26.3 MISS DIG & Utility Locates
Key Takeaways
MCL 460.725 generally requires notice 72 hours or more before excavation, excluding nonbusiness days, and no more than 14 calendar days before it.
A MISS DIG ticket is valid for 21 days from the start date shown on the ticket, or 180 days when the notice states the work will not be completed within 21 days.
Within the 48-inch caution zone, locate marked facilities by soft excavation. If full exposure is impractical, agree on protection with the facility owner or operator. Establish the precise location before using power equipment near the facility, and follow any applicable MIOSHA workplace rule.
MCL 460.729(2) protects a complying excavator from responsibility for damage to an improperly marked or unmarked facility, or one determined to be in the safe zone.
Ask who owns and maintains each line. Member operators mark the facilities for which they are responsible. Arrange a separate locate for privately maintained services outside that scope.
The Act, the System and the Call
Michigan's dig law is the MISS DIG Underground Facility Damage Prevention and Safety Act, 2013 PA 174, MCL 460.721 to 460.733, effective April 1, 2014. The act names the notification system itself: MISS DIG System, Inc., a nonprofit corporation formed and operated by facility owners and operators to administer a one-call system (MCL 460.723(v)). 811 is the number, and MISS DIG 811 answers 24 hours a day, 365 days a year.
Three roles are worth keeping straight:
- The excavator — any person performing excavation or blasting covered by PA 174 — must send a dig notice and must dig safely around the marks.
- MISS DIG receives the notice and transmits a ticket to every member facility owner or operator in the area. MISS DIG does not mark anything and is not liable for marking failures (MCL 460.729(1)).
- The facility owner or operator marks its own facilities and posts a positive response.
Ordinary MISS DIG notices are free for the excavator. The act defines excavation broadly — grading, trenching, digging, drilling, boring, augering, tunneling, scraping, cable or pipe plowing, pile driving and demolition — with narrow exclusions for certain farming operations, replacing a fence post or sign post in its existing location, cemetery grave sites, certain landfill operations, and specified railroad and roadway maintenance (MCL 460.723(m)). A residential footing, driveway, deck, fence line, sewer lead or pool is excavation; there is no size or depth threshold.
The notice window: 72 hours, not more than 14 days
An excavator must send a dig notice at least 72 hours, but not more than 14 calendar days, before starting excavation or blasting (MCL 460.725(1)). Business hours under the statute run from 7 a.m. to 5 p.m. Eastern Standard Time on business days. A notice during that window starts the clock immediately. A notice given earlier on a business day starts the clock at 7 a.m. that day, and a notice given after 5 p.m. or on a nonbusiness day starts it at 7 a.m. the next business day. Once counting begins, exclude hours on nonbusiness days. Overnight hours on business days count. The MPSC describes the minimum as three business days. For example, a Thursday 8 a.m. notice can reach 72 hours on Tuesday at 8 a.m., assuming Thursday, Friday, Monday and Tuesday are business days. Observe the ticket's stated legal start and confirm responses.
Every excavator on a site must send its own notice, even when several trades are digging the same hole (460.725(1)). The notice must contain the excavator's name, address and phone; a description of the area including street address and property description; the type of work; the start date and time; and whether the work will be completed within 21 days (460.725(2)).
Ticket life
A standard ticket is valid for 21 days from its listed start date. If the notice states that work will extend beyond 21 days, the ticket is valid for 180 days from the listed start under MCL 460.725(3). Separately, MISS DIG requires a new ticket if initial digging has not started within 14 calendar days of the ticket's legal start date. Under subsection (7), an excavator whose ticket expires before work begins must send a new notice and comply with the advance notice period. Obtain a valid ticket for continued work as well.
Positive response, colors and the caution zone
Before digging, check positive response: check each member response and compare it with conditions in the field. MARKED and NO CONFLICT are ordinary responses. A pending or missing response requires resolution. At the legal start time, notify MISS DIG and stop in the affected area if a missing response or other evidence indicates an unmarked facility.
Facilities are marked with the ANSI uniform color code (MCL 460.727(2)):
| Color | Facility |
|---|---|
| White | proposed excavation area, placed by the excavator |
| Pink | temporary survey markings |
| Red | electric power lines, conduit, lighting |
| Yellow | gas, oil, steam, petroleum |
| Orange | communications, cable TV, alarm and signal |
| Blue | potable water |
| Purple | reclaimed water, irrigation, slurry |
| Green | sewers and drain lines |
Under MCL 460.723(b), the approximate location is a strip at least 36 in wide and no wider than the facility plus 18 in on each side (460.723(b)). For work within the 48-inch caution zone on either side of the facility marks, MCL 460.725(5) requires exposing marked facilities by soft excavation. The statutory definition covers hand digging, careful use of nonmechanical tools, vacuum excavation and pneumatic hand tools. Where complete exposure is impractical, consult the facility owner or operator and agree on protection. When working parallel to a marked line in that zone, use soft excavation at intervals needed to establish its precise location. Power equipment in the caution zone requires exposure or a precise location under subsection (5). The safe zone provision in subsection (15) generally allows power equipment away from the marks without first establishing an exact location, subject to the rest of the Act.
