occupied without endangering the health or safety of occupants or users. The official sets a validity period (MCL 125.1513 and R110.4). The official suspends or revokes the certificate in writing when it was issued in error, was based on incorrect information, or the building or covered portion is found in violation (R110.5).
An illustrative house schedule shows how to tie work and approvals to the plans. Check the actual application and inspection scheduling with the enforcing agency.
| Example week | Milestone | Documents in play |
|---|---|---|
| 0 | Application filed | Plans, site plan, truss data, energy worksheet, fee |
| 1–3 | Plan review and corrections | Marked-up set, revised sheets, amended documents |
| 3 | Permit issued | Reviewed set and permit copy kept on site |
| 4 | Footing inspection | Section and footing details, survey elevations |
| 5 | Required check before backfill | Foundation plan, dampproofing and drain details |
| 6–8 | Framing, roof, windows, rough-ins | Framing plan, wall section, window schedule |
| 9 | Frame and applicable masonry checks | Approved drawings, truss drawings, rough-in approvals |
| 10 | Insulation and air sealing checks | Approved energy documents, insulation notes |
| 11 | Final inspection | Energy certificate, applicable test reports and trade sign-offs |
| 12 | Certificate of occupancy | CO issued, job closed out |
The Contractor's Standing Duties
Keep the approved set and permit or permit copy on site. Request checks with the agency’s scheduling instructions and keep work visible through approval. Maintain the inspection records and submit amended documents for departures from the approved set. For example, when the crew proposes a different window for a sleeping room, verify compliance using the product’s documented clear opening, update the affected documents if needed, and reconcile the installation and test records for closing the permit.
A residential building permit is issued on March 1 and no work begins. What happens under R105.5?
The permit expires after 30 days unless the fee is renewed
The permit remains valid for 12 months because residential permits run with the project
The permit expires only when the owner sells the property
The permit becomes invalid after 180 days unless the building official grants a written extension
Under R109.1.4 as amended for Michigan, what conditions must be met before the framing inspection?
As soon as the foundation is backfilled and the floor joists are laid out
After the roof, all framing, firestopping, draftstopping and bracing are in place and the plumbing, mechanical and electrical rough inspections are approved
After insulation and drywall are installed, so the inspector can see the finished assembly
Only at the final inspection, when the certificate of occupancy is requested
Sections you finish are checked off in the contents.