33.1 Concrete Formwork

Key Takeaways

  • For a 4-ft liquid head of fresh concrete at 150 lb/ft³, base pressure is 600 psf, with pressure decreasing toward the top. Check the form system and placement assumptions.

  • ACI 347R recommends 2.0 for new form ties based on ultimate strength. MIOSHA Table 1 uses 1.5 only for qualifying light, low-hazard formwork and 2.0 for taller, hazardous or architectural work. Compare working ratings with working demands.

  • ACI 347R addresses construction live load, all vertical and lateral forces, and full concrete head plus at least 25% for surge when pumping from the base.

  • MIOSHA R 408.42522 allows complete removal when the concrete can support its own weight and present loads and the specified removal or documented test path is satisfied. Follow the approved sequence and qualified-person release requirements.

  • Check project tolerances and clean the contact face before applying a compatible release product. Keep release material off reinforcement and joint faces.

Last updated: November 2026

Quick Answer: Use a form system sized and braced for the loads during placement. Check its bearing, ties and placement limits. Complete removal depends on the project’s conditions and the concrete’s capacity at the time of stripping.

A wall form can move during a pour even if it was straight at setup. Verify the tie layout, connections and placement rate against the approved system before loading it.

What Formwork Has to Do

A form system performs four jobs at the same time:

  1. Shape the concrete to the dimensions and section shown on the drawings, including chamfers, reveals and blockouts.
  2. Support the weight of plastic concrete, reinforcing steel, embedded items and the formwork itself.
  3. Resist pressure from concrete that behaves like a heavy liquid until it stiffens.
  4. Hold alignment so the wall stays plumb, straight, at the correct elevation and square to adjoining walls while all of the above is happening.

The Parts of a Wall Form

In a conventional tied wall form, sheathing, studs, walers and ties transfer the concrete pressure. Bracing and anchors complete the temporary load path.

ComponentFunction in the system
SheathingShapes the face and transfers pressure to supporting members
Studs or panel stiffenersSupport the facing and deliver load to walers or the designed supports
WalersCollect reactions from studs and distribute load to ties or other supports
StrongbacksStiffen and align the form as detailed
Ties and space holdersResist separation and maintain the designed wall thickness
Braces and kickersMaintain position and resist forces such as wind, placement impact and unbalanced loading
Stakes, anchors and bearing supportsTransfer loads from the forms and braces into adequate supporting material

A snap tie has a break-back detail that leaves a recess for the specified patch. Use the actual component’s installation method and capacity for the system.

Form Materials

MaterialSelection considerations
HDO concrete-form plywoodCoated facing for repeated use or a smooth finish. Verify rating and condition.
MDO concrete-form plywoodA matte face where suitable. Verify the marking and attachment.
Dimensional lumberRated studs, walers or bracing of the specified grade and condition
Aluminum or steel panelsModular systems with rated connections, facing and release procedure
Insulated concrete formsStay-in-place forms. Verify bracing, lift and placement-rate limits for the system.

Check the capacity of the assembled system at the planned load and placement rate. MRC R404.1.3.3.6 and R608.5.3 require adequate form and tie strength in their respective applications.

What the Forms Are Fighting: Design Loads

For a full liquid head, lateral pressure increases with depth at the unit weight of the fresh concrete. For an illustrative 150 lb/ft³ mix and a 4-ft head:

150 lb/ft³ x 4 ft = 600 lb/ft² at the base, tapering to zero at the top of the pour.

ACI 347R’s permitted pressure models depend on mixture, temperature, rate, slump and vibration. Check when full head applies, including SCC unless a qualifying alternative is justified. Follow the system’s placement limit. Base pumping calls for full head plus at least 25% for surge under the guide, with pressure controlled during pumping.

Other loads add to the lateral pressure:

  • Dead loads: formwork, fresh concrete, reinforcement and embeds.
  • Construction live loads: ACI 347R §4.2.1 recommends at least 50 psf on horizontal projection in the usual case, or 75 psf for motorized carts, subject to the guide’s stated scope. The combined unfactored minimum is normally 100 psf, or 125 psf with motorized carts.
  • Other actions: evaluate wind, placement impact, equipment movement, unbalanced loading and horizontal loads on the temporary system.

ACI 347R Table 4.4 recommends a factor of 2.0 for new form ties and hangers based on ultimate capacity. MIOSHA R 408.42517 Table 1 allows 1.5 for ties in light formwork up to 8 ft with no hazard to life. Its 2.0 category covers formwork over 8 ft, hazardous-to-life work and architectural concrete. Use the governing design and component rating and meet the applicable workplace rules.

Worked Example: Demands on a 4-ft Wall Form

A 24-ft-long, 8-inch-thick wall is 4 ft high. Assume full liquid head, a tie tributary area of 2 × 2 ft, studs at 16 inches on center and a simple 2-ft stud span between supports. This checks individual idealized demands. The approved system still needs its other checks.

Step 1 — Base pressure. Use 150 × 4 = 600 psf. It tapers toward the top. For simple conservative component checks, apply the maximum uniformly over the stated tributary area or span.

Step 2 — Tie demand and capacity. The uniform bound gives 600 psf × 4 ft² = 2,400 lb working tension. With an assumed ultimate-to-working factor of 2.0, minimum ultimate capacity for this check is 4,800 lb. A tie rated at 3,000 lb working capacity meets this tie-only demand if its rating applies to the actual installation. A tie with 3,000 lb ultimate capacity gives only 1,500 lb at the assumed factor and fails this check. For comparison, a 16 × 24-inch tributary area gives 1,600 lb under the same bound.

