47.1 Flashing, Gutters & Downspouts

Key Takeaways

  • Under MRC R903.2.1, flashing must be installed at wall and roof intersections, wherever there is a change in roof slope or direction, and around roof openings; where flashing is metal it must be corrosion resistant with a thickness of not less than 0.019 inch (No. 26 galvanized sheet gage), and a flashing must divert water away where the eave of a sloped roof intersects a vertical sidewall (the kick-out requirement).

  • R905.2.8.3 allows continuous base flashing or step flashing at a vertical sidewall on a shingle roof. It must be at least 4 inches high and 4 inches wide, with water directed onto the roof or into the gutter. Add counterflashing for an anchored masonry veneer sidewall.

  • Under MRC R903.2.2, a cricket or saddle is required on the ridge side of any chimney or penetration more than 30 inches wide as measured perpendicular to the slope, covered with sheet metal or the same material as the roof covering; unit skylights installed per R308.6 and flashed per the manufacturer's instructions are exempt.

  • For an asphalt-shingle roof, R905.2.8.2 allows open-valley metal at least 24 inches wide meeting Table R905.2.8.2. The open roll-roofing alternative uses qualifying mineral-surfaced stock with an 18-inch bottom ply and a top ply at least 36 inches wide.

  • Under MRC R801.3, in areas where expansive or collapsible soils are known to exist, roof drainage must be collected and discharged to the ground surface not less than 5 feet from foundation walls or to an approved drainage system.

Last updated: November 2026

At a roof penetration or change in plane, flashing restores the drainage path around the joint. Under R903.2 and R905.2.8, identify where water arrives, which layers intercept it and where it exits.

Where the Code Requires Flashing (R903.2 and R903.2.1)

Under MRC R903.2, flashings must be installed in a manner that prevents moisture from entering the wall and roof through joints in copings, through moisture-permeable materials, and at intersections with parapet walls and other penetrations through the roof plane. MRC R903.2.1 Locations then lists the specific triggers:

  • At wall and roof intersections.
  • Wherever there is a change in roof slope or direction (hips, valleys, rakes meeting eaves).
  • Around roof openings (chimneys, skylights, vent pipes).
  • A flashing must be installed to divert water away where the eave of a sloped roof intersects a vertical sidewall — this sentence is the code basis for the kick-out (diverter) flashing covered in Section 47.2.

The material floor is equally testable: where flashing is of metal, it must be corrosion resistant with a thickness of not less than 0.019 inch (No. 26 galvanized sheet gage). Use the specific listing and thickness for a valley lining under Table R905.2.8.2. The valley table has its own material-specific dimensions.

The Differential-Movement Principle

Roof framing and the wall can move differently as wood dries or loads change. The approved detail should shed water across the joint and accommodate that movement.

  • Step flashing separates the sidewall joint into overlapping pieces woven with shingle courses. A deck-fastened step flashing detail leaves the wall leg free to move beneath the drainage plane. Follow the selected shingle and wall system instructions for fastener locations.
  • For anchored masonry veneer, R905.2.8.3 requires base flashing and counterflashing. Lap counterflashing down over the upturned base flashing. Coordinate the veneer support, through-wall drainage and attachment details. Where exterior plaster or adhered veneer is used, integrate base flashing with that cladding’s water and flashing provisions.

Flashing Types and Their Locations

LocationFlashing typeGoverning rule and key numbers
Shingle roof against vertical sidewallStep flashing or continuous base flashing, individual pieces woven with each shingle courseR905.2.8.3: at least 4 inches high × 4 inches wide, with the vertical leg continuous under siding where provided. Direct water onto roof or into gutter.
Downhill end of a sidewall at the eaveKick-out / diverter flashingR903.2.1: divert water away from the eave-sidewall intersection
Chimney or penetration wider than 30 inches (measured perpendicular to slope)Cricket / saddle on the ridge sideR903.2.2: covering is sheet metal or the same material as the roof covering; exception: unit skylights installed per R308.6 and flashed per manufacturer's instructions need no cricket
Chimney front wall, soil stacks, vent pipesBase and cap flashing; bootsR905.2.8.1 (base and cap flashing) and R905.2.8.4 (flashing against vertical front wall, soil stack, vent pipe and chimney per manufacturer's printed instructions)
Open valleyValley metal (or roll-roofing lining)R905.2.8.2: metal lining at least 24 inches wide or qualifying two-ply mineral-surfaced roll roofing with 18-inch bottom / at least 36-inch top
Closed valley (shingled over)Complying smooth roll roofing at least 36 inches wide, an allowed open-valley lining, or the ASTM D1970 membrane alternativeR905.2.8.2
SkylightsUse the skylight flashing detail and check whether the unit skylight exception appliesR903.2.2 exception + R308.6
Eaves and rakesDrip edgeR905.2.8.5 (detailed in Section 47.2)

Under R905.2.8.1 Base and Cap Flashing, base flashing must be corrosion-resistant metal of minimum nominal 0.019-inch thickness or mineral-surfaced roll roofing weighing not less than 77 pounds per 100 square feet, and cap flashing must be corrosion-resistant metal of minimum nominal 0.019-inch thickness. Lap exposed drainage layers to shed water. Follow the approved joint and fastening detail for the material.

