25.3 Protection Procedures Prior to Demolition
Key Takeaways
Obtain the demolition permit from the enforcing agency with jurisdiction. LARA identifies state, county and municipal enforcement. Check current application and local site protection requirements.
For ordinary work, submit the MISS DIG notice at least 72 hours before excavation, excluding hours on nonbusiness days, and no more than 14 calendar days ahead. The ticket has a separate period of validity.
Part 91 generally requires an erosion control permit for earth changes of at least one acre or within 500 feet of a lake or stream. Obtain any required approval from the county or municipal enforcing agency and install controls before disturbance.
Notify the utilities, verify approved service shutdown, capping or protection, and document what must remain. The utility or local authority sets details such as the sewer-cap location.
Send ordinary building demolition debris to a facility authorized to accept it. Michigan's Part 115 solid waste rules and Part 55 air rules restrict open burning.
The pre-demolition checklist
Most demolition failures that are not collapses are paperwork and protection failures: a missing disconnect letter, a silt fence installed after the rain, a neighbor's window cracked by a bucket, a sewer left open under the new lawn. Use the checklist to assign responsibilities and document agency-specific prerequisites. Its rows are work packages.
| # | Item | Who confirms it | Evidence in the file |
|---|---|---|---|
| 1 | Demolition permit and any historic district or tree approval | Enforcing agency and any local authority | Permit card, approved site plan |
| 2 | Asbestos and lead survey, with abatement scope if applicable | Accredited inspector, licensed contractor | Survey report, lab results |
| 3 | EGLE asbestos notification, where the facility is covered | Owner or operator | Notice copy, delivery confirmation |
| 4 | Utility disconnect requests and confirmations | Water, gas, electric, sewer authorities | Written confirmations, meter removal tags |
| 5 | MISS DIG dig notice before any excavation | Contractor | Ticket number, locate marks photographed |
| 6 | Soil erosion and sedimentation controls installed | Contractor, applicable enforcing agency | Inspection record, photos |
| 7 | Storm sewer inlet protection | Contractor, municipality | Photos |
| 8 | Traffic and pedestrian control plan, lane closure permit if on a public road | Municipality or county road agency | Approved plan, signage photo |
| 9 | Neighbor notification letters and condition survey of adjacent structures | Contractor | Letters, dated photos, signed acknowledgments |
| 10 | Tree and landscaping protection installed | Contractor | Photos of fencing at the drip line |
| 11 | Site fencing, signage and barricades | Contractor | Photos, sign inventory |
| 12 | Pre-demolition walkthrough with the owner and, where relevant, the code official | All parties | Signed walkthrough form and photo log |
Permits and notifications
The applicable code requires a demolition permit from the enforcing agency with jurisdiction. LARA's jurisdiction list identifies where the state, county or local government enforces the code. Ask that agency which documents it requires, such as an owner's authorization, verification of utility controls or a site plan. Work in a designated historic district can require approval under Michigan's Local Historic Districts Act. A separate preservation review can apply to a federally assisted project. Screen the site for sensitive resources, such as protected vegetation, wildlife or historic material, and coordinate limitations before selecting the staging area.
For ordinary covered demolition, submit the NESHAP notice through EGLE as described in Section 25.2. Covered demolition without asbestos also requires advance notice. Foundation removal that disturbs soil is an earth change. Under Part 91, an erosion and sedimentation control permit is generally required for an earth change of at least one acre or within 500 feet of a lake or stream. Confirm applicable exemptions or local requirements with the county or municipal enforcing agency. Stage controls before disturbance.
Dig notice before the first bucket of soil
Under MCL 460.725, each excavator must submit a MISS DIG notice for ordinary excavation or blasting at least 72 hours ahead and at most 14 calendar days ahead. Start the count at the time of notice during business hours, at 7 a.m. for a notice given earlier on a business day, or at 7 a.m. on the next business day for a notice given after 5 p.m. or on a nonbusiness day. Exclude all hours on nonbusiness days. A Thursday 8 a.m. notice reaches 72 hours Tuesday at 8 a.m. when Thursday, Friday, Monday and Tuesday are ordinary business days and the weekend is excluded. Check the positive responses and resolve missing or unclear markings before excavation.
Tickets are ordinarily valid for 21 days from the listed start date, or 180 days when the notice identifies work extending beyond 21 days. Separate the advance-notice window from ticket validity. Confirm scope or request a new notice when the planned work falls outside the ticket. Retain the ticket and locate evidence. Member facility operators mark their facilities; arrange a separate locate when private lines are outside their responsibility.
Traffic, pedestrians and the public
A demolition on a residential street is a work zone. A dumpster in the roadway, a conveyor of trucks, a machine swinging over the sidewalk and a debris drop zone all interact with children, dog walkers and parked cars.
- Keep the sidewalk open where you can; close it properly where you cannot. A closure on a public street or sidewalk needs approval from the agency that owns the right-of-way, and traffic control is laid out to the Michigan Manual on Uniform Traffic Control Devices.
- Barricade the drop zone. Apply MIOSHA R 408.42034 to the drop path and receiving area. Required barricades are at least 42 inches high and 6 feet back from the opening and receiving area, with warnings at barricaded levels. The rule specifies protection for drops through more than one level and requires an enclosed opening or chute for an interior drop of more than 40 feet.
- Protect employee entrances. MIOSHA Rule 2033 requires a canopy for an employee entrance to a multistory structure being demolished, extending at least 8 feet from the structure and 1 foot past each side of the entrance, with a capacity of 150 pounds per square foot.
