37.4 Framing Openings

Key Takeaways

  • Measure header span between the inside faces of the supports. Table R602.7(1) for exterior bearing walls uses supported loads, building width, ground snow load and the specified lumber. Table R602.7(2) is the separate interior bearing lookup.

  • For No. 2 SPF under Table R602.7(1), with a roof, ceiling and one center-bearing floor, 28-foot building width and 30 psf ground snow, two 2x10s span 6 feet 2 inches with two jacks at each end. Two 2x8s stop at 5 feet.

  • Table R602.7.5 counts full-height studs separately from jacks. At the tabulated spans of 3 feet or less, 4, 8, 12 and 16 feet with 16-inch maximum stud spacing, the counts are 1, 2, 3, 5 and 6 per end. The adjacent full-height stud connects to each header end with four 16d end nails.

  • In a nonbearing wall, MRC R602.7.4 permits a single flat 2x4 header for openings up to 8 feet wide where the vertical distance to the parallel nailing surface above is not more than 24 inches, with no cripples required above the header.

  • Minimum rough attic access is 22 by 30 inches when R807.1 applies. Crawlspace access is at least 18 by 24 inches through a floor or 16 by 24 through a wall. General combustible clearances at a masonry fireplace are 2 inches from its front and sides and 4 inches from its back. For a masonry chimney, the general airspace is 2 inches inside the building or within an exterior wall and 1 inch entirely outside.

Last updated: November 2026

Anatomy of a Framed Opening

Where a wall opening interrupts bearing studs, the header and its end supports transfer the load around the opening:

MemberJobCode hook
King studFull-height stud at each side of the opening; ties the wall together and resists lateral loadR602.3, Table R602.7.5
Trimmer (jack) studShorter stud beside the king that supports the header and carries its load to the sole plateTable R602.7(1), R602.7(2)
HeaderBeam spanning the opening; receives loads from aboveTables R602.7(1) to R602.7(3)
Cripple studsShort studs above the header or below a rough sill; above the header they transfer loads to itR602.3
Rough sillHorizontal member at the bottom of a window openingR602.3
Sole and top platesContinue the wall's load path past the openingR602.3.2, R602.3.4

MRC R602.3 requires studs to be continuous from the sole plate to the top plate, with one precise exception: jack studs, trimmer studs and cripple studs at openings in walls that comply with Tables R602.7(1) and R602.7(2) need not be continuous. The exception is conditioned on the tables - which is the code's way of saying that the header and trimmer arrangement must actually be looked up, not improvised.

The header span is the clear distance between the inside faces of its supports. For jack-supported headers above a window, that distance is the structural rough opening width. If those faces are 60 inches apart, read a 5-foot span. Two 1-1/2-inch jacks, one at each end, give an overall header length of 63 inches in that layout. Use the unit’s printed rough opening dimensions to set the jack locations.

Sizing a Header - Table R602.7(1)

Header and girder spans for exterior bearing walls come from Table R602.7(1), which is organized by:

  • what the header supports - roof and ceiling; roof, ceiling and one center-bearing floor; roof, ceiling and one clear-span floor; roof, ceiling and two center-bearing floors;
  • building width - 20, 28 or 36 feet (measured perpendicular to the ridge, with span interpolation permitted for intermediate widths);
  • ground snow load - 30, 50 or 70 psf. Use the 30-psf column for ground snow below 30 psf where roof live load is no more than 20 psf;
  • header size - the sizes listed within that specific load case;
  • required jack studs (NJ) at each end. Where NJ is one, an approved framing anchor attached to the header and full-height stud is permitted. Use No. 1 or better southern pine per ICC’s 2015 errata. The other tabulated species assume No. 2 grade.

Excerpt for 30 psf ground snow (values in feet and inches; the table also carries 50 and 70 psf columns):

HeaderRoof + ceiling: 20 / 28 / 36 ftRoof + ceiling + one center-bearing floor: 20 / 28 / 36 ft
2-2x86'-10" / 5'-11" / 5'-4"5'-9" / 5'-0" / 4'-6"
2-2x108'-5" / 7'-3" / 6'-6"7'-0" / 6'-2" / 5'-6"
2-2x129'-9" / 8'-5" / 7'-6"8'-1" / 7'-1" / 6'-5"

All cells above use two jacks each end, except the roof-and-ceiling 2-2x8 at 20 feet, which uses one. Check the specific span and snow-load cell rather than borrowing a jack count from another column.

