19.3 Elevations & Surveying Instruments
Key Takeaways
For differential leveling, HI = known point elevation + backsight, and the next point’s elevation = HI − its rod reading. Transfer elevation between setups using a stable turning point.
The arithmetic check compares the backsight sum minus the foresight sum with the computed change in elevation. In the worked loop, 21.70 − 21.72 = −0.02 ft, matching 812.48 − 812.50. That agreement checks the notes.
Signed misclosure is the measured closing elevation minus the known closing elevation. Compare its magnitude with the project tolerance. Verify the control and observations if it fails.
Ground contours connect equal elevations. Close spacing means steeper terrain for the same contour interval. Across a typical stream valley the V in ground contours points upstream.
Compare existing and design elevations at the same point and on the same datum to compute cut or fill. Set and check the rotary laser plane against known grades. Verify total-station and GNSS layout with established control.
19.3 Elevations & Surveying Instruments
Setting grades is the part of site work that most directly determines whether water runs away from the house, whether the garage floor sits below the driveway apron, and whether the footing is deep enough. A level transfers elevations from known control. A transit, total station or GNSS setup can also help locate the point horizontally. Choose the instrument and control for the measurement and tolerance the job requires.
The instruments
| Instrument | How it works | Best residential use | Watch out for |
|---|---|---|---|
| Transit level | Manually leveled telescope that can turn horizontal and vertical angles | Elevations plus simple angle turns | Level the instrument and read the appropriate angle circle. |
| Automatic level | Internal compensator automatically establishes a horizontal line of sight | Differential leveling, grade checks, long runs | Center the bubble first. Check the line of sight after a bump or drop. |
| Digital level | Reads a compatible bar-coded rod and can compute or record heights from inputs | Loops where record-keeping and speed matter | Needs the matching bar-coded rod |
| Rotary laser | Rotating beam creates a reference plane, which a detector can find on the rod | Grading, footings, slabs, drainage, single-person work | Use a compatible receiver where the beam is hard to see. Confirm whether the instrument is in level or slope mode. |
| Cross-line laser | Projects level and plumb lines on interior surfaces | Cabinets, tile, ceilings, wall layout | Check operating range and accuracy for the job. |
| Total station | Electronic angle and distance measurement to a prism or, on capable instruments, a suitable surface | Staking corners, offsets, as-built locations | Needs stable control points and careful setup |
| Survey GNSS with corrections | Satellite positioning with project coordinates and an applicable correction service or base | Mapping and layout tied to verified project control | Canopy and reflected signals degrade the fix. Check the coordinate reference and independent points. |
An automatic level’s compensator needs an instrument within its leveling range. A centered bubble alone cannot confirm the line of sight after a bump. In a common two-peg test, read two stable rods from an approximately equidistant setup to establish their difference in elevation. Move the instrument near one rod, calculate the expected reading on the farther rod, and compare it with the measured reading. Follow the particular model’s procedure and tolerance. If the difference exceeds that tolerance, have the instrument adjusted and retested before relying on it.
Backsights, foresights, and the height of instrument
- Backsight (BS): the rod reading on a known starting point or on a turning point whose elevation was carried from the prior setup. It establishes the height of instrument.
- Height of instrument (HI): the elevation of the horizontal line of sight, computed as the reference point elevation plus the backsight.
- Foresight (FS): the last transfer reading before moving the level or closing the run. The closing point may have a known elevation. Subtract a foresight or an intermediate rod reading from HI to calculate the point’s measured elevation.
- Turning point (TP): a stable, identifiable point that carries the elevation forward when the instrument has to move. Its foresight closes one setup and its backsight opens the next.
The two rules never change: HI = elevation + backsight, and elevation = HI − foresight. With the same horizontal sight line and a plumb rod, a larger rod reading indicates a lower point.
A turning point must be something that will not move — the top of a hub with a tack, a brass plate, a concrete curb. Avoid points susceptible to movement, including a stake in soft fill or a loose stone. Keep the rod plumb and reoccupy the same contact point.
A five-setup level loop that reconciles
A crew starts on BM 1 at 812.50 ft, runs around a building pad, and closes back on BM 1.
| Setup | Backsight (BS) | Height of instrument (HI) | Foresight (FS) | Elevation (ft) | Remarks |
|---|---|---|---|---|---|
| 1 | 4.20 on BM 1 | 816.70 | 5.85 | 810.85 | TP 1 |
| 2 | 3.15 on TP 1 | 814.00 | 7.40 | 806.60 | TP 2 |
| 3 | 2.90 on TP 2 | 809.50 | 4.55 | 804.95 | TP 3 |
| 4 | 6.10 on TP 3 | 811.05 | 3.25 | 807.80 | TP 4 |
| 5 | 5.35 on TP 4 | 813.15 | 0.67 | 812.48 | Close on BM 1 |
| Totals | 21.70 | — | 21.72 | — | Misclosure −0.02 |
Work through one line to see the pattern. Setup 1: 812.50 + 4.20 = 816.70, then 816.70 − 5.85 = 810.85 at TP 1. Setup 2 begins from that elevation: 810.85 + 3.15 = 814.00, then 814.00 − 7.40 = 806.60 at TP 2. Each setup repeats the same two operations.
For the arithmetic check, the sum of backsights minus the sum of foresights should equal the computed final elevation minus the starting elevation. Here 21.70 − 21.72 = −0.02 ft, matching 812.48 − 812.50. If those numbers disagree, check the arithmetic and notes. Agreement can occur even when an observation or benchmark is wrong.
