39.2 Engineered Roof Trusses: Bracing & Uplift

Key Takeaways

  • Metal-plate-connected wood trusses follow ANSI/TPI 1-2014 under 2015 MRC R802.10.2 and Chapter 44. Michigan allows the truss design data sheet at permit application, and requires design drawings approved before installation and delivered with the trusses.

  • Under R802.10.4, obtain approval from a registered design professional before altering a truss. Verify the truss can support any added load that exceeds its design load.

  • Follow the construction documents and individual truss drawings for bracing. When specific bracing requirements are absent, R802.10.3 calls for accepted industry practice, such as the SBCA BCSI guide.

  • With spacing no greater than 24 inches on center, R802.11.1 allows Table R602.3(1) attachment by either the up-to-200-lb uplift check or the separate basic wind, Exposure B, roof pitch and roof span check.

  • Stabilize the first set of trusses and restrain and brace each subsequent truss during erection. Transfer restraint to the completed permanent work before removing the temporary components it replaces.

Last updated: November 2026

A metal-plate-connected wood truss is designed as an assembly of chords, webs and plate joints. Use the individual drawing to find its bearings, design loads, reactions and required member restraint. Read the building plans for the permanent system and connections into the rest of the structure.

Truss Components and Design Documents

  • Top chords support the roof deck and carry roof loads. Bottom chords can support ceiling loads and act as a tension tie in a typical simply supported triangular truss under gravity load.
  • Webs carry forces between the chords. A web may be in tension or compression depending on the design and load case. The metal connector plates transfer forces through the joints.
  • Heel is the joint where the top and bottom chords meet near the end of a typical truss. A truss may also be designed for other bearings. Panel points are joints between members. Use the design drawing for the permitted concentrated load points and required restraint locations.

R802.10.2 requires accepted engineering practice and ANSI/TPI 1 for metal-plate-connected wood truss design and manufacture. Chapter 44 of the 2015 code references ANSI/TPI 1-2014. The truss designer specifies the individual truss. The building designer coordinates support and system bracing with the truss package. The contractor checks the delivered components and provides installation restraint and bracing in accordance with the project documents and applicable guidance.

Michigan’s submittal amendment (R 408.30506) permits the truss design data sheet in Figure R802.10.1 at permit application under R106.1.4. Submit the actual truss design drawings for building official approval before installation. The drawings must also accompany delivery to the jobsite. Check geometry and bearing widths, top and bottom chord live and dead loads, concentrated loads and their locations, controlling wind and seismic loads, reaction forces and directions, and the required connection and restraint details.

R802.10.2.1 gives a limited design scope when snow controls. The building can be up to 60 ft perpendicular to the span and 36 ft parallel to it, up to three stories above grade plane and within slopes of 3:12 to 12:12. The scope is limited to a 140 mph maximum design wind, Exposure B or C and a ground snow load of up to 70 psf. It uses 0.7 times ground snow load to compute roof snow for this application. For example, Michigan Table R301.2(5) assigns 70 psf to Alger County, giving 49 psf for this calculation where the remaining conditions apply. Keweenaw County sites are assigned 90 or 100 psf, depending on township, so the simplified scope does not cover them. Even within the limits, use trusses designed in accordance with R802.10.2.

Handling, Storage and Installation

Keep bundles stable, dry and supported as directed by the supplier. Inspect them for damage to members and connectors before lifting. Use the appropriate spreader, rigging and pick locations for the designed lift. Out-of-plane bending during handling can damage the joints. Follow the manufacturer’s lifting and storage instructions and the applicable BCSI guidance.

Check the placement diagram against the individual drawings for identification, spacing, bearing widths and support locations. Set each truss at the specified bearings and check plumb and alignment. Connect it at the specified locations using the required connector and fasteners. Restrain and brace the trusses as erection progresses. Follow the jobsite restraint and loading instructions before allowing construction material to be staged on them.

Field Alterations and Added Loads

R802.10.4 applies specifically to trusses. Get approval from a registered design professional before a member is cut, notched, drilled, spliced or otherwise altered. R802.7.2 also addresses engineered wood products, including trusses. The specific truss alteration requirement governs this case. For an added load over the truss’s design load, such as equipment in an attic, verify capacity before adding it.

If a duct clashes with a web, hold the cut and coordinate rerouting or an approved alteration. If a chord has already been damaged, keep the area clear of loads, arrange support as needed and obtain the manufacturer’s and design professional’s repair instructions before covering the work.

