19.1 Surveying, Benchmarks & Reference Points
Key Takeaways
A benchmark is a documented physical point with a known elevation. Read the stated datum on each source. NAVD 88 and NGVD 29 values differ by location, and a local assumed elevation needs a verified tie for comparison to either datum.
The height-of-instrument method: HI = benchmark elevation + backsight, and ground elevation = HI − foresight. With BM 812.50 ft, BS 4.20 ft, and FS 5.85 ft, HI is 816.70 ft and the stake elevation is 810.85 ft.
A Michigan professional surveyor retraces the boundary and documents monuments. A topographic survey shows terrain and elevations. Resolve disputed boundaries before staking and read recorded instruments for the terms of easements.
Screen for distinct flood requirements. Part 31 regulates qualifying river, stream and drain work and generally excludes watersheds under 2 square miles at the downstream project limit. Use MCL 324.30301 and .30304 and the applicable wetland rules to determine if activities in a wetland require Part 303 approval.
A 0.5-degree directional error produces roughly 0.87 ft of cross-track offset at a 100-ft station. A +0.02-ft bias in each computed setup elevation difference accumulates to +0.10 ft across five setups. Compare the measured closure with the specified tolerance.
19.1 Surveying, Benchmarks & Reference Points
A house can be perfectly built and still be wrong. If it sits two feet inside the side-yard setback, or the footing is eight inches below the elevation the plan calls for, no amount of good carpentry fixes it. Site engineering answers two separate questions on a residential job: where the work goes on the lot (horizontal control) and how high it goes (vertical control). This section covers the control points behind both answers, who is responsible for them, and how small survey errors become large construction failures.
Who does what
The Michigan professional surveyor retraces boundaries, verifies or sets monuments, records land measurements, and can prepare topographic surveys and certify elevations within the scope of the work. MCL 54.212 reserves preparation of a certified survey map to a professional surveyor licensed in Michigan. The certified map and supporting records provide evidence for the location. If a boundary dispute persists, the parties may need a legal resolution before the layout can proceed.
The contractor works from the verified boundary and grade control. Protect monuments, carry elevations to batter boards or grade stakes, verify dimensions against field conditions, and coordinate MISS DIG before excavation. If a monument lies in the work area, involve the surveyor before disturbance so the location can be documented and any required preservation or reestablishment arranged. Use separate construction offsets that the crew can recover without disturbing the boundary mark.
Benchmarks, datums, and what an elevation is
A datum is the reference surface from which elevations are measured. A benchmark (BM) is a fixed point of known elevation, marked and described so the next crew finds the same height. A turning point (TP) is a stable point read from two instrument setups to transfer an elevation. It can be temporary. Its role is to carry the elevation to the next setup.
| Term | Meaning | Field example |
|---|---|---|
| Datum | Reference surface for all elevations on the project | NAVD 88, or an assumed 100.00 ft |
| Benchmark | Stable, documented mark of known elevation | Brass disk in a bridge abutment |
| Turning point | Stable point for transferring elevation between setups | Top of a hub with a tack |
| Elevation | Vertical position relative to the datum, commonly in feet | 812.50 ft |
| Grade | Ground elevation at a point, or slope when expressed as a ratio or percent | 2% falling away from the foundation |
| Station | Position measured along a baseline | Station 1+25 |
NAVD 88 is the current official orthometric vertical datum listed by NOAA’s National Geodetic Survey. Older plans and flood studies may use NGVD 29. The shift varies by location. Use a documented transformation appropriate to the location, such as NGS VERTCON, and confirm the unit and reference before comparing values.
A project may use an assumed datum by assigning a stable point an elevation such as 100.00 ft and measuring all project differences from it. When a permit or design check involves an outside elevation, such as a flood elevation on NAVD 88, have the project elevations tied to that required reference before comparing them.
For a published benchmark, recover the exact point from its description and stamping and check for evidence of disturbance. Use a second verified control point where available to check the local tie. Document the actual point read, since the cover of a hydrant and its flange, for example, are at different heights.
Monuments and reference points
Boundary corners may be marked with found or set monuments, such as iron pins or capped rebar. For certified surveys, MCL 54.212 requires permanent magnetic corner markers and the specified cap identification, subject to its provisions for existing iron stakes and obstructions. An obstructed corner can be referenced from other monumented corners, with an alternative mark such as a chiseled X when appropriate. Use the bearings, distances and descriptions supplied by the surveyor. Before excavation, photograph the identified marks and set construction reference points outside the work area.
Boundary survey versus topographic survey
Select the survey deliverable for the layout decision. A project can use both types of information on the same sheet.
| Boundary (property) survey | Topographic survey | |
|---|---|---|
| Question answered | Where are the surveyed boundaries? | What is the shape of the ground? |
| Shows | Corners and monuments, bearings and distances, lot area, easements, rights-of-way, encroachments | Contours, spot elevations, benchmark, drainage, trees, visible utilities, existing structures |
| Used for | Setbacks, fence and garage siting, the permit plot plan | Grading, drainage, foundation design, retaining walls, septic layout |
| Typical deliverable | Survey map identifying the surveyed parcel and evidence | Contour map with spot shots and a stated datum |
A mortgage inspection or location sketch prepared for a lender has a different purpose. When a design dimension depends on a lot line, work from control established by the professional surveyor. Consult the deeds, plats and recorded instruments for applicable rights and restrictions.
Floodplain and wetland identification
Site control work also has to answer whether the lot can legally be built on as planned. Two Michigan regulatory programs come up constantly.
