31.1 Prior to Concrete Placement

Key Takeaways

  • Under MRC R109.1.1 and amended R109.4, the foundation inspection follows excavation, any required forms and supported reinforcing steel. Obtain approval before placing concrete.

  • Footings bear on undisturbed natural soil or engineered fill. The Michigan baseline for exterior footings and foundation systems is 42 inches below actual grade, subject to approved modifications under R 408.30522.

  • The prescriptive footing and cast-in-place wall provisions use 3 inches of cover for steel cast against earth. Standard sill-plate bolts are at least 1/2 inch in diameter, extend at least 7 inches into concrete or grouted masonry cells, and are spaced at most 6 feet on center, subject to the full R403.1.6 detailing rules.

  • Check the base and vapor-retarder requirements and exceptions independently. Where required, the 6-mil polyethylene or approved retarder goes below the slab with laps of at least 6 inches.

  • At 150 lb/ft³, a 4-foot head of fresh concrete produces an estimated 600 psf at the base under a full-liquid pressure assumption. Use the form design and placement limits for the actual pour.

Last updated: November 2026

Quick Answer: Before releasing a concrete order, check the bearing surface, set and brace the forms, secure the steel and embedments, prepare the specified slab layers, and obtain the required inspection approval.

An anchor bolt that shifts during placement or a footing that loses bearing after a rain can require evaluation and substantial repair. Pre-pour checks give the crew a chance to fix both problems while the work is accessible.

Step 1 — Approve the bearing surface

Every footing and slab delivers load to the ground, so the ground is the first structural element. The residential code requires footings to be supported on undisturbed natural soil or engineered fill (IRC R403.1, adopted through the Michigan Residential Code). Loose backfill, construction debris, root pockets, frozen ground and mud are not bearing material.

  • Elevation and depth. Check the excavation against the plans and Michigan’s general 42-inch minimum below actual grade for exterior footings and foundation systems. Verify applicable frost protection and any depth modification approved under R 408.30522.
  • Bearing inspection. R109.1.1 places the inspection after excavation and installation of any required forms and supported reinforcement. The permit holder or agent requests the inspection. Michigan’s amended R109.4 requires approval before work proceeds past the inspection point. If already covered, coordinate the corrective action with the building official.
  • Water and silt. Dewater using approved controls. Remove sloughed soil and soft silt, and follow the approved bearing restoration detail if excavation goes below plan elevation. Wet soil that still meets the approved bearing requirements is distinct from an unstable or contaminated bearing layer.
  • Frost. Remove snow and ice and thaw frozen supporting soil before placement. Soil that thaws under a load can settle, and ice reduces contact between the concrete and bearing surface.

Step 2 — Check the forms

Forms hold the shape and elevation and resist lateral pressure. For normal-weight concrete at 145 to 150 lb/ft³, a full-liquid head of 4 feet gives 580 to 600 psf at the base. Actual design depends on the form system, placement rate, mix, temperature and consolidation. Check the design, ties, stakes, braces and pour-rate limit before loading the forms.

Check line, plumb and elevation. On a planned rectangle, check side lengths and diagonals. Verify that stakes, anchors and bracing have the support required by the form design. Tight joints retain mortar and help avoid rock pockets and honeycombing. Have significant voids evaluated before selecting a repair.

Apply compatible form release to clean contact faces as directed, and keep it off reinforcing steel and joint faces where bond is needed. Check the top elevation or strike-off guides, then secure blockouts and sleeves so they stay in position.

Step 3 — Verify reinforcement and embedments

Verify bar size, position, laps, support and clear cover before placement. The MRC prescriptive support-and-cover provisions for the covered footing and wall assemblies use 3 inches where concrete is cast against earth. For removable forms exposed to earth or weather, they call for 1-1/2 inches for No. 5 and smaller bars and 2 inches for No. 6 and larger. Check the applicable detail for protected or stay-in-place work and use approved supports that keep the bars fixed. Remove mud, ice, oil and loose material that interferes with bond.

Embedments fail silently, so they get their own pass:

  • Sill anchors. Under R403.1.6, baseline bolts have at least a 1/2-inch diameter, at least 7 inches of embedment and no more than 6 feet between bolts. Check the plate middle third, nuts and washers, and generally two bolts per plate section with one between seven bolt diameters and 12 inches from each end. Check the short-section exceptions and any more restrictive design details. Approved equivalent anchors are another option.
  • Hold-downs, post bases and uplift straps. Use the location, orientation and embedment on the approved plans.
  • Dowels and keyways. Verify these against the joint detail. A keyway profile depends on the design and intended transfer of force.
  • Sleeves, waterstops and isolation-joint filler. Secure them at the specified elevations and orientations before placement.

Step 4 — Slab base, vapor retarder and planned joints

R506.2.2 generally requires a 4-inch graded base for slabs below grade, with a well-drained or qualifying Group I soil exception. R506.2.3 generally places 6-mil polyethylene or an approved retarder immediately under the slab with at least 6-inch laps, over the base or prepared subgrade. Check each section’s exceptions, the approved design and any flooring-specific requirements.