Temporary and Permanent Bracing (R802.10.3)

Brace the trusses for lateral stability and against rotation in accordance with the construction documents and the individual truss design drawings. When they do not specify bracing, use accepted industry practice such as SBCA’s Building Component Safety Information (BCSI) guide. In the 2018 BCSI edition, B1 covers handling and the first truss, B2 covers temporary restraint and bracing, B3 covers permanent restraint and bracing, and B4 covers construction loading. Later editions organize this guidance differently.

A continuous lateral restraint limits sideways movement of individual chords or webs and helps hold the spacing. Diagonal bracing provides a path that keeps the restrained trusses from leaning or racking together. The system needs the specified restraint, diagonals and anchorage. A truss marked for individual reinforcement may instead use the reinforcement detailed by the design professional.

  1. Check the drawings, placement, supports and truss condition before the lift.
  2. Stabilize the first truss or initial set with the planned anchored supports. Restrain each subsequent truss and install the diagonal bracing as erection proceeds.
  3. Check the top chord, web and bottom chord planes. Follow the planned loading and installation sequence.
  4. Where the design uses the sheathing to restrain top chords, secure the panels and replace temporary restraint progressively according to the installation instructions. Keep restraint in place until the permanent components that replace it are installed.
  5. Finish the web, bottom chord and gable-end connections and bracing required for the assembly. For a gable end frame, verify the detail that transfers its lateral wind load to the building.

Uplift and Connectors (R802.11)

At spacing of 24 inches on center or less, R802.11.1 provides two independent routes to attachment under Table R602.3(1):

  • The uplift force is 200 lb or less.
  • The basic wind speed under the provision is no greater than 115 mph, exposure is B, roof pitch is at least 5:12 and roof span is 32 ft or less.

Use the enforced design criteria and correctly identified wind basis for the project. Michigan Table R301.2(1) and footnote (d) require the applicable wind value and site exposure. A printed wind value alone does not establish eligibility for the second route. Check both routes as applicable. For trusses otherwise use R802.11.1.1: resist the uplift on the accepted truss design drawings or construction documents, using Table R802.11 when applicable or an engineered determination. R802.11.1.2 covers individual rafters and roof system beams. R301.2.1 carries the uplift path through the walls and floors to the foundation.

Worked connection check. Assume an accepted design gives a 30-ft symmetric gable, trusses at 24 inches on center, roof slope 6:12 and Exposure C. The tributary plan area for one end on an interior truss is 2 ft × 15 ft = 30 ft². In this simplified uniform-load example, the design supplies compatible allowable-stress inputs of 30 psf uplift and a 10 psf effective resisting dead-load contribution, both on that plan-area basis. The resulting uplift is (30 − 10) × 30 = 600 lb. This exceeds the force-based allowance, and Exposure C rules out the other allowance. Use the 600-lb demand from the design to select a connection with at least that allowable uplift resistance for the actual load direction, wood and specified fasteners.

For comparison, with the same spacing and Exposure C, a verified reaction of 190 lb qualifies under the force-based route. For a separate example meeting the basic-wind, Exposure B, slope and span limits, the second route does not also require proving that the reaction is 200 lb or less.

Traps to expect

  • Confusing truss spacing with rafter spacing; the drawings govern, even when both say 24 in.
  • Assuming the permit-set review replaces the truss design drawings, when R802.10.1 requires the drawings themselves, approved before installation, and shipped with the trusses.
  • Treating a gable-end truss like an ordinary interior truss.
  • Leaving bottom chords unbraced in an unfinished attic because there is no drywall to brace them.
  • Removing temporary restraints outside the approved handoff to permanent bracing.
  • Cutting a web for a duct and calling a nailed plywood scab a repair.
Test Your Knowledge

Which statement about truss design drawings is correct under the Michigan Residential Code?

A

A manufacturer's catalog page showing the truss profile may be substituted for them.

B

They must be provided to the building official and approved before installation, and they must arrive with the shipment of trusses.

C

They are required only when the roof slope is steeper than 8:12.

D

They are required only for spans longer than 40 ft.

Test Your Knowledge

A plumber wants to cut a truss bottom chord to clear a drain line. What is the correct course of action?

A

Cut the chord and double it with a 2x4 nailed on each side.

B

Cut the chord and nail plywood gussets on both faces of the joint.

C

Hold the cut. Reroute the drain or obtain the registered design professional’s approval and alteration detail before cutting.

D

Notch the top chord instead, because top chords are always in compression.

Sections you finish are checked off in the contents.