11.1 Costs & Expenses in Construction
Key Takeaways
Trace direct costs to a job and allocate shared costs on a supportable basis. An overhead recovery charge used for bidding is separate from classification in the financial statements.
Build labor burden from applicable employer payroll taxes, compensation premiums and benefits. Apply each cost to the right wage base or allocation basis.
A cost-to-cost example with $150,000 of eligible costs against $250,000 estimated eligible cost yields 60% progress and $180,000 of revenue on a qualifying $300,000 contract.
An amount earned with the right to payment still conditional on further work can be a contract asset. An advance received or unconditionally due before performance can be a contract liability.
A 20% cost markup yields a 16.7% gross margin. A 20% gross margin requires a 25% markup on the same cost base.
Job cost records track a project by cost code. Financial statements measure the entity’s results and position. A profitable job can still put pressure on cash if the owner pays after labor, supplies and loan installments come due.
Direct costs and labor burden
A direct cost can be traced to a particular job on the basis in use. Useful coding groups include the following.
- Labor. Track hours and wages for the job with the applicable employer labor burden.
- Materials. Record the lumber, concrete, fixtures and other materials supplied to the work.
- Equipment. Trace an invoice for equipment rented exclusively for the job. Where an owned machine serves several jobs, allocate its operating and ownership costs using a supported usage rate.
- Subcontracts. Track the trade scope and its incurred costs and open commitments.
- Other direct costs. A permit or test billed for one job can be traced to that job. If shared, apply a consistent allocation.
Labor burden includes the costs the employer incurs beyond base pay, such as payroll taxes, workers’ compensation and benefits. Use the payroll records and coverage terms for the actual crew.
| Burden component | How to estimate it |
|---|---|
| Employer Social Security | 6.2% of covered wages up to the annual wage base. The 2026 base is $184,500 per worker. |
| Employer Medicare | 1.45% of covered wages with no wage cap. The extra Medicare withholding has no employer match. |
| FUTA | 6% on the first $7,000 of covered wages before any credit. The effective rate can be 0.6% with the full state unemployment credit. |
| Michigan unemployment | Apply the employer’s assigned rate and applicable Michigan taxable wage base. |
| Workers’ compensation and benefits | Use policy or benefit costs and the appropriate covered payroll or allocation base. |
If a carpenter earns $32 per hour and the estimated burden for those hours is 28% of wages, budget $40.96 per hour. For 40 hours, bare wages are $1,280 and the burdened total is $1,638.40. Omitting the burden understates the estimate by $358.40.
Indirect Costs: Field Overhead and Company Overhead
Indirect costs benefit several jobs or activities and require an allocation if included in job cost. Some field overhead is specific to one site. Keep those costs distinct from running the whole company.
- Field overhead or general conditions. Site supervision and temporary facilities often support the entire project. Trace what is job-specific and allocate shared costs consistently.
- Company overhead. General administration includes office rent, bookkeeping and compensation for running the business. Under ASC 340-40, general and administrative costs are ordinarily expensed as incurred. Specifically chargeable items may qualify for capitalization when the applicable criteria are met.
Budget recovery of both site and company costs. An overhead loading for bidding helps recover shared cost through prices. Support any project allocation with the selected cost base and avoid counting the same cost as both a direct charge and an allocation.
Cost Codes and Cost Centers
A cost code organizes a category of work within a budget. A cost center identifies a unit that accumulates costs, such as a specific job or crew. Use consistent coding to compare quantities and costs, track changes and reconcile records for progress applications and sworn statements. The statutory statement has its own contents under MCL 570.1110.
Committed Costs Are Not the Same as Actual Costs
Use these three amounts to separate incurred costs from pricing for remaining work.
- Actual cost to date is cost incurred, including accruals as applicable.
- Open commitment is the portion of an issued purchase order or subcontract for future work or deliveries.
- Forecast to complete includes open commitments for that work and any additional cost still expected, using current scope and rates.
Add cost to date and the forecast to complete to get projected final cost. Use the open commitment column to check what remains covered by purchase orders and subcontracts. The commitment is included in the forecast, so adding it again overstates the cost to finish.