- Notify neighbors in writing with the dates, hours, haul route and a phone number. Neighbor notification is good practice everywhere and a local ordinance requirement in some communities; it is also the cheapest way to prevent a complaint-driven stop-work order.
Utility abandonment, step by step
Notify the serving companies and confirm service status before releasing the site. Under R 408.42031 the employer ensures that utilities are shut off, capped or otherwise protected from damage. For example:
- Water: Coordinate the shutoff, meter handling and approved disconnection point with the water utility. A valve inside the work area may leave the service to the building live.
- Sewer: Have the service capped at the location specified by the sewer authority and obtain the required inspection before concealment. A cap protects the public main from debris and limits the entry of groundwater or storm water.
- Gas and electric: Have the serving utilities disconnect their facilities according to their service rules and obtain confirmation. Identify any approved temporary power that remains for the job and verify its protection.
- Other services and fuel: Coordinate removal or protection of communication drops and have tank systems evaluated for the applicable closure or removal procedure before demolition.
Dust, noise and vibration
Dust is controlled with water, not with hope. Wet the structure before and during wrecking, keep a hose or misting head on the working face, wet the debris before it is dumped into the container, and use temporary wind screening on the downwind side. Cutting concrete or masonry with a saw raises respirable crystalline silica; apply MIOSHA Part 690 (adopting the federal construction silica standard). Required controls and any respirator depend on the task and duration under Table 1 or the applicable exposure assessment. Water and dust suppressants must not run to a storm drain; contain the runoff.
Noise is a local ordinance question. Check local restrictions on hours and environmental noise. For worker exposure, MIOSHA Construction Part 680 uses a permissible eight-hour time-weighted average of 90 dBA. If exposure exceeds the applicable limit, use feasible engineering or administrative controls. If those controls leave exposure above the limit, implement a continuing, effective hearing conservation program.
Vibration travels through soil into adjacent foundations. A nearby hydraulic breaker can affect sensitive masonry depending on equipment, soil, separation and building condition. Reduce it by using a smaller breaker, cutting instead of hammering near the line, sequencing heavy work away from the shared wall, and documenting pre-existing cracks with dated photographs before the first blow.
Protecting what stays
- Adjacent structures. Photograph and, where the neighbor agrees, walk the interior of adjacent buildings before work; note cracks, out-of-square doors and settled stoops. On a shared foundation, expose and protect the party wall before the demolished side comes down. Check how soil and neighboring foundations are supported. Rule 2041 distinguishes removal of the retained load before manual demolition from underpinning the adjoining building that a bearing wall supports.
- Trees and vegetation that remain. Fence at the drip line, not the trunk, and keep equipment, spoil and washout out of the root zone. Cutting roots, compacting soil and stockpiling material inside the drip line kill trees slowly and produce claims quickly. Confirm the local tree rules and property boundaries before removing trees or disturbing their root zones.
- Wildlife and historic material. Survey affected structures and vegetation for protected wildlife before demolition. If birds are using a nest, consult the appropriate wildlife office and plan around any applicable protections. If a project subject to federal preservation review uncovers possible archaeological material, stop disturbance at and near the discovery and follow the project's notification plan.
- Lawn, walks, drives and utilities that remain. Protect with plywood tracking pads or mats under the machine and trucks.
- Storm drainage. Provide inlet protection where called for by the erosion plan while maintaining safe drainage.
- Wells and septic systems. Confirm whether each system will remain in service. Arrange compliant plugging for an abandoned well under the Michigan well code and consult the local health department about any onsite septic system that will be taken out of service. Keep the applicable reports and approvals.
Burning and haul-off
Route ordinary demolition debris to an authorized facility. R 299.4128 limits open burning of solid waste and Part 55 air rules further restrict burning. MCL 324.11539 also prohibits burning household waste containing specified materials such as plastic, treated wood or electronics. Separately regulated fire training does not authorize a contractor to burn a debris pile.
Haul-off discipline is protection too: cover loads, sweep the street at the end of each day, keep the container lid closed and off the roadway, and never use a container as a work platform or as a place to put liquid wastes, tires, appliances with refrigerant, or anything with a battery.
Site security and the walkthrough file
Secure the perimeter and post the signs required by the site protection plan and the applicable authorities. Match the barriers to the exposures at the site. Secure the site at the end of every day: no open excavations, no unbraced wall left standing, no ladder or machine key left accessible. An open basement is an attractive nuisance and a lawsuit waiting for a curious kid on a Saturday.
The last protection step is documentation. A pre-demolition walkthrough with the owner, the code official where the municipality sends one, and photographs of every adjacent structure, tree, sidewalk crack and driveway apron creates the baseline that settles the argument three weeks later. Combine it with the permit, the surveys, the notices, the disconnect confirmations, the dig ticket, the SESC inspection and the daily site log. The file is the protection; the fence is only the visible part of it.
A crew plans to start foundation excavation Tuesday at 8 a.m. Thursday, Friday, Monday and Tuesday are ordinary business days and the intervening weekend is excluded. Which MISS DIG notice meets the advance timing rule?
Call 811 on Monday morning before the machine starts
Submit the notice no later than Thursday at 8 a.m. and no more than 14 calendar days before excavation.
Submit a notice 30 days in advance and wait for written approval from every utility
No notice is needed because the excavation is on private property
How is the sanitary sewer properly abandoned when a house is demolished?
Have the lateral capped at the point specified by the sewer authority and obtain any required inspection before covering it.
A rag or plug is pushed into the basement floor drain
The line is left open so groundwater can drain away from the foundation
The line is filled with demolition debris and covered during grading