Valley Linings and Material Compatibility

Valleys concentrate water from two roof planes, so the code sets its most specific metal schedule here. Under R905.2.8.2, open-valley metal lining must be at least 24 inches wide and comply with Table R905.2.8.2, whose minimums include:

Valley lining materialMinimum (Table R905.2.8.2)
Galvanized steel0.0179 inch, 26-gage, G90 zinc coating
Aluminum0.024 inch
Cold-rolled copper0.0216 inch nominal (16 oz per sq ft)
High-yield copper0.0162 inch nominal (12 oz per sq ft)
Stainless steel28 gage
Zinc alloy0.027 inch
Lead2.5 lb
Painted terne20 lb

Material compatibility is a code requirement, not just good practice: R904.2 requires roof assemblies to be of materials that are compatible with each other. Mixing dissimilar metals in wet contact creates a galvanic couple — the less noble metal corrodes. Classic failures include copper flashing draining onto galvanized-steel gutters (the zinc coating sacrifices itself and the gutters rust) and aluminum gutters under a copper roof. Follow the material-specific R905 provisions and the roofing manufacturer’s fastener instructions for the selected assembly.

Gutters and Downspouts

Separate roof collection from disposal at grade. Under R903.4, a roof that does not slope to drain over its edges needs drains at low points. R903.4.1 addresses emergency overflow where the roof perimeter could trap water if primary drains back up. The applicable storm-drainage sizing provisions use the design rainfall and tributary area. For dwellings where expansive or collapsible soils are known, R801.3 requires controlled discharge to grade at least 5 feet from foundation walls or to an approved system. Verify the outlet with the local authority, particularly for a storm connection or a subsurface disposal system.

Eave gutters collect runoff along the fascia and deliver it to outlets and leaders. K-style and half-round profiles offer different cross sections. Use the selected profile’s capacity, outlet details and hanger schedule. Seamless gutters reduce the number of joints in straight runs, while sectional gutters require attention to lap, sealing and expansion at joints. Keep gutters sloped toward the outlets as specified, and size each downspout for its tributary run.

Worked Example: Gutter Layout for a 1,500 ft² Roof

A symmetric gable has 1,500 ft² in plan and two 40-ft eaves. For this example, assume vertical rain at a stated design rate of 4 in/hr, no contributing walls and one outlet per equal roof plane.

  • Flow. Each plane receives rain on 750 ft² of horizontal projection. At 4 in/hr, the collected volume is 750 × (4 ÷ 12) = 250 ft³/hr. At about 7.48 gal/ft³, each outlet needs about 31.2 gpm of capacity. One outlet serving the whole roof would need about 62.3 gpm. Select the gutter, outlet and downspout together for the calculated rate and approved sizing method.
  • Material area. A 6:12 pitch produces about 1,677 ft² of sloped roof surface for covering quantities. That slope factor does not increase the vertical rainfall in this example. Use the design rainfall and area definition of the applicable sizing method, including any contributing area it requires.
  • Fall and supports. If the selected detail specifies 1/16 inch of fall per foot, a 40-ft run drops 2.5 inches. With assumed 24-inch maximum spacing and hangers at both ends, 480 ÷ 24 = 20 spaces, or 21 hangers. Check the actual product limits near outlets and under snow and ice loads.

Maintenance

Gutter and flashing failures are progressive, so inspection is seasonal work: clean gutters and outlets each spring and fall, verify downspout extensions still discharge well away from the foundation, reseal end caps and seams on sectional gutter, re-anchor hangers pulled loose by ice, confirm kick-outs are intact after any siding or roofing work, and watch for galvanic corrosion staining where dissimilar metals meet. If water pools by the wall, check the discharge point and site grading together.

Test Your Knowledge

Under the general metal flashing provision in MRC R903.2.1, what material and thickness are required?

A

Any corrosion-resistant metal of any thickness, provided both sides are painted

B

Corrosion resistant with a thickness of not less than 0.019 inch (No. 26 galvanized sheet gage)

C

A minimum of 0.024-inch aluminum in every application

D

Not less than 16-ounce copper regardless of where it is installed

Test Your Knowledge

A masonry chimney on an asphalt shingle roof measures 34 inches wide as measured perpendicular to the slope. Under MRC R903.2.2, what is required?

A

No cricket is required, because the code threshold is chimneys wider than 36 inches

B

A cricket is required only when the chimney is wider than 24 inches measured along the eave

C

No cricket, provided the chimney flashing is installed per the shingle manufacturer's printed instructions

D

A cricket or saddle on the ridge side, covered with sheet metal or the same material as the roof covering

Test Your Knowledge

Under MRC R905.2.8.2, what is the minimum width for the metal lining of an open valley on an asphalt shingle roof?

A

24 inches wide, of corrosion-resistant metal listed in Table R905.2.8.2

B

16 inches wide, regardless of the lining material

C

10 inches from the valley centerline each way for all slopes

D

36 inches wide of smooth roll roofing only; metal is prohibited in open valleys

Sections you finish are checked off in the contents.