Worked example - the 6-foot opening

Conditions: exterior bearing wall, 6-foot clear opening, 28-foot building width, 30 psf ground snow, and roof, ceiling and one center-bearing floor supported above. Assume No. 2 SPF and the other table conditions.

  1. Read the "roof, ceiling and one center-bearing floor" block at 28 feet and 30 psf.
  2. 2-2x8 = 5'-0". The opening is 6'-0". Short by a foot. Reject.
  3. 2-2x10 = 6'-2" with 2 jack studs each end. Passes with 2 inches of margin, which is thin but legal - and a reason to verify the actual clear span before cutting.
  4. 2-2x12 = 7'-1". Passes comfortably and is the choice when the opening might grow.
  5. Alternative: 4-2x8 = 7'-3" with only 1 jack stud each end. A shallower four-ply header can keep more headroom if the assembly and its support fit the wall thickness. Check the full-height studs separately.

Now change one variable: make it a single-story wall supporting roof and ceiling only at the same 28-foot width and 30 psf snow, and 2-2x8 = 5'-11". A 6-foot opening still fails - by one inch. That single inch is a classic exam setup, because a crew that eyeballs "2x8 sounds fine for a window" is wrong in both scenarios.

Interior bearing walls - Table R602.7(2)

Table R602.7(2) removes the snow variable and organizes by building width and number of floors supported. For one floor only, 2-2x10 spans 7'-0" at 20 feet, 6'-1" at 28 feet and 5'-5" at 36 feet, with 2 jack studs each end throughout. An interior bearing header over a 6-foot cased opening in a 28-foot-wide house therefore works with 2-2x10 - and the 2-2x8 entry at that width is 5 feet, which falls short.

Table R602.7(3) covers open porches, keyed to porch depth: 2-2x10 supporting a roof at 30 psf snow spans 12'-4" with an 8-foot porch depth and 9'-4" at 14 feet. Porch headers are not garage-door headers, and the depth variable is what examiners use to separate candidates who actually read the table.

Header Types and Their Supports

Not every opening gets a built-up dimensional header. The code provides four alternatives, each with conditions:

TypeProvisionConditions
Built-up dimensional headerTables R602.7(1) and (2)Plies nailed per Table R602.3(1) item 10: 16d common at 16 inches on center along each edge for a 2-ply header with a 1/2-inch spacer. The 16d box option uses 12 inches on center along each edge.
Single-member headerR602.7.1A single flat 2-inch-nominal member or wall plate not less in width than the studs, above and below the header, face nailed with 10d box nails at 12 inches on center
Rim board headerR602.7.2Size and span per Table R602.7(1); supported at each end by full-height studs, with at least the number displaced by half the header span at the maximum allowable stud spacing. Figure R602.7.2 prohibits a splice over the span, shows a 6-inch extension past the outer full-height stud and calls for joist hangers when bearing is less than 1-1/2 inches. Concentrated loads require design.
Wood structural panel box headerR602.7.3 and Table R602.7.3Panel faces of at least 15/32-inch Exposure 1, 8d common or galvanized box nails at 3 inches on center staggered, jack studs required over 4-foot spans

For a 15-inch-deep box with panel faces on both sides, Table R602.7.3 gives spans of 8 feet at 24- and 26-foot house depths, 7 feet at 28 and 30 feet and 6 feet at 32 feet. A 15-inch box faced on one side is limited to 5 feet at 24 or 26 feet. Those spans assume a one-story house with a clear-span trussed roof or a two-story house whose floor and roof are supported by interior bearing walls. Use continuous plates and keep the stud module for cripples per Figure R602.7.3. The panel face is a single piece, with alternate nails staggered 1/2 inch.

Nonbearing openings - R602.7.4

Load-bearing headers are not required in interior or exterior nonbearing walls. A single flat 2x4 may serve as a header for openings up to 8 feet wide where the vertical distance to the parallel nailing surface above is not more than 24 inches, and in that case cripples or blocking above the header are not required. Measure the clear opening and the distance to the parallel nailing surface above. This detail provides framing at an opening without a bearing load.

King studs and jack studs - Table R602.7.5

Two separate requirements govern the ends of a header:

  1. Jack studs (trimmers) under the header, counted from Table R602.7(1) or (2) - typically 1 to 3 per end.
  2. Full-height king studs beside the opening. The header must be supported at each end on one or more jack studs or approved framing anchors, and the connection from the adjacent full-height stud at each end to the header uses four end nails (16d, 3-1/2 by 0.135 inch). The minimum number of full-height studs at each end of a header in an exterior wall comes from Table R602.7.5:
Header spanStuds each end, 16 in. o.c. wallsStuds each end, 24 in. o.c. walls
3 feet or less11
4 feet21
8 feet32
12 feet53
16 feet64

Notice what this table is really doing: a wide opening removes studs that were bracing the wall and carrying load, so the ends must be built up in proportion to the span. That is why a 12-foot exterior-wall header needs five full-height studs per end at the stated 16-inch spacing or three at 24 inches, separate from its bearing supports.

