49.1 Foam Board & Fiberboard
Key Takeaways
Use the labeled board thickness and documented test conditions. C578 applies to qualifying EPS and XPS, C1289 to faced polyiso, and C208 to cellulosic fiber insulating board.
Michigan’s R-13 + R-5 option pairs cavity insulation with continuous insulation or qualifying insulated siding. The foundation table has separate entries and geometry.
Check R316.4 thermal protection and applicable exceptions. The attic and crawl ignition-barrier provisions differ.
Identify fiberboard’s intended use. Check the SFB bracing detail when the panel is part of a braced wall.
Use the local termite classification and history. R318.4’s stated foam restrictions and exceptions are distinct from exterior foundation insulation covering requirements.
Choosing Rigid Foam Board
Foam boards can provide a continuous insulation layer over framing. Select the board for its rated thickness, exposure, loads and attachment. The product types and examples below help when comparing submittals.
| Material | How to identify it | Example thermal data |
|---|---|---|
| Expanded polystyrene (EPS) | Molded polystyrene beads. ASTM C578 covers qualifying rigid cellular polystyrene types. | Atlas ThermalStar E+ Type II lists R-4.2 for a one-inch sample at a 75°F mean temperature. |
| Extruded polystyrene (XPS) | Extruded cellular polystyrene board. ASTM C578 also covers qualifying XPS types. | Owens Corning FOAMULAR NGX 250 lists R-5 at one inch under its 75°F, 180-day rating. |
| Faced polyisocyanurate (polyiso) | A closed-cell polyiso core with facers. ASTM C1289 covers faced rigid polyiso board. | Johns Manville AP Foil-Faced lists R-6 at one inch. Its evaluation reports Class I vapor performance at the stated thickness. |
Use the board's rated installed thickness and approved end use. Compressive resistance, water absorption and permeance vary by type, thickness, facer and test conditions. A board specified as insulation is only part of a continuous air or water barrier when the product and detailing support that use. At foundations and under slabs check the product approval for soil contact, the design loads and protection during construction. Use the fastening and joint treatment specified for the assembly.
The FTC home-insulation test conditions generally use a 75°F mean for mass insulation. Aged thermal ratings account for changes in some closed-cell products as blowing gases diffuse. Long-term thermal resistance (LTTR) is a rating determined under the applicable method. Keep the test temperature, conditioning and thickness with the reported value. An in-service assembly may operate at different temperatures and include other heat-flow paths. Compare like ratings and use the accepted assembly value for code calculations.
Michigan Wall and Foundation Applications
- Wood-frame walls. The prescriptive table permits R-20 cavity or R-13 cavity plus R-5 continuous insulation or qualifying insulated siding in Zones 5A, 6A and 7. Continuous insulation reduces bridging through studs and plates. Under footnote f, where structural sheathing covers at most 40 percent of the exterior, the continuous value can be reduced by no more than R-3 in the sheathed locations to maintain a consistent total sheathing thickness.
- Basement walls. Zone 5A is 10/13, meaning R-10 continuous on the inside or outside, or R-13 in a cavity on the interior side. Zones 6A and 7 use 15/19, meaning R-15 continuous or R-19 interior cavity, with R-13 interior cavity plus R-5 continuous also allowed under footnote c. The required insulation runs from the top of the basement wall to the floor or to 10 feet below grade, whichever comes first.
- Unvented crawl spaces. The wall option instead of insulating the floor uses 15/19 in all three zones. Fasten the insulation permanently, from the floor above down to finished grade, then continue at least 24 inches vertically, horizontally or both. Cover exposed soil with a continuous Class I vapor retarder. Lap seams 6 inches and seal them, and extend and attach the edges at least 6 inches up the stem wall where the crawl requirements apply.
- Slab edges. For slab-on-grade floors less than 12 inches below grade, the table lists R-10 with 2 feet of extent in Zone 5A and 4 feet in Zones 6A and 7. Add R-5 at the edge of a heated slab. Start at the top of the slab, with a vertical, under-slab or outward layout as permitted. Cover any outward extension with pavement or at least 10 inches of soil. Check the exception for jurisdictions designated as having a very heavy termite infestation.