Step 3 — Stud flexure. At 16 inches on center, a stud takes 600 psf × (16 ÷ 12) ft = 800 lb/ft under the stated bound. For the illustrative simple span:

M = wL² / 8 = 800 x 4 / 8 = 400 lb-ft = 4,800 lb-in.

With an assumed adjusted allowable bending stress of 1,000 psi, the required section modulus is 4,800 ÷ 1,000 = 4.8 in³. With the strong axis in bending, an actual 1.5 × 3.5-inch member has about 3.06 in³ and an actual 1.5 × 5.5-inch member about 7.56 in³. The smaller fails this flexure check. The larger passes this check only. The design must also verify grade and condition, shear, deflection, sheathing, walers, connections, bracing and bearing.

Step 4 — Bracing and bearing. Install the brace angles, spacing, anchors and bearing in the job plan. Confirm the actual support can carry the reactions. Evaluate changes in excavation, rain-softened ground or material substitution before loading.

Step 5 — Placement. Monitor from a safe location. Stop and secure the area if the form moves, ties fail or supports shift. Resume only when the responsible person has confirmed the support system and placement plan.

Alignment, Bracing and Tolerances

Use the established layout, elevations and installed ties to check geometry before placement. Check the braces, connections and bearing again if the form is bumped or the ground changes.

Read tolerances by type. A local slope or plane tolerance cannot replace a separate plumb, elevation or alignment requirement.

Where ACI 117-10 §4.8.2 is specified, the ordinary local formed-surface tolerance is ±0.3% over 10 ft, or 0.36 inch over 120 inches. Check its tighter categories and apply the separate plumb provision or project tolerance for global alignment.

Compare the finished surface with the applicable tolerance and measurement procedure. Recheck installed forms during and after placement from a safe access point.

Form Release Agents

Release agents reduce bonding between concrete and the form. Two common mechanisms are:

MechanismApplication consideration
BarrierCoats the face to separate it from the concrete. Verify the product suits the facing and required finish.
Chemically activeReacts at the interface. Compatible products can reduce staining or surface voids in architectural work.

Clean the face and apply the specified release product evenly and at its recommended coverage. Prevent buildup and keep it off reinforcing steel and surfaces that need bond.

Form Removal

Under MIOSHA R 408.42522, complete removal requires a determination that concrete supports its weight and current superimposed loads. Follow the removal conditions in plans and specifications, or the rule’s alternative of documented adequate compressive strength from appropriate ASTM testing. Follow the qualified-person release provisions for shoring and bracing.

ACI 347R recommends project-specific criteria and planned stripping. Side panels and load-bearing soffits can have different conditions:

  • Side panels: check the specified condition for removal, edge damage and the remaining curing or protection plan.
  • Soffits and shores: confirm the required in-place strength, actual stage loads and approved sequence. Field-cured specimens or an approved in-place method can support the determination.
  • Reshores and other temporary supports: use the planned stages and approvals for transferring loads to the structure and releasing supports.

Secure forms handled by lifting equipment before releasing the load line. Strip without damaging the concrete and inspect the result. Evaluate significant honeycomb and use the approved repair.

Reuse, Cleaning and Safety

Inspect reused panels, fasteners and rated hardware for damage, wear and enlarged holes. Use the capacity justified by the design for the actual components. Clean, handle and store the forms as directed by their manufacturer or supplier.

Before placement, verify safe access, form and shore inspections, and how the crew will communicate a stop.

  • Keep current formwork and shoring drawings available and confirm installed components against them.
  • Use the required runways, ramps or platforms for placement and follow MIOSHA access and guarding rules.
  • In the Part 45 formwork-face and reinforcing-steel case, provide the applicable protection against falls of 6 ft or more. Check the separate provisions for openings, platforms and other activities.
  • Keep workers clear of unstable forms and follow the approved monitoring and placement plan.

Formwork Checklist Before the Pour

CheckWhat to confirm
GeometryForms at the design line, elevation, plumb and required dimensions
Load pathSpecified facing, supports, ties, walers and attachments installed
BracingAnchors, spacing and supported bearing match the plan
Clearances and embedsSpacers, sleeves, blockouts and joint hardware secure
Form faceClean, with compatible release and uncontaminated steel and joint surfaces
PlacementApproved lift and rate, access and clear response to movement
RemovalSpecified stripping, protection and support-transfer requirements understood
Test Your Knowledge

A crew is placing a 4-ft-high, 8-in. basement wall in one continuous pass using concrete at about 150 lb/ft³. Using the conservative full-hydrostatic assumption, what lateral pressure must the forms resist at the base of the wall?

A

600 lb/ft²

B

150 lb/ft²

C

1,200 lb/ft²

D

50 lb/ft²

Test Your Knowledge

Assume 600 psf acts uniformly over a tie tributary area of 2 × 2 ft and the design uses the ACI 347R factor of 2.0 on ultimate strength. What minimum ultimate rating meets this tie check?

A

1,200 lb

B

2,400 lb

C

4,800 lb

D

600 lb

Test Your Knowledge

Under MIOSHA Part 25, what must be established before completely removing forms from newly placed concrete?

A

At least 24 hours have elapsed under a statewide minimum.

B

The same seven-day waiting period applies to all assemblies.

C

The inspector has selected a stripping date by measuring wall thickness alone.

D

The concrete supports its own weight and present superimposed loads, as established through the specified removal conditions or the rule’s documented test path.