Cripples, sills and the details that fail inspection

  • Cripple studs above a header continue the stud module so sheathing, siding and drywall have support, and they transfer roof or floor load to the header. Spacing them at the stud layout (16 or 24 inches) is what keeps the exterior plane flat.
  • Rough sills at windows are doubled or single per the opening size and must be level; a sill out of level shows up as a window that will not close.
  • Protect the header supports. Lay out services so jacks and kings stay intact where possible. If a penetration is needed, verify the applicable cut limits, load path and approved stud-shoe detail before cutting.
  • King studs are full height for a reason: they are the lateral continuity of the wall. Shortening one to fit a header turns a braced line into a hinge.
  • Top plate cuts for piping or ducts that remove more than half the plate width in an exterior or interior bearing wall require a galvanized metal tie at least 0.054 inch thick and 1-1/2 inches wide, with eight 10d nails each side, extending at least 6 inches past the opening (R602.6.1). The exception is where wood structural panels cover the entire affected side of the wall.

Rough Openings, Skylights, Access and Chimneys

Rough opening dimensions

Measure the rough opening (R.O.) at the framing. For exterior windows and doors, R609.1 requires the manufacturer’s written installation instructions. Match the model’s opening, sill and flashing detail before framing.

  • Window example. An Andersen 400 Series Tilt-Wash full-frame picture unit listed at 3 feet 1-5/8 inches wide has a minimum rough width of 3 feet 2-1/8 inches. The extra 1/2 inch is for this unit. Verify the separately listed height, since the clearances can differ by dimension and model.
  • Prehung door example. If a selected door schedule calls for a 34-inch rough width and 82-1/2-inch rough height above the finished floor, use those dimensions, not the slab size. If the opening is laid out from a subfloor with 3/4 inch of finish buildup, the header underside is 83-1/4 inches above the subfloor for that detail.
  • Check the finished-floor reference, installation space for shims and square opening dimensions. For a required escape opening, verify clear passage of the installed unit separately.

Recheck the delivered model against the opening schedule before installation.

Skylights

A skylight uses the manufacturer’s roof-opening, attachment and flashing details. Some units fit between the existing rafters or trusses. Verify clear spacing and the installation detail before assuming a member needs alteration.

  • If sawn rafters or ceiling joists are interrupted, R802.9 governs the headers and trimmers. A header of 4 feet or less may be a single member of the same size, with a single trimmer permitted where that header is within 3 feet of the trimmer bearing. Over 4 feet double and size the header and trimmers, and over 6 feet use approved header-to-trimmer hangers.
  • Any roof-truss member or component alteration needs approval from a registered design professional under R802.10.4. Check the design for extra loads at the opening.
  • A curb-mounted skylight uses a compatible curb. A deck-mounted unit has its own fastening and flashing detail. Check the roof slope and model’s instructions.

Attic access - R807.1

Where a building has a combustible ceiling or roof and an attic with at least 30 inches of vertical height over at least 30 square feet, an attic access opening is required. The rough-framed opening must be at least 22 by 30 inches, located in a hallway or other readily accessible location; in a wall it must be 22 inches wide by 30 inches high, and a ceiling access needs 30 inches of unobstructed headroom at some point above it. Measure the attic’s qualifying height from the top of ceiling framing to the underside of roof framing, and the headroom above a ceiling access from the bottom of ceiling framing. Follow R802.9 where members are interrupted and the applicable energy provisions for access through the thermal envelope. If the attic contains mechanical equipment, also check M1305.1.3.

Crawl space access - R408.4

Access must be provided to all under-floor spaces. Openings through the floor must be at least 18 by 24 inches; openings through a perimeter wall must be at least 16 by 24 inches. If any part of a wall opening is below grade, provide an areaway at least 16 by 24 inches with its bottom below the access threshold. Maintain the floor or foundation load path and check equipment-access provisions where applicable.

Fireplaces and chimneys

Framing near a chimney is a clearance problem first and a structural problem second.