Worked Example: A Zone 5A Basement Wall
A conditioned basement has an 8-by-40-foot wall. Its floor is less than 10 feet below grade. With no openings in the example, cover the full 320 ft². A selected 2-inch exterior XPS board labeled R-10 meets the continuous-insulation entry. A thinner board labeled R-7.5 does not. Alternatively, install full-thickness R-13 insulation in the interior frame cavity. The cavity claim and the whole-wall U-factor answer different questions. If the plan moves to Zone 7, use the table's separate 15/19 choices and verify the new product thickness and assembly.
Protection and Vapor Design
Protect exterior insulation on basement walls, crawl walls and slab edges with rigid, opaque, weather-resistant covering over the exposed portion and at least 6 inches below grade. Coordinate the covering with approved foundation drainage and waterproofing or dampproofing. The 6-inch extent of the protective covering and the slab insulation extent are separate dimensions.
Indoors, apply R316.4 unless a specific exception applies. The prescriptive options include at least 1/2-inch gypsum wallboard, 23/32-inch wood structural panel or a material passing both NFPA 275 thermal barrier tests. R316.3 generally sets the foam plastic flame-spread and smoke-developed indices at 75 and 450 with its stated test conditions and approved thickness exception. Check the following before leaving foam exposed:
- R316.5.1 allows at least 1 inch of masonry or concrete to separate the foam from the interior of the specified masonry or concrete wall, floor or roof.
- R316.5.3 and R316.5.4 govern required-access attics and crawl spaces entered only to repair or maintain. Both include options such as 3/8-inch gypsum board, 1/4-inch wood structural panel or 1-1/2-inch mineral fiber. The attic list separately includes 1-1/2-inch cellulose and 1/4-inch fiber-cement panel, soffit or backer board. Follow the applicable list or a specifically approved end-use configuration under R316.6.
- A below-grade location alone does not exempt foam from thermal protection. Where an approved coating is part of the tested assembly, check the coating, board, substrate and thickness conditions.
Select the vapor-control strategy separately. Exterior insulation affects sheathing temperature and drying. Michigan enforces amended R601.3 and its assembly exceptions, including Table R702.7.1. For below-grade assemblies, that rule permits an interior Class III retarder or none, and permits Class I or II where the wall has no air-permeable insulation. Address bulk water before insulating.
Fiberboard Is a Separate Material
ASTM C208 covers cellulosic fiber insulating board. Use the product's listed application, such as wall sheathing or a roof cover or insulation board. Identify damaged or soft material during a retrofit and correct the water entry before replacement. Follow the required water-resistive barrier, flashing and siding attachments for the wall. A generic fiberboard label does not establish structural bracing. If the drawings use the structural fiberboard bracing method (SFB), check the applicable Table R602.10.4 panel, stud spacing and fastening and preserve the required bracing layout when replacing panels.
Termite Protection
Michigan Rule 516 directs the user to Figure R301.2(6) and the jurisdiction's damage history. R318.4 addresses sites classified as having very heavy infestation probability. In that setting it restricts below-grade foam locations, generally requires 6 inches between above-grade foam and exposed earth, and lists exceptions including the interior side of basement walls. Verify the project's applicable classification and approved detail. R318.1 is a separate termite protection provision. Check the drainage and covering details even where the prescriptive very-heavy-infestation restriction does not apply.
The submittal describes a C578 board made by extrusion and a labeled R-5 at one inch. Which material is it?
Molded expanded polystyrene
Extruded polystyrene
Faced polyisocyanurate
Cellulosic fiberboard
What does the Zone 5A basement-wall entry of 10/13 in Michigan Table N1102.1.1 mean?
R-15 continuous or R-19 cavity
R-20 cavity only
R-10 continuous inside or outside, or R-13 interior cavity
R-5 exterior continuous insulation alone
Which of these is an approved prescriptive R316.4 thermal barrier for a foam-board wall facing the interior when no exception applies?
At least 1/2-inch gypsum wallboard
One coat of standard latex paint
A sheet of 6-mil polyethylene
1/4-inch plywood applied directly to the foam