Set planned construction-joint locations and details before placing concrete. Arrange delivery and crew pace to consolidate successive loads together within the placement plan. If an unplanned interruption lets the first lift stiffen, assess the interface and get an approved joint treatment before continuing.

Step 5 — Weather, plant and crew

Hot weather speeds setting and surface evaporation. ACI 305R addresses the combined effects of temperature, wind and humidity. ACI 305.1-14 and ACI 301-20 use 95°F at discharge as their baseline maximum where that specification governs. Check the project limit and have windbreaks, shade, evaporation controls and curing equipment ready.

Cold weather under ACI 306R-16 begins when air temperature has fallen or is expected to fall below 40°F during the protection period. Plan heat, blankets and a suitable mix and clear frozen soil, snow and ice before placing. ACI uses about 500 psi to protect against one early freeze. Repeated cycling in critically saturated concrete requires continued protection to about 3,500 psi. Track the specified protection duration and in-place strength needed for loading or form removal.

Confirm truck access, actual chute reach or pump setup, pour sequence and crew capacity with the supplier. Provide leakproof concrete washout containment and have curing materials on site. Confirm the applicable delivery specification before ordering. The 2015 IRC foundation-wall provision references ASTM C94 or C685, and Chapter 44 lists C94/C94M-13 for ready mix. That edition retained the 90-minute discharge limit with its waiver provision. C94/C94M editions from 2021 use a purchaser–producer time limit. Apply the referenced edition and project terms. Check the mix identification, batch time and water allowances on the ticket and verify any required fresh properties at delivery.

The pre-pour checklist

CheckWhat ready looks likeWhat goes wrong if skipped
BearingFirm undisturbed soil or approved engineered fill at the plan elevationSettlement and cracked footing
FormsAligned, adequately braced and tight, with clean contact facesBulge, blowout, honeycombing or wrong dimensions
ReinforcementCorrect size, spacing, laps, support and coverDisplaced or exposed steel and reduced capacity
EmbedmentsBolts, hold-downs, dowels and sleeves secured to layoutMisaligned or missing connections
Slab layersApproved base and retarder where required, with stated overlapsPoor support, punctured membrane or moisture problems
InspectionRequired inspection completed with approval to proceedWork stops at the inspection point pending correction
WeatherProtection and curing plan readyPlastic shrinkage, freezing or surface damage
DeliveryApproved mix and limits, firm access, confirmed reach and contained washoutBatch rejection, cold joint or runoff

Worked scenario: the footing pour that rains out

The plans show a 60-foot footing, 24 inches wide and 12 inches deep. After 2 inches of weekend rain, the trench has standing water and sloughed sides. When dispatch calls Monday morning about a truck 45 minutes away, hold further loads and coordinate disposition of the dispatched batch with the supplier.

Re-check in this order:

  1. Dewater and clean. Pump through suitable sediment controls. Remove the mud and debris down to approved bearing material.
  2. Restore the bearing elevation. If cleanup takes the trench below design grade, follow the approved repair, such as compacted engineered fill where permitted. Have any proposed footing changes approved.
  3. Recheck the forms. Re-establish line and elevation. Check braces and stakes for loss of support in the wet soil.
  4. Reset the steel. Clean the bars, reset displaced supports and measure cover again.
  5. Check the embedments. Verify the bolt and dowel positions after cleanup.
  6. Confirm inspection approval. Notify the inspector of the changed conditions and obtain approval before pouring.
  7. Recheck truck access. Make sure the route can carry the truck and the crew can place the load within the applicable delivery and placement limits.

Once approved, recalculate using the actual dimensions. At the original dimensions, 2 ft × 1 ft × 60 ft = 120 ft³ = 4.44 yd³. If the revised takeoff still gives 4.44 yd³, an illustrative 5% allowance gives about 4.67 yd³. If the supplier sells by quarter-yard increments, round up to 4.75 yd³.

Test Your Knowledge

Under the residential code, when is the foundation inspection made?

A

After trenches are excavated and forms and required reinforcement are in place, but before concrete is placed

B

Immediately after the concrete is struck off and before finishing begins

C

After the forms are removed and the foundation has been backfilled

D

Only after the sill plate is anchored and the first floor is framed

Test Your Knowledge

A footing excavation fills with silt-laden water after two days of rain. The crew pumps it out, leaving about an inch of soft mud on the bearing surface. What is the correct action before placing concrete?

A

Pour immediately, because heavier concrete will displace the mud

B

Add 2 inches of concrete to the footing to compensate for the soft layer

C

Remove the softened material down to firm bearing soil, restore the elevation with compacted approved material, and re-request inspection

D

Lay the vapor retarder over the mud and pour on top of it

Test Your Knowledge

For ordinary prescriptive wood sill-plate anchorage to a concrete foundation using bolts, what are the baseline bolt diameter, embedment and maximum spacing under R403.1.6?

A

3/8 inch diameter, 4 inches of embedment, spaced 4 feet on center

B

1/2 inch diameter, 7 inches of embedment, spaced no more than 6 feet on center

C

5/8 inch diameter, 10 inches of embedment, spaced 8 feet on center

D

1/2 inch diameter, 12 inches of embedment, spaced 4 feet on center