For employees exposing or likely to expose public utility facilities in the settings covered by MIOSHA Rule 931, apply the separate hand digging and support requirements. If a marked facility cannot be found within its statutory approximate location, request additional assistance through MISS DIG under §460.725(8).
Call-to-Dig Timeline, Emergencies and Liability
| When | Action | Authority |
|---|---|---|
| Up to 14 calendar days before start | Describe the site. If the description is insufficient, white-line before notice or provide the reasonably requested help. | MCL 460.725(1), (13) |
| At least 72 hours before ordinary start | Use the business-hour intake rules to start counting. Exclude all hours on nonbusiness days. | MCL 460.725(1) |
| By the ticket's stated start date and time | Each member marks its facilities and posts positive response | MCL 460.727(1), (3) |
| Day before and morning of | Check each status and resolve missing or inconsistent responses before working in the affected area | MCL 460.726 |
| During excavation | Apply caution-zone exposure and precise-location rules, plus any applicable MIOSHA rule | MCL 460.723(f), (aa); 460.725(5) |
| Marks covered or destroyed | Notify the system; for notice received during business hours, the operator re-marks within 24 hours excluding nonbusiness days | MCL 460.727(4) |
| Line not found near the paint | Request additional assistance. The ordinary response is within 3 hours of a business-hours request, subject to timing exceptions or agreement. | MCL 460.725(8); 460.727(5) |
| Day 21, or day 180 for long projects | Ticket validity ends. Plan a replacement notice before continuing. | MCL 460.725(3), (7) |
White lining and design tickets
White lining means the excavator marks the proposed excavation with white paint or flags before sending the notice, so the locator can see the work area (460.723(ee)). If the description is insufficient to identify the tract or parcel, white-line before submitting the ticket or give reasonable requested assistance under §460.725(13).
A design ticket is different: it requests facility information for planning and bidding, has a 10-business-day response time under current MISS DIG ticket guidance. A design response under §460.726a can include marking where records are unavailable. A separate dig notice and applicable excavation responses remain required.
Emergencies
A statutory emergency involves imminent danger and requires immediate excavation or blasting to restore or protect essential services or public transportation. Give prompt emergency notice and proceed only as reasonably required under §460.725(12). The facility owner or operator responds within three hours, or by the listed start if it is more than three hours after notice (§460.727(7)). If damage causes escape of flammable, toxic or corrosive gas or liquid, or endangers life, health or property, call 9-1-1 and notify the facility owner immediately, then take reasonable measures to protect people and the environment until the utility or first responders arrive and take control (460.725(11)).
Damage, penalties and who pays
- Report every contact. An excavator that contacts or damages a facility must notify the owner or operator immediately (460.725(10)).
- Concealment is a crime. Knowingly damaging a facility and failing to notify, or backfilling to hide the damage, is a misdemeanor punishable by up to 1 year in prison, a fine of up to $5,000, or both; willfully destroying marks is also prohibited, except after completion or as an expected consequence of the work (460.731(1)).
- Civil fines. After notice and hearing the Michigan Public Service Commission may impose on a nongovernmental violator a civil fine of up to $5,000 per violation and may also require training (460.731(2)).
- Liability follows compliance. An excavator that complies with the act is not responsible for damage to a facility that was improperly marked, not marked, or located in the safe zone (460.729(2)). Compliance includes responding to unmarked-facility evidence and observing the exposure and protection rules.
- Stop-and-call triggers. Visible evidence of a facility with no marks, a missing positive response, or a member response indicating a facility with no marks each require immediate additional notice and a stop in that area (460.725(9)).
Private lines: the trap that costs the most
The notification system routes tickets to member facility owners or operators. Confirm their ownership and maintenance boundaries. A shed feeder, privately maintained service or yard irrigation line can be outside their locating responsibility. Use records and an appropriate private locating service where needed. Provide support or bracing reasonably necessary to protect the facilities under §460.725(6).
Exam traps
- MISS DIG marks the lines. No: MISS DIG transmits the ticket, and each facility owner marks its own facilities.
- Counting notice time. Count hours on business days after the clock starts, including nights. Exclude weekends and holidays observed by MISS DIG.
- The ticket is good for the season. Twenty-one days from the start date, and 180 days only when the notice declares a longer job.
- Using power equipment near marks. The caution-zone rules require exposure or establishing the precise location before power work, with the separate hand-digging rule for covered workers.
- Locating private facilities. Confirm the operator's marking scope and arrange separate help for services outside it.
- The homeowner called, so I am covered. The excavator sends the notice; if the contractor is digging, the contractor calls.
Under the ordinary MISS DIG advance-notice rule, when must an excavator submit a dig notice?
At least 24 hours and not more than 7 calendar days before excavation
At least 72 hours and not more than 14 calendar days before excavation
At least 10 business days before excavation, with no maximum lead time
At any time before the excavator breaks ground
How long is a standard MISS DIG ticket valid?
7 days from the notice date
14 days from the notice date
21 days from the start date shown on the ticket
One full construction season
Under PA 174, how far does the caution zone extend on either side of the facility marks?
Within 48 inches of either side of the marks
Within 18 inches of either side of the marks
Within 10 feet of the marks
Only where paint happens to be visible