18.2 Sworn Statements & Lien Waivers
Key Takeaways
A contractor gives the owner or lessee a sworn statement at payment due or request and upon a demand by or for either. A subcontractor gives one to the contractor at payment due or request and to the owner or lessee on a qualifying demand.
For a residential structure, give receipt notice to furnishing-notice providers or covered named parties whose notice was excused. Give an entitled requester a copy within 10 business days after receiving the request.
Withholding under §110(7) can support direct payment. When the contract calls for normal progress payments through the general contractor, give at least five business days’ notice before the first direct payment and after a return to that normal practice.
A contract cannot require waivers before work is performed. A conditional waiver takes effect on the stated payment. Use the partial forms for partial payments when retainage remains unpaid.
Verify qualifying residential waivers received indirectly with the named claimant, subject to the laborer-agent rule. A sworn statement alone cannot defeat a required-notice claimant or one excused from notice under §108 or §108a.
The sworn statement: MCL 570.1110
A sworn statement is a notarized accounting of the issuer’s subcontractors, suppliers and laborers with qualifying unpaid amounts. Match it to the actual work, payment request, prior checks and notices.
Who must provide one, and when
- A contractor gives the statement to the owner or lessee when payment is due or requested and when either demands it or a demand is made on their behalf (MCL 570.1110(1)).
- A subcontractor gives it to the contractor when payment is due or requested. A demand by or for the owner or lessee also requires a statement to the owner or lessee, if they complied with the applicable residential receipt requirements (§110(2)–(3)).
- If a contractor omitted the statement before recording, the omission leaves the lien intact but bars payment and filing to enforce it until delivery. For a subcontractor with an outstanding §110(2) statement, the lien also survives and filing to enforce it must wait for delivery (§110(9)–(10)).
What must be in it
List each subcontractor and supplier the issuer contracted with for the improvement and each contracted laborer owed unpaid wages, fringe benefits or withholdings. Use substantially the statutory form, with the property description, payees, contract price, paid and owing amounts and separately itemized unpaid labor amounts. The form has warnings for the owner or lessee and the deponent and is sworn before a notary. Material from the issuer’s existing inventory that was not bought specifically for the contract need not be listed (§110(4)–(5)).
A contractor or subcontractor seeking a draw commits a crime by giving an owner or lessee a required false statement with intent to defraud. On amount alone, under $200 is a misdemeanor with up to 93 days in jail. At $20,000 or more the felony has up to 10 years’ imprisonment. The applicable fine limit at those endpoints is the greater of three times the amount or $500 and $15,000, respectively. Prior convictions can affect the classification and related statements in a scheme may be aggregated within a 12-month period (§110(11)–(14)).
The residential receipt duty
For a residential structure, the owner, lessee or designee gives receipt notice in writing, by telephone or in person to each subcontractor, supplier and laborer that supplied a furnishing notice. If notice was excused under §108 or §108a, give the receipt notice to each such party named in the statement. Give an entitled requester a copy within 10 business days after receiving the request (§110(6)). Use this check to identify discrepancies before payment.
The direct-payment valve
After the statement is provided, the owner or lessee may withhold, and on the contractor’s written demand must withhold, enough from amounts due or to become due for work already performed to cover amounts shown or due to lien claimants who provided furnishing notices. The owner or lessee may directly pay sums shown due from those funds. When the contract ordinarily routes progress payments through the general contractor, give the contractor at least five business days’ notice before the first direct payment. Give notice again if the owner first returned to paying all sums through the contractor. Credit direct payments as payments to the contractor or subcontractor as applicable. On request, provide the contractor or subcontractor an itemized statement of amounts withheld or paid (§110(7)).
One worked draw
On an $84,000 remodel the contract calls for normal progress payments to the general contractor. A $14,000 request includes a sworn statement showing $4,400 owed to the electrical subcontractor, $3,800 to the lumber supplier and $1,200 in unpaid laborer wages. The owner elects direct payment for the first time. With notice to the general contractor at least five business days before the direct payment, the owner may withhold and pay $9,400 to those claimants. That leaves $4,600 from the draw payable to the contractor. The payments are credited against the draw. Keep the payment records and verify the associated waivers.
The limit everyone forgets
Under MCL 570.1110(8) an owner, lessee, designee, mortgagee, or contractor may rely on another party's sworn statement to avoid a claim by a subcontractor, supplier, or laborer only if the claimant failed to provide a required notice of furnishing. A claimant who provided the required notice or was excused from doing so under §108 or §108a can still pursue the claim despite the statement.
Lien waivers: MCL 570.1115
A waiver of lien is the claimant's written surrender of lien rights, and the Act recognizes exactly four forms — partial unconditional, partial conditional, full unconditional, and full conditional — each in a statutory format (MCL 570.1115(9)).
