42.2 Mortar & Grout Application

Key Takeaways

  • 2015 MRC R606.2.7 ordinarily permits either the code table proportions or ASTM C270-12a property criteria.

  • The tabulated masonry foundation walls require Type M or S. Match the mortar to the actual structural role and exposure.

  • Use TMS 602-13's 2½-hour ordinary mortar limit and its two-hour hot-weather limit. Retemper only while permitted and effective.

  • Distinguish ASTM C476-10 strength-specified conventional grout from proportion-specified and self-consolidating mixes.

  • R606 checks grout space and pour height as well as lift height. A pour over 8 feet uses lifts no higher than 64 inches with special inspection. The building official determines whether the over-64-inch pour requires cleanouts.

Last updated: November 2026

Quick Answer: Mortar beds and bonds masonry units. Grout fills cells and bond beams and embeds reinforcement. Select the mortar under the design and its cited specification. For grout, check the mix, the available space, the total pour and each lift as separate decisions.

Select the mortar and batch it

Mortar creates contact at the bearing surfaces, bonds units and helps resist water at filled, well-tooled joints. The mix needs enough workability to spread and enough water retention to bond. Mortar strength, bond, air content and resistance to moisture all matter. For site-batched cement-lime mortar, use the specified cementitious products, hydrated lime, graded masonry sand and clean water. Measure the ingredients in consistent containers. A bag of masonry cement or mortar cement still needs the specified sand and water. A packaged dry mortar may already contain sand. Check the product before adding anything in the field.

Under 2015 MRC R606.2.7, ordinary unit-masonry mortar follows the proportions in Table R606.2.7 or the property requirements of ASTM C270-12a. The table and laboratory property route establish separate compliance criteria. Surface-bonding mortar, AAC mortar and glass-unit mortar have separate provisions.

Mortar typeMinimum 28-day laboratory average under C270-12a property specificationOne cement-lime batch example, portland cement : lime : sandSelection context
M2,500 psi1 : ¼ : 3One option for the foundation tables beneath grade
S1,800 psi1 : ½ : 4½Another option for those foundation walls, also used in designed structural masonry
N750 psi1 : 1 : 6Common for suitable above-grade work such as anchored clay brick veneer
O350 psi1 : 2 : 9Can be used in some nonbearing interior applications

The lab values describe mortar prepared for the property specification. They are neither the in-wall mortar strength nor a field acceptance limit for mortar sampled from a board. The volume examples all use three parts damp, loose sand for each combined part of cement and lime. For the MRC cement-lime entries, the permitted aggregate ratio is 2¼ to 3 times the combined cement and lime volume. The lime proportion also varies by type. Where the project uses a property specification, qualify the mix under that route instead of imposing the proportion example as a second limit.

R606.2.7.1 requires Type M or S for walls designed using Tables R404.1.1(1) through (4). Under R606.2.7.2, M, S or N is permitted for masonry serving as the lateral-force-resisting system in Seismic Design Categories A, B and C. Under R606.2.7.3, that system in categories D₀, D₁ or D₂ uses M or S portland cement-lime or mortar cement mortar. Check the product and the assembly. Historic repointing requires matching the existing materials and exposure. ASTM C270-12a covers M, S, N and O. A historic recipe called Type K is a separate designation.

Batch example. With 1 ft³ of cement, the selected Type S proportion uses 0.50 ft³ of lime and 4.50 ft³ of damp loose sand. If the quantity of cement changes to 0.75 ft³, use 0.375 ft³ lime and 3.375 ft³ sand. Sand ÷ combined binder = 3.375 ÷ 1.125 = 3. The summed measured volumes are batch inputs. The placed mortar yield is a separate quantity.

TMS 602-13 Article 2.6 A specifies three to five minutes of mechanical mixing for conventional mortar. Use the approved recipe and a consistent sequence. While the mix remains usable, remix and retemper as permitted to restore workability lost to evaporation. Discard mortar that has begun to harden and unused conventional mortar at the applicable time limit. The ordinary outside limit is 2½ hours after initial mixing. Under the Article 1.8 D hot-weather trigger, it is two hours. Glass-unit and other special mortars can have different limits.

Place the units

The 2015 MRC joint default is ⅜ inch, with the starting bed joint on a foundation allowed from ¼ to ¾ inch. Set units against clean bedding surfaces with workable mortar and enough pressure to close the joint. Avoid deep furrows that leave voids. If the unit moves enough to break its initial bond, remove it and relay it in fresh mortar.

For solid units, fill bed and head joints and any interior vertical joints designed to receive mortar. For hollow units, fill bed and head joints in from the face for at least the face-shell thickness. In partially grouted walls, fully bed the cross webs that bound a cell to be grouted under R606.3.5.3. Keep the intended grout column open. Half-unit overlap is a common running bond. R606.3.7.1 calls for one-quarter unit offset or the horizontal reinforcement required by R606.3.7.2. Verify the wall design before changing the bond.

