18.1 The Construction Lien Act: Notices & Deadlines

Key Takeaways

  • Under MCL 570.1107, eligible contractors, subcontractors, suppliers and laborers can claim a lien for an improvement. The claimant’s own contract amount less payments limits its lien. Identify the property interest and any residential licensing and written-contract requirements.

  • Section 108 governs recording for nonresidential improvements. Section 108a instead requires a residential response within 10 days of mailing a proper certified-mail request with the supplied blank forms. Nonoccupants who receive those blank forms must post the completed notice.

  • Under §109, 20 days from first furnishing is the ordinary subcontractor and supplier rule. Laborers use separate wage and fringe-benefit clocks. A contractor dealing directly with an owner or lessee is exempt for liens arising from that contract.

  • Record within 90 days of last qualifying furnishing and serve the recorded claim within 15 days after recording. Keep proof of the applicable furnishing notice and proof of service of the recorded claim for separate filing steps.

  • MCL 570.1119 generally assigns equal priority among construction liens. The ordinary priority marker is the first actual physical improvement. Special design-professional notices and prior mortgage advances have separate rules.

Last updated: November 2026

A lien created by statute

The Construction Lien Act, 1980 PA 497, took effect January 1, 1982. An eligible unpaid claimant can secure its claim against specified property interests. The Act also protects owners through notice and payment defenses. MCL 570.1302(1) permits substantial compliance with Part 1. In Vugterveen Systems v Olde Millpond, 454 Mich 119 (1997), the Michigan Supreme Court applied that rule to notice of furnishing while distinguishing clear statutory requirements. Follow the statutory deadlines and forms.

Who holds lien rights

MCL 570.1107(1) gives a construction lien to each eligible contractor, subcontractor, supplier or laborer that provides an improvement. It may reach the interest of the contracting owner or lessee, an owner who subordinated its interest to the construction mortgage, or an owner who required the improvement. The claimant’s contract amount less payments on that contract limits that claim. The combined cap for multiple liens uses the amended owner or lessee contract less qualifying payments made under a contractor’s sworn statement or lien waiver in accordance with the Act (§107(6)).

TermStatutory meaningSection
ContractorPerson who, under a contract with the owner or lessee, provides an improvement to real property570.1103(5)
SubcontractorPerson other than a laborer or supplier who performs part of the contractor's contract under a contract with someone other than the owner or lessee570.1106(5)
SupplierPerson who leases, rents or otherwise provides material or equipment used in the improvement under a contract with a contractor or subcontractor. Design professionals and their §107b subcontractors are excluded570.1106(6)
LaborerIndividual who provides an improvement through personal labor under a contract with a contractor or subcontractor570.1104(7)
DesigneePerson named by the owner or lessee to receive notices; the owner may name himself, but may not name the contractor (a contractor providing only architectural or engineering services is the exception)570.1104(3)
ImprovementResult of labor or material: surveying, engineering, architectural planning, construction management, clearing, demolishing, excavating, filling, building, erecting, altering, repairing, landscaping, paving, leasing equipment, installing fixtures570.1104(6)
Residential structureAn individual residential condominium unit, or a residential building with not more than 2 residential units, plus the land and appurtenances, where the contracting owner or lessee resides or will reside when the work is complete570.1106(4)

The definition of improvement is broad. Design and equipment leasing can count. Actual physical improvement under MCL 570.1103(1) means a readily visible physical change from contracted labor that would alert a reasonable inspector. Surveying, soil borings and testing, plans, drawings and material merely delivered or stored do not establish that marker. Apply the separate design-professional priority provision in §119(6) when relevant.

The unlicensed contractor has no lien and no lawsuit

When Article 24 licensure is required, MCL 339.2412(1) bars a suit to collect compensation without alleging and proving licensure during performance. Subsection (3) bars imposition of a lien where the required license was missing during performance. In Stokes v Millen Roofing Co, 466 Mich 660 (2002), the Michigan Supreme Court rejected an unlicensed roofing company’s lien and its attempt to obtain the compensation through equity. Determine whether the work required licensure before applying the bar.

On top of the licensing bar, MCL 570.1114 imposes a residential paperwork condition: a contractor has no lien on the interest of an owner or lessee in a residential structure unless the improvement was provided under a written contract between the owner or lessee and the contractor, with any additions or amendments also in writing. The contract must contain, in type no smaller than the body of the contract, a statement that residential builders and residential maintenance-and-alteration contractors must be licensed under Article 24 of the Occupational Code (and that electricians, plumbers, and mechanical contractors must be licensed under the Skilled Trades Regulation Act), and — if the contractor is required to be licensed — that the contractor is licensed, including the license number. A handshake remodel can produce excellent work and no lien at all.

The notice of commencement: two different statutes

The Act runs two parallel commencement tracks, and mixing them up is the classic exam error.

