7.1 Financing Requirements & Construction Loans

Key Takeaways

  • Identify the agreement and the party being paid. Act 524 covers qualifying written public facility contracts of at least $30,000 with four or more payments. Ordinary private home draws depend on the construction and loan agreements.

  • Single-closing financing combines construction and permanent financing. A two-closing structure uses a separate loan to pay off interim financing. Check the conditions for funding, conversion and take-out in the actual documents.

  • The builder owes the owner or lessee a sworn statement when payment is due or requested, or on a qualifying demand. Match each lien waiver to the claimant, payment and statutory verification requirements.

  • Before suspension or termination, check the precise default, notice, cure and remedy provisions. A lender’s freeze may delay funds while leaving the owner’s independent payment duties intact.

  • Under 2008 PA 6, actual occupancy starts the 365-day transfer restriction. The occupancy permit starts the two-year sale disclosure period. The latest of completion, first occupancy and purchase starts the 24-month disclosure-remedy period.

Last updated: November 2026

The construction agreement governs what the owner owes the builder. A separate loan agreement governs what the lender owes the borrower, how progress is verified and what can delay an advance. Start with both documents when the planned cash dates disagree.

Four ways a residential project gets financed

StructureSourceHow payment worksRisk to track
Owner cash or equityThe owner uses available funds, such as savings or sale proceedsThe owner pays deposits, progress payments or milestones under the construction agreementCash availability during the job
Single-closing construction-to-permanent loanInitial closing includes the construction and permanent phasesThe lender manages advances under its terms. The loan converts to long-term financing when conversion conditions are metDelayed advances, incomplete work or unmet conversion conditions
Interim construction loan with separate take-outConstruction lender first and a separate permanent loan at completionConstruction advances follow the first loan. Proceeds of the later loan retire the interim balanceAn interim maturity before a successful refinance
Seller financing for the land or home purchaseA seller extends purchase credit, for example under a land contractThe buyer pays installments to the seller as agreed. Verify separately how labor, materials and draws will be fundedThe buyer has purchase financing but lacks sufficient funds to build

In a single-closing structure, the borrower closes on construction and permanent financing together. The lender manages disbursements during construction. For example, Fannie Mae’s single-closing program requires completion and conversion before it buys the loan. The loan can also require completion evidence, title updates and other conditions. Check the rate, modification and conversion provisions. A single closing by itself does not establish a rate lock or promise that any payment will be released on a stated construction date.

A construction-only loan can mature before long-term financing closes. In a two-closing structure, verify the interim maturity, extension terms, and the separate permanent lender’s eligibility and closing conditions. Check the note for how interest accrues and when it is due. Interest-only payments are one structure. A multiple-advance loan may charge interest only on drawn balances or may use other terms. Regulation Z’s Appendix D describes disclosure estimates for eligible multiple-advance loans. Use the contract and actual draw dates for cash projections.

Under MCL 339.2403(b) a property owner may act without an Article 24 license on a structure on that owner’s property for the owner’s own use and occupancy. Separately assess anyone hired to perform regulated work. The Owner Built Residence Transfer Act, 2008 PA 6 (MCL 445.881–.891) covers an unlicensed individual who builds or acts as general contractor for a residence the individual or a family member occupies or intends to occupy for personal use upon issuance of the occupancy permit. For an owner-builder who intended to live there at the outset, §445.885 requires residence after completion and permit issuance or allows an offer for sale if unforeseen circumstances prevent residence. That exception is limited to once per calendar year. An owner-builder who actually lives there full- or part-time cannot transfer it for at least 365 days after first living there.

Section 445.887(1) requires identifying the home as owner-built when a sale occurs no more than two years after issuance of the occupancy permit. Subsection (2) requires a separate signed and dated notice at offering, in at least 12-point type, disclosing that an unlicensed owner-builder built the home. If required disclosures are omitted, §445.889 allows recovery for specified workmanship and code repairs and qualifying temporary shelter. The liability and filing period is up to 24 months after the latest of completion, first occupancy or purchase. The court awards costs and actual attorney fees to a buyer who prevails in whole or part.

The draw system: money follows verified progress

A draw is an advance under the construction loan. The initial advance may cover authorized costs such as land purchase, deposits or mobilization. Later advances may use percent complete or milestone evidence. A lender’s progress review serves the purposes of the loan. Building officials, designers, and owners exercise separate approval and acceptance responsibilities under their own authority.

Check each draw’s loan and construction documents for the required evidence.