FEMA mapping. Use the effective Flood Insurance Rate Map (FIRM), Flood Insurance Study where available, and effective map changes. The Special Flood Hazard Area (SFHA) covers the 1-percent-annual-chance flood. A base flood elevation (BFE) is the water-surface elevation for the base flood at a location. Zone AE has published BFEs. An approximate Zone A generally lacks a published BFE, so obtain the applicable elevation and source from the local floodplain administrator before setting grades. The floodway is the channel and adjoining land needed to carry the base flood. Zone X is outside the mapped SFHA and can still include areas with flood risk.
Michigan approvals. Under MCL 324.3108 and R 323.1311–.1312, confirm Part 31 coverage with EGLE for structures, fill or grading in a regulated river, stream or drain floodplain. The rules exclude a watershed under 2 square miles measured at the downstream end of the proposed work, and provide other exclusions. Mere location in an inland lake or Great Lakes floodplain away from a regulated watercourse does not itself trigger a Part 31 permit. Work there can still require other state or local approvals. Check the separate flood provisions of the Michigan Residential Code and community requirements. Where amended R322.2.1 applies, the lowest floor surface generally must be at least 1 foot above the design flood elevation, with the bottom of the lowest horizontal member of the floor system at or above that elevation. Confirm the applicable elevation, same-datum tie and required documentation with the local official.
Wetlands. With the exceptions in Part 303, MCL 324.30304 requires permission to place fill, remove soil or minerals, construct or maintain development, or drain surface water in a regulated wetland. Screen for qualifying wetland soils, vegetation and hydrology, and for the jurisdictional criteria in MCL 324.30301. These include contiguity, wetlands larger than 5 acres, federally jurisdictional waters meeting the wetland definition and certain rare wetlands or documented protected species. Under R 281.921, contiguity screening includes locations within 1,000 feet of the ordinary high-water mark of a Great Lake or Lake St. Clair, or 500 feet of qualifying inland waters. EGLE can determine that a wetland within those distances has no surface-water or groundwater connection. Also check small isolated sites that EGLE has determined are essential and for which it has issued notice. Maps flag areas for review. Use field delineation and the agency determination to resolve boundaries and jurisdiction before laying out fill, access or drainage.
How errors propagate
Systematic bias can accumulate over a run. Random reading variation and individual mistakes require separate checks.
- Angular error grows with distance. A horizontal line turned 0.5 degrees from the intended alignment is off by about 100 × tan(0.5°) = 0.87 ft at the 100-ft station. At the 200-ft station, the offset grows to about 1.75 ft.
- Elevation error grows with each setup. If the backsight at each setup has a +0.02-ft bias and the foresight is unbiased, the computed rise is +0.02 ft too high per setup. Five setups carried forward accumulate +0.10 ft. A positive bias in the foresights alone would reverse the sign, and equal biases in both readings would cancel in their difference.
- Errors cascade through trades. A foundation set 1.5 ft off moves the excavation, the utilities, the driveway, and the final grade. A late correction can require redesign and substantial rework.
Use verified control on the project datum, a check to a known closing elevation, independent ties and geometry measurements for critical dimensions, and a written record. A loop returning to the starting mark cannot detect a wrong elevation assigned to that mark.
Reading survey notes and a worked elevation
Survey notes use bearings in degrees, minutes, and seconds — a line noted as N 42°15′30″ E runs 42 degrees, 15 minutes, 30 seconds east of north — with distances to hundredths of a foot and labels such as POB for point of beginning. Read the legend for abbreviations that vary between drawings, such as POC, and use the found and set notes to identify the marks. Elevations appear as decimal feet, and the datum note tells you what zero means.
The arithmetic every contractor should be able to do in the field is the height of instrument (HI) method:
- HI = benchmark elevation + backsight.
- Ground elevation = HI − foresight.
With a benchmark at 812.50 ft, a backsight of 4.20 ft, and a foresight of 5.85 ft:
- HI = 812.50 + 4.20 = 816.70 ft
- Ground elevation at the stake = 816.70 − 5.85 = 810.85 ft
| Reading | Value | Meaning |
|---|---|---|
| BM 1 elevation | 812.50 ft | Known reference |
| Backsight on BM 1 | 4.20 ft | Rod reading to the reference |
| Height of instrument | 816.70 ft | Elevation of the line of sight |
| Foresight on the stake | 5.85 ft | Rod reading to the unknown point |
| Stake elevation | 810.85 ft | Ground height at that point |
In this example the rod was held on existing ground at the stake. If finished grade at that same point is 811.30 ft, the finish surface is 811.30 − 810.85 = 0.45 ft above the measured ground. Use the subgrade elevation and layer thicknesses to determine the actual construction fill. Answering that question in the field, with numbers and from a verified reference, is the difference between managing a site and guessing at it.
A side boundary is uncertain, and the designer needs a certified survey map before releasing the layout. Who may prepare the map under Michigan law?
The general contractor using the recorded plat and a tape
The building official performing a permit inspection
A professional surveyor licensed in Michigan
The utility locate crew marking underground facilities
A surveyor assigns 100.00 ft to a specified point on a fire hydrant and measures the project elevations from that point. What reference has the surveyor established?
An assumed project datum tied to the identified point
An official NAVD 88 height based on the assigned number alone
A temporary turning point that must be read at every setup
A published base flood elevation for the parcel
Which proposed work normally needs an EGLE floodplain permit under Michigan Part 31?
A house in an inland lake floodplain away from the lake inlet and outlet, with no affected watercourse
Nonagricultural fill and a garage in a regulated stream floodplain, where the watershed at the downstream project limit is 3 square miles
Planting vegetation on a stream floodplain without filling or grading
Building a deck entirely on upland outside any regulated floodplain or channel