Unit estimate. A nominal 8 × 8 × 16-inch CMU commonly has a 7⅝ × 15⅝-inch exposed face. The 8 × 16-inch module includes the joint, so each unit covers 128 in², or 1.125 units per square foot. A straight 20 × 8-ft wall without openings has 160 ft² and needs 180 unit equivalents before cuts or waste. Check with 15 units per course and 12 courses. With 5% added for this estimate, allow 189 equivalents. Count specials and end conditions from the actual layout.

Select grout and measure the space

2015 MRC R606.2.11 permits grout under ASTM C476-10 or Table R606.2.11. It also permits Type M or S mortar with enough water added to achieve pouring consistency. Follow the approved material specification and placement route. Fine grout uses fine aggregate. Coarse grout adds coarse aggregate and needs a compatible space. ASTM C476-10 conventional grout specified by strength has 8–11 inches of slump and at least 2,000 psi at 28 days. Conventional grout may alternatively be specified by proportions. TMS 602-13 Article 2.6 B separately calls for 8–11 inches for its ordinary conventional grout unless otherwise required. ASTM C476-10 self-consolidating grout uses a separate strength route with slump flow of 24–30 inches and a visual stability index no greater than 1. It is placed without mechanical consolidation where that route is approved. Confirm the governing specification before substituting it on a prescriptive R606 job.

A pour refers to the full height grouted before building additional masonry. A lift is one increment of placement within the pour. The R606.3.5.1 table determines permitted pour height from grout type and space. The following rows use the two different dimensions the table calls for.

Maximum pour in this rowFine, between wythes / hollow cellCoarse, between wythes / hollow cell
1 ft¾ in. / 1½ × 2 in.1½ in. / 1½ × 3 in.
5 ft2 in. / 2 × 3 in.2 in. / 2½ × 3 in.
12 ft2½ in. / 2½ × 3 in.2½ in. / 3 × 3 in.
24 ft3 in. / 3 × 3 in.3 in. / 3 × 4 in.

Measure clear dimensions between protrusions and account for the horizontal projection of the bar diameters in the cross section. The vertical steel area in a hollow cell must be no more than 6% of the grout-space area. Apply the lowest row that covers the planned height. A 10-ft coarse grout pour needs the dimensions of at least the 12-ft row. For a hollow cell that means 3 × 3 inches clear before any added allowance for horizontal bars. It still uses separate lift and inspection limits. A nominal unit size cannot stand in for these measurements.

Place and verify grout under the prescriptive R606 route

  1. Inspect cells, reinforcement and grout barriers before filling. Remove projections of mortar over ½ inch into the grout space and other foreign material. Where the building official requires cleanouts for a pour higher than 64 inches, put them in the bottom course. In solid-grouted masonry space the required openings no more than 32 inches on center. Seal them after inspection and before placement.
  2. Place a thoroughly mixed, cohesive grout by pump or an approved alternative before initial set and within 90 minutes of adding water. Aluminum pipe is excluded.
  3. Use lifts no higher than 8 feet unless total pour height is over 8 feet. For a taller pour use lifts no higher than 64 inches and provide special inspection during grouting. A permitted 10-ft pour can consist of two 60-inch lifts. TMS 602-13 Article 3.5 has its own grout space, lift and consolidation criteria on that design path. Its conditional 12-ft 8-in. conventional lift uses at least four hours of wall curing, 10–11-inch slump and no intermediate reinforced bond beam for the straightforward case. Keep the two design paths separate. Under TMS 602-13 Article 3.5 E, a conventional pour up to 12 inches can be consolidated by puddling or vibration. Above 12 inches, mechanically vibrate and reconsolidate after initial water loss and settlement.
  4. Under R606.3.5.1 consolidate during placement by puddling or mechanical vibration as appropriate. Reconsolidate after the grout loses excess moisture to the masonry and while it can still move. Keep reinforced cells filled solidly. Where work stops for an hour or more, stop the tiers at the same elevation and leave grout 1 inch below the top to form the construction joint.
Test Your Knowledge

The drawings use a 2015 MRC Table R404.1.1 design for a masonry foundation wall. Which mortar types does R606.2.7.1 permit for that wall?

A

Type O only

B

Type N or O

C

Type K only

D

Type M or Type S

Test Your Knowledge

A conventional masonry grout is specified by strength under ASTM C476-10, with no separate high-lift specification. Which slump range applies?

A

8 to 11 inches

B

2 to 4 inches

C

5 to 7 inches

D

12 to 14 inches

Test Your Knowledge

A reinforced CMU wall under the 2015 MRC R606 prescriptive route will receive a 10-ft grout pour and meets Table R606.3.5.1 space requirements. Which placement plan satisfies the lift and inspection requirements?

A

One 10-ft lift with a pump

B

Two 60-inch lifts and special inspection during grouting

C

One 96-inch lift followed by one 24-inch lift with special inspection

D

Two 60-inch lifts without special inspection