  • Payment application. Use the required form and schedule of values. AIA G702/G703 are examples when adopted for the job.
  • Progress evidence. Identify which inspections or observations the contract, lender and building authority require. Ask who has to sign and how stored materials are treated.
  • Sworn statement. Deliver it under MCL 570.1110 and reconcile it to the application without assuming the lender’s form satisfies the Act.
  • Waivers and title. Identify the claimant, scope and payment stage for each waiver. Check the loan’s separate title and disbursement requirements, including how existing liens or unresolved exceptions affect advances.
  • Final approval. An occupancy document, completion report or title update may be required by the relevant contract or loan program.

Under MCL 570.1115, a construction contract cannot require a waiver in advance of work. A waiver obtained as part of the contract is invalid except to the extent the signer received payment for furnished labor or materials. A conditional waiver takes effect on payment of the amount it states. On receipt of full payment, provide the full unconditional form. For partial payment, provide the partial unconditional form for the amount received on the owner, lessee or designee’s request. Section 115(6) addresses payments made in reliance on waivers and timely written notice that consideration failed. When §115(7) applies, verify indirectly received residential waivers with the claimant who provided the required furnishing notice or was excused under §108 or §108a. Check the laborer-agent rule under §115(8).

The sworn statement identifies the issuer’s applicable trades and unpaid labor. MCL 570.1110(1) requires it when payment is due from or requested of the owner or lessee or on demand by or for either. Section 110(4) covers contracted subcontractors and suppliers and itemized overdue wages, fringe benefits and withholdings. If the statement was omitted before recording, §110(9) preserves the contractor’s lien but bars payment and filing to enforce it until delivery. Giving a required false statement to the owner or lessee to draw money with intent to defraud is a crime. At $20,000 or more it can carry up to 10 years, a fine up to the greater of $15,000 or three times the amount, or both (§110(11)(d)). For residential receipt and entitled requester copies, apply §110(6), including named parties whose furnishing notice was excused. Where the contract calls for normal progress payments to the general contractor, §110(7) requires five business days’ notice before the first direct payment, with a new notice after returning to normal payments.

A subcontractor or supplier ordinarily serves the furnishing notice within 20 days after first furnishing, subject to §§108 and 108a. A contractor contracting directly with the owner or lessee is exempt for a lien arising from that contract (§109(1)). For residential improvements, use the §108a certified-mail request with blank forms when requesting the notice from the owner or lessee. Record the claim within 90 days of last qualifying furnishing, then serve the claim and any recorded proof within 15 days of recording (§111). Start foreclosure within one year of recording and record lis pendens at commencement (§117).

Worked example: a $280,000 house on five draws

Assume a $280,000 contract, 10% retainage withheld from the first four draws and a final draw that pays the entire remaining balance. The table shows the contractor’s own waiver on each draw. Reconcile separate claimants’ waivers to their individual payments.

DrawMilestoneGross10% retainageNet fundedContractor’s waiver for pending payment
1Foundation, waterproofing and backfill after required inspections$42,000 (15%)$4,200$37,800Partial conditional for $37,800
2Framing, roof dry-in, windows, framing inspection$70,000 (25%)$7,000$63,000Partial conditional for $63,000
3Rough trades, required approvals and insulation$70,000 (25%)$7,000$63,000Partial conditional for $63,000
4Drywall, trim, cabinets, flooring, paint$56,000 (20%)$5,600$50,400Partial conditional for $50,400
5Substantial completion, final inspections, occupancy approval and closed punch list$42,000 (15%)None$65,800 including $23,800 releaseFull conditional for $65,800 if tendering the complete remaining payment

The first four draws total $238,000 gross. They withhold $23,800 and pay $214,200. The last draw pays $42,000 plus the $23,800 holdback, bringing the total to $280,000. Obtain partial unconditional waivers on request after partial payments and full unconditional waivers after each claimant’s full payment. If the parties instead hold 10% on all five draws, the total holdback is $28,000 before release under their agreement.

Contract clauses that allocate financing risk

For ordinary private residential work, use the signed construction agreement to identify when payment is due and what supports the request. MCL 125.1561–.1562 instead governs covered written public facility projects with at least $30,000 and four or more payments. Check whether the agency is covered. State transportation, school districts, junior and community colleges, MSHDA, and municipal electric utilities or agencies are excluded. Use the named parties and agreed routing for written requests. Processing can wait for prior-sequence work to be in place and approved. Payment is due within 30 days after the designated architect or professional engineer certifies the work to the agency, or 15 days after the agency receives applicable state or federal funds, on the later applicable deadline. The designated requester may include reasonable interest on the overdue amount in the next request.