Non-residential work: record before you start (MCL 570.1108)

On a commercial or other non-residential project, the owner or lessee contracting for the improvement must record a notice of commencement with the register of deeds for each county where the property is located before any improvements begin. One notice covers one project. The recorded notice must contain the legal description; the name, address, and capacity of the contracting owner or lessee; the fee owner if the contracting party is a land contract vendee or lessee; the designee's name and address; the general contractor, if any; the statutory notice to lien claimants and subsequent purchasers; the preparer's name and address; and the owner's (or agent's) verifying affidavit (MCL 570.1108(2)). A copy of the notice must have a blank notice of furnishing attached, easily detachable, which need not be recorded (1108(3)).

The owner, lessee or designee must supply the notice with the blank form within 10 days after mailing of a qualifying written certified-mail request (§108(5)). A contractor or subcontractor that received the notice has the same deadline on request from its direct subcontractor, supplier or laborer (§108(6)–(7)). The responsible party keeps a conspicuous copy posted during work and provides a copy to the general contractor, if any (§108(8)–(9)). Failure to record or provide the notice on request extends the subcontractor or supplier clock to 20 days after the notice is actually recorded or furnished. The laborer gets the later of the ordinary §109 deadline or 30 days after the notice is actually recorded or furnished (§108(10)–(13)). Specified posting and delivery failures can also cause liability for actual expenses of obtaining the information (§108(14)–(16)). Under §108(17), if the contractor makes the specified certified-mail request after the first improvement and the responsible party fails to comply within 10 days of receipt, the owner’s hold-harmless rights are limited to the extent stated there, with an exception for a claim that compliant payment under a sworn statement could have avoided.

Residential work: prepare, provide, post (MCL 570.1108a)

Under MCL 570.1108a(1), (3) and (5), the contracting owner or lessee must prepare and provide a notice in response to a proper written request. The owner, lessee or designee responds within 10 days after mailing of the certified-mail request. A contractor, subcontractor, supplier or laborer who requests the residential notice from the owner or lessee supplies the blank notice of commencement form with a blank detachable furnishing notice at the time of the request. Section 108’s recording requirement applies to the nonresidential track.

The residential notice includes the legal description, contracting party, fee owner if applicable, designee, general contractor if any and the required caption, preparer, verification and statements to lien claimants and purchasers. It includes the bold homeowner warning under §108a(2)(f). If the owner or lessee does not live at the property and a blank form was received under §108a(5), the owner, lessee or designee posts the completed notice conspicuously during the work. A posting failure exposes the responsible party to the claimant’s actual cost of obtaining the information (§108a(8), (11)).

If a proper request for a residential notice goes unanswered, §108a(9) extends the subcontractor or supplier’s furnishing period to 20 days after the commencement notice is actually furnished. For a laborer, §108a(10) gives the later of 30 days after receipt of the commencement notice and the ordinary deadline under §109. A contractor or subcontractor that received a notice forwards it with the detachable form within 10 days after a qualifying certified-mail request from its direct subcontractor, supplier or laborer. If it did not receive the notice, it must provide the owner or lessee’s name and address (§108a(6)–(7)).

The notice of furnishing (MCL 570.1109)

The notice of furnishing is how a downstream party warns the owner that someone other than the general contractor must be paid. Under MCL 570.1109(1), a subcontractor or supplier must serve it on the designee and the general contractor, if any, as named in the notice of commencement, at the addresses shown, personally or by certified mail, within 20 days after furnishing the first labor or material. If no designee is named, or the designee has died, service goes to the owner or lessee named in the notice. Certified-mail service is complete on mailing. Crucially, a contractor is not required to serve a notice of furnishing to preserve lien rights arising from its contract directly with the owner or lessee — the general contractor's protection comes from its contract, not from a notice.

For laborers, unpaid wages trigger a 30-day period after wages were contractually due. Serve personally or by prepaid first-class mail (§109(2)). Unpaid fringe benefits and withholdings trigger a deadline of the fifth day of the second month after the month in which they were contractually due. Use personal service or certified mail (§109(3)). Serve the designee and any named general contractor, with the named owner or lessee substituted if there is no named designee or that person has died. Observe applicable §108 or §108a extensions. A missed designee notice defeats the lien for the amounts covered by that notice. Missing only the general contractor notice can create liability for actual damages without defeating the lien (§109(7)–(9)).

For a subcontractor or supplier, a late notice preserves rights as to qualifying work and materials after service (§109(5)). Earlier work remains eligible except to the extent the owner or lessee, directly or through another payer, paid the contractor for that claimant’s work pursuant to a qualifying contractor’s sworn statement or lien waiver (§109(6)). Subsection (6) excludes laborers. Track the actual date, amount and documented basis of each qualifying payment.

The claim of lien

Record within 90 days after the claimant last furnishes labor or materials under the contract for the improvement. Record in each county where the affected property lies. The claim is valid only for property it describes in a county of recording (§111(1)). Use substantially the statutory form, with the first and last furnishing dates, legal description, contracting owner or lessee, amount claimed and notarized verification. The contractor, subcontractor or supplier reports the contract amount including extras and payments received. The laborer uses the form’s separate wage and benefit fields (§111(2)). Subcontractors, suppliers and laborers attach proof of furnishing-notice service when applicable (§111(4)). Within 15 days after recording, serve the recorded claim and any recorded proof on the designee, or on the named owner or lessee if no designee was named or that person has died. Serve personally or by certified mail with return receipt requested. Service by certified mail is complete on mailing. Attach proof of service of the recorded claim to any pleading enforcing the lien (§111(5)).