Reading a Job Cost Report
Job 214 is a $300,000 custom home. The report below includes the open commitment in the forecast to complete. Positive projected variance in this report means the forecast cost is above the revised budget.
| Cost code | Revised budget | Cost to date | Open commitment shown | Forecast to complete | Projected variance |
|---|---|---|---|---|---|
| 01-0000 General conditions | $15,000 | $14,000 | — | $1,000 | $0 |
| 02-0000 Sitework | $18,000 | $18,400 | — | $0 | +$400 |
| 03-0000 Concrete | $32,000 | $31,200 | — | $400 | −$400 |
| 06-0000 Carpentry | $55,000 | $40,000 | $15,000 | $15,000 | $0 |
| 09-0000 Finishes | $62,000 | $20,000 | — | $42,000 | $0 |
| 15-0000 Mechanical | $38,000 | $15,000 | — | $23,000 | $0 |
| 16-0000 Electrical | $30,000 | $11,400 | — | $18,600 | $0 |
| Total | $250,000 | $150,000 | $15,000 | $100,000 | $0 |
The $400 sitework overrun offsets $400 of forecast savings on concrete. The job projects $250,000 in total cost and $50,000 in gross profit. In carpentry, $40,000 is incurred and the $15,000 open commitment covers the forecast remaining work. Review the remaining scope before concluding the package will finish on budget.
Work in Progress: Overbillings and Underbillings
For this example, assume the contract qualifies for revenue recognition over time and that all illustrated costs are eligible inputs under the contractor’s cost-to-cost method.
- Percent complete = costs to date ÷ estimated total cost = $150,000 ÷ $250,000 = 60%.
- Earned revenue = 60% × $300,000 = $180,000.
- Earned gross profit = $180,000 − $150,000 = $30,000.
Next compare performance with the amount billed and unconditionally due. These alternatives assume no additional advance has been received.
- If $165,000 is due and billed, $15,000 of recognized revenue is unbilled. Assume the right to that amount is conditional on further performance, so it is a contract asset.
- If $195,000 is due and billed, amounts due exceed recognized revenue by $15,000, a contract liability in this example. This can arise before the customer pays.
Compare rights and obligations at the contract level under the applicable revenue standard. The $15,000 contract asset on Job 214 and a $9,000 contract liability on a separate, unrelated contract should remain visible. Do not infer collections from either balance.
Costs Versus Expenses
A cost measures resources used or acquired. It may initially be an asset or be expensed under the applicable standard. For example, $12,000 of unused lumber that the builder still controls and holds for a future job can remain materials inventory. Some fulfillment costs outside other topics are capitalized under ASC 340-40 if they relate directly to the contract, create or enhance a resource for future performance and are expected to be recovered. Expense costs of work already performed as applicable. A $48,000 truck held for repeated use is equipment, with its depreciable amount allocated over its useful life.
Use the cash-flow statement and collection schedule alongside accrual profit. Asset purchases, loan principal, advance payments and retainage can affect cash in a different period from reported revenue or expenses.
Applying Overhead
If annual company overhead is $372,000 and planned revenue is $4,200,000, the planned recovery is 8.86% of revenue. This ratio spreads the budgeted overhead across expected sales for pricing. The extra sales needed to cover a new fixed cost depend on the contribution from those sales after their incremental costs.
Watch the difference between margin and markup, because exam questions exploit it:
| Intended margin on price | Required markup on cost |
|---|---|
| 10% | 11.1% |
| 15% | 17.6% |
| 20% | 25.0% |
| 25% | 33.3% |
With $250,000 of comparable cost, a 20% markup produces a $300,000 price and $50,000 gross profit, or 16.7% of the price. For a 20% margin on the same cost, divide $250,000 by 0.80. Price is $312,500 and gross profit is $62,500, a $12,500 difference.
When the Job Goes Bad
Under ASC 605-35, recognize the entire estimated loss once evident for an in-scope construction-type contract. Apply the rule to the contract or qualifying unit of account under the entity’s policy. Suppose Job 214’s estimated final cost rises from $250,000 to $310,000 without changing the $300,000 consideration. Forecast lifetime profit falls from $50,000 to a $10,000 loss. If $30,000 of cumulative profit was previously recognized, the current period must reflect a $40,000 loss to bring the cumulative result to negative $10,000. The $60,000 drop is the change in the lifetime forecast. Recompute normal revenue and cost recognition and provision only the additional loss needed to reach the full cumulative loss.
An over-time $300,000 contract uses cost-to-cost. Eligible cost to date is $150,000 and total estimated eligible cost is $250,000. The owner has been billed $165,000, now due, and has made no advance payment. The right to the remaining earned amount is conditional on further performance. All balances are current. What does the WIP schedule show?
$165,000 of revenue and a $15,000 contract liability
$180,000 of revenue and a $15,000 contract liability
$150,000 of revenue and a $30,000 contract asset
60% progress, $180,000 of revenue and a $15,000 contract asset
Which cost is general company overhead in a builder’s job-cost report?
Compensation for general office administration and rent for the central office
Lumber supplied for one project
HVAC installation under the subcontract for one house
The workers’ compensation cost allocated to the crew hours for one job