Five rules that decide the questions
- Advance waivers. A contract cannot require a waiver before work is performed. A waiver obtained as part of the contract is invalid except to the extent the signer actually received payment for furnished labor and materials (§115(1)). A promissory note or other evidence of debt alone does not waive otherwise valid rights.
- Full unconditional waiver. The claimant provides it to the owner, lessee or designee upon full payment for the contract (§115(2)).
- Partial unconditional waiver. After partial payment, the claimant provides a waiver for the amount received if the owner, lessee or designee requests it (§115(3)).
- Conditional waivers. A partial or full conditional form takes effect on payment of the stated amount (§115(4)).
- Retainage. For purposes of the Act, retainage contingent on a further event in the contract is not due when the improvement is furnished (§115(5)). Use a partial waiver for a partial payment while a holdback remains, and verify the stated amount and coverage. The full statutory form releases all lien rights once effective.
Section 115(6) makes a waiver effective when a person pays in reliance on it unless that payer already had written notice that the consideration for the waiver had failed. Under §115(7) the owner, lessee or designee on a residential structure must verify a waiver received from someone other than the named claimant if the claimant provided the required furnishing notice or was excused under §108 or §108a. Verify directly with the claimant in writing, by phone or in person, subject to §115(8).
The four statutory waivers
| Waiver | Payment stage | Scope |
|---|---|---|
| Partial unconditional | Partial payment received, provided on request | Stated amount through the stated date. Indicates whether cumulative waivers cover all amounts due through that date |
| Partial conditional | Specific partial payment pending | Same partial scope, effective on payment of the stated amount |
| Full unconditional | Full contract payment received | Releases the claimant’s lien rights against the described property |
| Full conditional | Specific final payment pending | Releases the claimant’s lien rights when the stated payment is made |
Complete the dollar amount and through-date where applicable and retain a copy. A qualifying agent for a laborer or group of laborers normally provides waivers unless the laborer or group gives the designee written notice designating someone else. An individual laborer may also provide a waiver directly (§115(8)–(9)).
The payment packet that keeps everyone whole
For a residential progress draw, the payment file can follow this sequence:
- Application. Submit the agreed schedule of values and measurements.
- Statement. Give the owner or lessee the sworn statement when required. They or the designee handle receipt notices and copy requests under §110(6).
- Conditional waivers. Match each pending payment to its claimant, amount and work. Verify an indirectly received waiver when §115(7) applies.
- Payment. Record the actual payment and paid amount. If using joint checks or statutory direct payment, document the parties and resulting credits.
- Unconditional waivers. A partial unconditional waiver follows actual partial payment on request. Obtain the full unconditional waiver on full payment and reconcile the final statement to any outstanding balances.
In the $14,000 draw example, match the claimants’ waivers to their separate $4,400, $3,800 and $1,200 payments. A partial conditional waiver for the lumber supplier takes effect when the stated $3,800 is paid. A contractor’s waiver does not stand in for the supplier’s waiver.
Traps the exam repeats
- Distinguish a prohibited waiver obtained as part of a contract before work from a conditional waiver for a later, specified payment on work furnished.
- Verify the amount and scope before signing a full form. A holdback that is not yet due calls for a partial form when only part of the contract is paid.
- Keep the sworn-statement defense, indirect-waiver authentication and payment-in-reliance rules separate. Each has its own conditions.
- Document payment. Acceptance of a promissory note alone does not release the lien.
Under MCL 570.1110, when must a contractor provide a sworn statement to the owner or lessee?
Only when the entire project reaches final completion
Only if the contract price exceeds $50,000
When payment is due or requested, and whenever a demand is made by or on behalf of the owner or lessee
Within 90 days after the building permit is issued
A drywall subcontractor properly served a notice of furnishing twelve days after it first furnished labor and is still unpaid. The general contractor gives the owner a clean, notarized sworn statement showing no unpaid subcontractors. May the owner rely on that statement to defeat the drywall subcontractor's lien?
Yes, because a notarized sworn statement is conclusive against every claimant on the project
No, because an owner may not rely on a sworn statement to avoid the claim of a subcontractor, supplier, or laborer who served a notice of furnishing
Yes, but only if the subcontractor's own contract was under $5,000
No, because sworn statements are never admissible in a construction lien action
The contract calls for normal progress payments to the general contractor. After receiving a sworn statement showing unpaid subcontractors, the owner decides to pay them directly for the first time. What notice must the owner give?
No notice at all; direct payment is entirely within the owner's discretion
10 calendar days' written notice to the register of deeds
15 days' notice by certified mail to the owner's designee
At least 5 business days' notice to the general contractor before the first direct payment