For closure, compare the measured closing elevation against the independently known elevation of that benchmark. Here the signed misclosure is −0.02 ft. If this example’s specification allows a magnitude up to 0.03 ft, it passes the closure comparison. With a limit of 0.01 ft, it fails. Use the project’s control procedure for acceptance, any required control adjustment and reporting. A return to the starting benchmark checks the run but cannot detect a wrong elevation assigned to that benchmark.
If closure is outside tolerance, verify benchmark identity and datum, check notes, rod plumb and turning-point stability, then check the instrument and repeat the observations as needed. Limit sight distances and avoid shimmer. Balancing backsight and foresight distances reduces the effect of consistent collimation error. It can also reduce distance-dependent curvature and refraction effects, although unequal atmospheric conditions can leave residual error.
Topographic maps, contours, and spot elevations
A topographic survey represents three-dimensional ground on a flat sheet. The main tool is the contour line, a line connecting points of equal elevation. The contour interval — the elevation difference between adjacent contours, which depends on plan scale and terrain — is stated in the legend.
- At the same contour interval, close lines indicate steeper ground and wider spacing indicates gentler ground.
- Index contours are heavier and labeled with their elevation, so you can count up or down from them.
- In a typical stream valley, a ground-surface contour bends into a V pointing uphill (upstream). Follow the labeled elevations to confirm the direction of fall.
- An unlabeled closed loop needs its neighboring elevations for interpretation. Elevations increasing inward indicate a hill. Inward hachures mark a depression on maps that use that convention.
- On an ordinary site plan with a single ground elevation at each location, read adjacent contours using the stated interval. Where steep faces or special features make lines hard to separate, use spot elevations and field checks.
- Spot elevations are labeled points — often at building corners, inverts, and the existing slab — and provide explicit elevations at those points. Verify critical points rather than estimating them between contours.
For a house site, contours answer three questions quickly: where the high and low ground are, which way water currently drains, and where proposed elevations differ from existing ones. Compare existing and design grades or subgrades at the same points to estimate earthwork.
Grade stakes, offsets, and cut and fill
Elevations become useful when they are converted into instructions for a machine operator. One setup uses a grade stake or a hub and tack paired with a labeled guard stake. Record the point or station, offset and direction, reference elevation or mark, target surface and cut or fill. Set offsets where they can be recovered outside the excavation and document enough other control to replace an offset if it is lost.
For elevations on the same datum at the same horizontal point, use the reference surface for the work stage:
- Cut = existing elevation − proposed elevation (a positive result means dirt comes out)
- Fill = proposed elevation − existing elevation (a positive result means dirt goes in)
At a pad corner with existing ground at 814.20 ft and a proposed subgrade of 815.00 ft, the stake reads F 0.80. Where existing ground is 816.10 ft and the proposed subgrade is 815.00 ft, the stake reads C 1.10 — cut 1.10 ft below the marked point. For this example the mark refers to the measured ground at each target point. An offset hub can have a different elevation. Read the reference and offset information before applying its cut or fill notation.
For a small rectangular pad where the depth changes smoothly across the area and all corners are in cut, average the corner depths for a geometric estimate. A 20-ft by 30-ft pad with corner cuts of 0.4, 0.6, 0.8, and 1.2 ft:
- Average depth = (0.4 + 0.6 + 0.8 + 1.2) ÷ 4 = 0.75 ft
- Area = 20 × 30 = 600 sq ft
- Volume = 0.75 × 600 = 450 cu ft = 450 ÷ 27 = 16.7 cu yd
Two corrections keep that estimate honest. If the estimate is meant to exclude topsoil stripping, use the stripped surface as the cut reference or account for stripping separately. Do not count the same soil twice. The 16.7 cu yd is an in-place estimate. Apply soil-specific volume changes and loading assumptions separately for loose haul quantities or compacted fill.
A rotary laser and compatible receiver can support one-person grade checks. Set the laser on a stable tripod with a clear beam path. At the benchmark, read the receiver on a plumb rod to establish the plane elevation in level mode. At each work point, use the rod reading and target elevation to determine cut or fill. Check the plane against known control before grading and after a disturbance.
For horizontal layout, a total station or a GNSS unit sets corners and offsets from control points. Whatever sets the corners, verify them independently: verify the specified side lengths and both diagonals for a rectangular footprint, use a 3-4-5 triangle to check a right angle, and check setbacks from the surveyed lines. Equal diagonals alone do not establish the size or location of the layout. Tree canopy and reflective surfaces can degrade satellite observations. Use documented site control and an independent check. If GNSS is used for grades, verify the transformation from ellipsoidal height to the project’s vertical reference before comparing elevations.
Interior cross-line and dot lasers belong to finish work — cabinet lines, tile layout, ceiling grid, and door head heights. For exterior grade control, verify the instrument range, beam visibility, reference and tolerance.
A level is set up between BM 1 at elevation 812.50 ft and a ground stake. The backsight on BM 1 is 4.20 ft and the rod reading on the ground at the stake is 5.85 ft. What is the ground elevation at the stake?
806.65 ft
810.85 ft
816.70 ft
822.55 ft
A level loop begins on BM 1 at 812.50 ft and returns to it. The backsights total 21.70 ft and the foresights total 21.72 ft. What are the measured closing elevation and the signed misclosure (measured minus known)?
812.50 ft and zero misclosure
812.52 ft and +0.02 ft
834.22 ft and +21.72 ft
812.48 ft and −0.02 ft
On a ground-surface topographic plan, the contours bend into a V as they cross a stream valley. Which way does the V point?
Downstream, toward lower elevation
Perpendicular to the valley, locating a dam
Upstream, toward higher elevation
North, regardless of slope