2.2 Independent Arbitration in Builder Disputes

Key Takeaways

  • A mediator facilitates an agreement. A binding arbitrator decides a dispute submitted under a valid agreement, subject to limited statutory court review of the award.

  • MCL 339.2411(4)(d) lets a builder contractually provide a neutral third-party dispute-resolution procedure for department complaints; the licensee initiates it and gives certified-mail notice at least 30 days before it begins

  • MCL 339.2411(4)(e) limits initiation of a workmanship proceeding when a qualifying contractual procedure has yet to be used and completed. Exceptions include noncompliance with a decision, failure to finish within 90 days after filing, and unavailability to the complainant.

  • The Michigan Uniform Arbitration Act generally enforces agreements in a record (MCL 691.1686). The ordinary vacatur deadline is 90 days from notice of the award or of an arbitrator-modified or corrected award, with a discovery rule for corruption, fraud or undue means (MCL 691.1703).

  • An arbitration award reduced to an unsatisfied judgment feeds discipline: MCL 339.2411(2)(l) lists failing to satisfy judgments or liens as an Article 24 violation

Last updated: November 2026

Independent arbitration is part of the PSI Residential Builder Business & Law outline. A homeowner and builder might ask a neutral to decide whether a disputed leak is covered by a warranty. The effect of that decision depends on the parties' agreement and the governing law.

Mediation, Arbitration and Litigation

Arbitration is a private dispute process in which the parties submit their disagreement to a neutral third party (a sole arbitrator or a panel), who conducts a hearing — evidence, documents, testimony — and issues a decision called an award. It is an alternative to court litigation: faster, private, and often decided by someone with construction knowledge.

ProcessNeutral's roleResult
MediationFacilitates negotiationSettlement if the parties agree
Binding arbitrationDecides the submitted disputeAward subject to limited statutory court review
LitigationCourt adjudicates the disputeJudgment subject to applicable appeal rules

The distinction between binding and nonbinding arbitration is what the parties agreed the neutral's decision would do.

  • Binding arbitration. A valid agreement assigns a covered dispute to the arbitrator for a binding award subject to statutory court review.
  • Nonbinding arbitration. The parties receive an advisory decision. They may accept it as part of a settlement or pursue any available next step.

Negotiation, mediation, arbitration and litigation are different routes. For example, a contract may require mediation before arbitration, or it may send the dispute directly to arbitration. Read the dispute-resolution clause to identify any prerequisites.

Why Builders Put Arbitration Clauses in Their Contracts

An arbitration clause can specify the rules, forum, selection of a neutral and allocation of fees. Time, cost, access to evidence and privacy depend on the agreement and applicable rules. A later court filing about the award may be public. In a warranty dispute, a mediator helps the parties agree on repairs or payment. A binding arbitrator can instead decide the dispute submitted under the clause.

Michigan Workmanship Proceedings and Arbitration Awards

Contractual ADR in an Administrative Workmanship Case

This is the provision that ties "independent arbitration" to your license. Under MCL 339.2411(4)(d), a licensee may contractually provide for an alternative dispute resolution procedure to resolve complaints filed with the department. The statute imposes conditions that read like an arbitration checklist: the procedure must be conducted by a neutral third party; it must be initiated by the licensee, who gives the complainant notice of its commencement by certified mail at least 30 days before the procedure begins; and it must be held at a location mutually agreed by the parties. The word "independent" fits: the process runs outside the department's own hearing system, before a neutral who is independent of LARA.

Under MCL 339.2411(4)(e), LARA generally cannot initiate a proceeding under that subsection when the qualifying contractual procedure has yet to be used and completed. LARA may proceed if the licensee fails to comply with its decision or order, the procedure has not been fully completed within 90 days after the complaint was filed, or a procedure meeting subdivision (d) is unavailable to the complainant. The owner may still file the complaint. Separately, subdivision (f) generally requires proof of reasonable repair access and no repairs within 60 days after sending the notice, subject to the statutory safety exception.

Enforcing or Challenging an Arbitration Award

Michigan's Uniform Arbitration Act, 2012 PA 371, took effect July 1, 2013. The act covers court review of the agreement and of the award.

  • Agreement. MCL 691.1686 generally enforces an arbitration agreement contained in a record, subject to grounds for revoking a contract. The court determines whether an agreement exists and whether the dispute is covered.
  • Confirmation. After notice of an award, a party may ask the court to confirm it. The court issues a confirming order unless the award is vacated, modified or corrected under the statute. The court then enters a corresponding judgment (MCL 691.1702 and 691.1705).
  • Vacatur. Grounds include fraud or corruption in obtaining the award, evident partiality of a neutral, prejudicial misconduct or exceeded powers. The usual deadline is 90 days after receiving notice of the award, or of an award the arbitrator modified or corrected. For corruption, fraud or other undue means in obtaining the award, it is 90 days after discovery or when reasonable care would have discovered the ground (MCL 691.1703). Mere disagreement with the merits is insufficient. MCL 691.1704 separately allows a court to correct limited matters such as an evident mathematical error.

Why This Matters for Your License

The award and a court judgment are separate steps. If a court enters judgment on the award and the builder fails to satisfy that judgment, MCL 339.2411(2)(l) supplies a possible discipline ground. Separately, under MCL 339.2412(2), failure to use the contract's ADR procedure is an affirmative defense to an action against a licensee in Michigan court under Article 24.

Applying the Two Deadlines

If a qualifying workmanship ADR process has stalled, count 90 days from the LARA complaint filing to determine whether that exception to administrative deferral applies. If a party wants a court to vacate an arbitration award for exceeding the arbitrator's powers, count 90 days from notice of the award, or notice of an arbitrator-modified or corrected award. Each deadline applies to its own proceeding.

Test Your Knowledge

A Michigan residential construction contract contains a valid binding arbitration agreement that covers a payment dispute. What is its effect when the dispute is submitted to the arbitrator?

A

The parties may appeal the arbitrator's award to circuit court as if it were a trial-court judgment on the merits

B

The arbitrator's decision is only a recommendation that either party may ignore and take to court

C

The department must approve the arbitration award before it becomes effective

D

The arbitrator's award binds the parties, subject to limited statutory court review.

Test Your Knowledge

A party receives notice of an original arbitration award and wants to vacate it because the arbitrator exceeded the powers granted under the agreement. There is no later modified or corrected award. What is the ordinary filing deadline in Michigan?

A

30 days after filing a licensing complaint

B

60 days after entry of judgment

C

90 days after receiving notice of the award

D

90 days after reaching a settlement

Test Your Knowledge

A builder's contract with an owner provides a neutral third-party dispute-resolution procedure meeting the requirements of MCL 339.2411(4)(d), and the owner files a workmanship complaint with the department. The builder promptly initiates the procedure but never completes it, and 90 days pass after the complaint was filed. What can the department now do?

A

Proceed against the licensee, because the ADR procedure was not completed within 90 days after the complaint was filed

B

Do nothing, because a contractual ADR clause permanently blocks department proceedings

C

Suspend the owner's right to complain about workmanship for one year

D

Convert the complaint automatically into a citation with a mandatory fine