Priority and construction mortgages

Under MCL 570.1119(1)–(3), construction liens generally have equal rank among themselves, subject to subsection (4). They outrank later-recorded interests and later garnishments of the contract debt. Priority ordinarily dates from the first actual physical improvement for the project (§119(6)(a)). The priority date can be the recording of an eligible professional-services contract or subcontract notice under §§107a–107b; if actual physical improvement follows, those notices are effective only from the first actual physical improvement. The separate requirements for claiming and enforcing a lien still apply.

A mortgage recorded before the lien arises generally ranks first, with separate rules for advances after the lien arises (§119(4)). For the general advance protection, the mortgagee receives the contractor’s sworn statement, disburses according to it, and obtains the contractor’s waiver and waivers from the parties who gave furnishing notices. A claimant omitted from the statement is ordinarily subordinate to the advance unless it gave the designee the required notice or recorded the claim first. An advance after notice, a statutory excuse from notice, or recording of the claim is subordinate to that claimant unless the lender first receives a full unconditional waiver or a partial unconditional waiver covering all sums due through a date within 30 days before the advance. Retainage conditional on an additional event is excluded from amounts then due for this purpose (§119(5)).

Deadline table

EventWho actsDeadlineStatute
Record notice of commencement for nonresidential workContracting owner or lesseeBefore improvements begin570.1108(1)
Provide nonresidential notice on qualifying certified-mail requestOwner, lessee or designee10 days after mailing the request570.1108(5)
Provide residential notice on qualifying certified-mail request with blank formsOwner, lessee or designee10 days after mailing the request570.1108a(5)
Post residential notice after receipt of blank form if owner or lessee lives elsewhereOwner, lessee or designeeDuring improvement570.1108a(8)
Serve ordinary furnishing noticeSubcontractor or supplier20 days after first furnishing570.1109(1)
Serve ordinary furnishing notice for wagesLaborer30 days after wages due but unpaid570.1109(2)
Serve ordinary furnishing notice for benefits and withholdingsLaborerFifth day of second month after the month due but unpaid570.1109(3)
Record claim of lienClaimantWithin 90 days after last qualifying furnishing570.1111(1)
Serve recorded claim and any recorded proofClaimantWithin 15 days after recording570.1111(5)
Commence foreclosureClaimantWithin one year after recording570.1117(1)

Two worked dates

Scenario 1. The tile subcontractor last furnishes work for the original improvement on April 10, 2026. Exclude April 10. April contributes 20 days, May 31 and June 30. Day 90 is July 9, 2026. For statutory day counts check the last-day weekend or legal-holiday rule in MCL 8.6. If the claimant records on July 9, the recorded claim must be served by July 24, 2026 and the foreclosure action commenced by July 9, 2027, with lis pendens recorded at commencement. A later warranty visit to re-caulk a joint that adds no value to the completed work does not restart the 90 days. Separately contracted repairs that do improve the property can qualify as an improvement. See Stock Building Supply v Parsley Homes, 291 Mich App 403 (2011).

Scenario 2. Assume the ordinary rule applies. A lumber supplier makes its first delivery on May 4 and properly serves the notice on May 22, 18 days later. This is timely as to furnishing notice. If the supplier serves on June 8, 35 days after the first delivery, later deliveries retain the notice protection. For earlier deliveries, assume the owner paid the contractor for $4,000 of the supplier’s $7,000 in pre-notice material under a qualifying sworn statement or lien waiver. The earlier work can support up to $3,000 after applying §109(6), subject to other lien requirements and defenses.

Test Your Knowledge

A material supplier makes its first lumber delivery to a Michigan residential jobsite. A notice of commencement naming the designee and general contractor was properly provided, and no exception or extension applies. What is the period for serving a notice of furnishing?

A

Within 10 days after the first delivery

B

Within 20 days after first furnishing labor or material

C

Within 30 days after the first delivery

D

Within 90 days after the first delivery

Test Your Knowledge

How does the notice of commencement work for an improvement to a residential structure under MCL 570.1108a?

A

The owner records it with the register of deeds before work begins, exactly as on a commercial project

B

The general contractor records it and pays a state fund fee at the time of recording

C

The building department issues it with the permit, so no written request is required

D

The owner, lessee or designee responds within 10 days after the written certified-mail request is mailed. A requester asking the owner or lessee supplies the blank commencement and furnishing notices.

Test Your Knowledge

Under the ordinary furnishing-notice rules, which claimant has a direct-contract exemption for a lien arising from that contract?

A

A general contractor whose contract is directly with the owner or lessee

B

A material supplier delivering to a subcontractor

C

A laborer owed unpaid wages and fringe benefits

D

A second-tier subcontractor with no direct contract with the owner