Match the risk to the particular contract term.

  • Financing contingency. Check who can invoke it, what proof and notice are required, when it expires, and what happens to deposits and work already performed. A financing delay alone does not establish a right to stop work.
  • Due dates, charges and interest. Identify the actual terms. Under MCL 438.31, when the Usury Act governs, the general rate is 5% per year, with a written agreement permitted up to 7%. The Act excepts certain debt regulated under other laws and credit-sale time-price differentials. Section 438.31c and other state or federal rules may govern a particular mortgage or land contract. When §438.32 applies to a violation, the seller or lender is barred from recovering interest, official fees, delinquency or collection charges, attorney fees and court costs. The borrower or buyer is entitled to attorney fees and court costs. Distinguish a late charge on a construction invoice, interest on a loan, and statutory interest on a covered public payment.
  • Suspension and remobilization. Check the required notices, cure period, schedule adjustment, protection of work and any cost recovery.
  • Direct payment and joint checks. Document who is paid and what is credited against the owner’s debt. Apply §110(7) if using statutory withholding and direct payment.
  • Access and acceptance. Specify which approvals affect loan funding and which affect the owner’s acceptance and payment.
  • Retainage. Use the release conditions specified in the signed contract. Section 115(5) treats retainage contingent on an additional event as not due on furnishing for purposes of the Lien Act.

When the lender stops funding

A frozen draw can arise from incomplete documents, a title exception, an appraisal issue or borrower default. When the builder’s only agreement is with the owner, look first to the construction agreement for payment. The unpaid amount and available remedy depend on work earned, any enforceable payment condition, and the notice and cure terms. A separate lender promise or agreement requires its own review.

  1. Identify the problem. Confirm the lender’s reason, the owner’s payment obligation and any unmet condition. Record work in place, approved changes and documentation for eligible stored materials.
  2. Submit the correct request. Give the required statement to the owner or lessee. Match conditional waivers to the actual proposed payment.
  3. Give any required notice and allow cure. Use the contract’s recipient, delivery method and dates. Protect completed work and document agreed schedule and cost effects.
  4. Use the remedy supported by the facts. A suspension or termination requires an applicable right and compliance with its conditions. Account for work and amounts due under the chosen remedy.
  5. Calendar lien rights separately. Preserve the applicable furnishing notice, recording, service and enforcement dates while addressing the payment problem.

Compare the disputed items independently. A signed change may increase the contract amount. A lender may still ask for additional disbursement documentation. A holdback may have its own release condition.

Quick reference: who does what on a draw

PartyResponsibility to confirm
Lender and its inspectorVerify progress and release advances under the loan terms
Title providerSupply the agreed title information or coverage subject to its exceptions and terms
OwnerPerform the owner’s approval and payment duties under the construction agreement
ContractorSubstantiate completed work, furnish required sworn statements and provide applicable waivers
Subcontractor or supplierServe timely applicable furnishing notices and match its own waiver to payment
Test Your Knowledge

A new residential construction contract requires the contractor to give an advance waiver covering all future draws before any work or payment. What is its effect under MCL 570.1115(1)?

A

It is fully enforceable because the contractor signed it voluntarily and knew the project scope

B

It is void except to the extent payment for labor and material was actually made, because a lien waiver cannot be required in advance of work

C

It is enforceable only if it is notarized and recorded with the register of deeds before the first draw

D

It automatically converts into a conditional waiver when the lender funds the first draw

Test Your Knowledge

The builder requests draw 3 from the owner without the required sworn statement and then records its claim of lien without delivering the statement. What does Michigan law require?

A

The builder may refuse because sworn statements are required only from subcontractors and suppliers

B

Failure to provide the sworn statement automatically voids the construction lien

C

The sworn statement eliminates the lender's need to obtain lien waivers for that draw

D

The builder must provide it when payment is due or requested, and failing to do so does not void the lien but bars payment and lien enforcement until it is provided

Test Your Knowledge

A $280,000 contract is billed on five draws of 15%, 25%, 25%, 20%, and 15%. The first four approved draws are paid in full less 10% retainage, with the holdback released in the final draw. How much cash does the contractor receive before the final draw?

A

$214,200

B

$238,000

C

$252,000

D

$280,000