ItemRequirementSource
Combustibles at masonry fireplace sides and frontAt least 2 inches clearanceR1001.11
Combustibles at masonry fireplace backAt least 4 inches clearanceR1001.11
Chimney clearance to combustibles inside the building or within an exterior wall2 inches airspaceR1003.18
Chimney located entirely outside the exterior walls1 inch airspaceR1003.18
General masonry firebox minimum depth20 inches (qualifying Rumford exception)R1001.6
Hearth extension, opening under 6 square feet16 inches in front, 8 inches each sideR1001.10
Hearth extension, opening 6 square feet or larger20 inches in front, 12 inches each sideR1001.10
Masonry chimney termination3 feet above the highest point where it passes through the roof and 2 feet above any portion of the building within 10 feetR1003.9

Frame to preserve the required clearance. R1001.11 and R1003.18 contain specific exceptions for listed assemblies and specified adjacent trim or masonry conditions. At a chimney’s floor or ceiling penetration, R1003.19 requires securely fastened noncombustible fireblocking, self-supporting or supported on metal strips or lath at combustible framing. Preserve the airspace elsewhere.

Vents and small penetrations

A duct that fits between studs can often avoid an interrupted stud. It still needs exterior weather detailing and a check of any braced panel, fireblocking and equipment requirements. If cutting is proposed, determine whether the stud, panel or connection is structural before laying out an opening.

R502.8.1 limits the hole in a solid-sawn joist to one-third of actual depth and at least 2 inches of clearance to the top, bottom, other holes and any notch. A 9-1/4-inch-deep sawn joist allows a hole of about 3.08 inches by diameter, so a 4-inch duct needs another route or a designed detail. For a rim member, check its actual role and applicable detail. Use the product rules or specific engineering for an engineered rim assembly.

Whole-house fan openings

Lay out the ceiling grille from the fan manufacturer’s template. For a ducted whole-house fan, first try a compatible grille within a clear joist bay, then verify the fan support and duct route above. An opening that interrupts sawn ceiling framing needs the R802.9 header and trimmer detail. Check separately for an engineered member or roof truss. Where the closure penetrates the thermal envelope, use the specified damper and air-sealing and insulation detail. A whole-house cooling fan with a ceiling grille is a different assembly from a gable or roof attic fan whose opening is in the attic enclosure.

Exam Traps

  1. Header size depends on span AND bearing condition. With roof and ceiling only at a 28-foot width and 30 psf ground snow, the sampled 2-2x8 row covers a 5-foot opening but falls short at 6 feet.
  2. Snow load changes the answer. Higher ground snow can shorten the allowable span. Use the Michigan jurisdiction’s R301.2(5) value and check the table’s load conditions.
  3. Building width changes the answer. 20, 28 and 36 feet are not interchangeable; a wider building means more tributary load on the same header.
  4. Header span is the clear span between trimmers, not the window or door size.
  5. King studs are full height and are counted separately from jack studs; Table R602.7.5 controls the count at each end.
  6. Protect header supports. Try the adjacent bay for services and verify any proposed alteration before cutting.
  7. Nonbearing does not mean anything goes: the flat 2x4 header allowance stops at 8 feet and requires 24 inches or less to the nailing surface above.
  8. For solid-sawn joists, one-third of 9-1/4 inches is about 3.08 inches. A 4-inch route needs another location or a designed detail.
  9. Clearances are not caulk gaps. Two inches at a fireplace side and 2 inches of chimney airspace are measured air, not filled space.
  10. Rough openings come from the manufacturer's sheet, not from a rule of thumb, once the unit is on site.
Test Your Knowledge

A 6-foot clear opening is framed in a 28-foot-wide house at 30 psf ground snow. The exterior bearing wall carries the roof, ceiling and one center-bearing floor. Assume No. 2 SPF and the conditions of 2015 MRC Table R602.7(1). Which listed header works?

A

Two 2x6 plies with one jack stud at each end

B

Two 2x8 plies with two jack studs at each end

C

2-2x10 plies with two jack studs at each end

D

A single flat 2x4 with cripples above

Test Your Knowledge

A 7-foot-wide cased opening is planned in an interior nonbearing partition. The parallel nailing surface is 18 inches above the opening. What does MRC R602.7.4 permit?

A

A single flat 2x4 member as the header, with no cripples required above it

B

A minimum two-ply 2x8 header with one jack stud at each end

C

A minimum doubled 2x10 header sized from Table R602.7(2)

D

No framing at all, because nonbearing walls carry no load

Test Your Knowledge

For an attic with combustible roof or ceiling construction that meets the R807.1 height and area trigger, what minimum rough-framed access opening does that section require?

A

18 by 24 inches

B

20 by 30 inches

C

24 by 36 inches

D

22 by 30 inches