23.2 Material Takeoffs & Measurements
Key Takeaways
Select the measurement and the purchase unit independently. Use the correct drawing dimensions and match material deductions to the layout, scope and pricing basis.
A 24 × 36 ft slab 4 inches thick is 288 cubic feet, or about 10.67 cubic yards. With 5% allowance it needs 11.20 cubic yards before supplier rounding, or 11.25 if sold in quarter-yard increments.
One board foot is 144 cubic inches. For a vendor using nominal board measure, multiply the nominal thickness and width in inches by the length in feet, then divide by 12. Order actual pieces in the required sizes.
The no-opening-deduction 12 × 16 ft room has 448 square feet of wall and 192 of ceiling. With 4 × 8 sheets and a stipulated 10% quantity allowance, the area estimate is 22 sheets. Check the panel layout.
Compute roof area on the slope, then apply the specified field allowance. Round to the selected product’s purchasable package using its published coverage.
Match the measure to the material
A quantity takeoff measures the work from the drawings and specifications. Keep a net quantity and a purchase quantity. The latter reflects layout, yield or waste and the supplier’s package size. Price the quantity you expect to buy.
| Measure | Unit | Used for | Basis |
|---|---|---|---|
| Linear | LF | Trim, pipe, conduit, footings and roof edges | Measure the specified line and deduct runs where the material stops. |
| Area | SF and squares | Flooring, siding, board, roofing and paint | Use the actual surfaces within scope. Subtract openings as appropriate to the layout. |
| Volume | CY or ft³ | Concrete, gravel and soil | For rectangular work use length × width × depth. Convert all dimensions to feet before multiplying. |
| Board measure | BF | Lumber sold by board volume | Use the specified thickness and width basis in inches and length in feet. |
| Count | EA | Doors, windows, fixtures and members | Cross-check schedules and tags against the current plans. |
Squares are the roofing and siding shorthand: 1 square = 100 square feet. Cubic yards are the concrete shorthand: 1 cubic yard = 27 cubic feet. A board foot is 144 cubic inches — a piece 1 inch thick, 12 inches wide and 12 inches long.
Two rules of measurement come before any arithmetic:
- Resolve the dimensions. Use the written dimensions on coordinated drawings. Clarify contradictions and missing dimensions before relying on scaled values. When scaling is authorized, confirm the scale for that view and print size.
- Choose nominal or actual size for the task. A standard dry dressed 2×6 is 1½ × 5½ inches. Use an actual dimension for physical fit, a call size for the order, and the vendor’s stated dimension basis when pricing by board measure. Framing center spacing comes from the layout or plan.
Board feet, worked both ways
On the nominal billing basis used in this table:
Board feet = thickness (in.) × width (in.) × length (ft.) ÷ 12
The conversion also works with measured dimensions when volume or the stated sale method requires them. If all three dimensions are in inches, divide by 144 instead.
| Piece | Calculation | Board feet |
|---|---|---|
| 2×4×8 | (2 × 4 × 8) ÷ 12 = 64 ÷ 12 | 5.33 |
| 2×6×12 | (2 × 6 × 12) ÷ 12 = 144 ÷ 12 | 12.00 |
| 2×8×14 | (2 × 8 × 14) ÷ 12 = 224 ÷ 12 | 18.67 |
| 2×10×16 | (2 × 10 × 16) ÷ 12 = 320 ÷ 12 | 26.67 |
| 2×12×20 | (2 × 12 × 20) ÷ 12 = 480 ÷ 12 | 40.00 |
Worked example. Fifty 2×10×16 floor joists are 50 × (2 × 10 × 16) ÷ 12 = 1,333.33 bf on the stated billing basis. If the estimator carries a 10% allowance using the same stock length, order 55 pieces. That is 1,466.67 bf, about 1.467 MBF when the supplier quotes per thousand board feet. Retain the purchase dimensions and count even when comparing MBF prices.
Sheet goods and waste
A 4 × 8 sheet covers 32 sf, a 4 × 10 covers 40 sf, and a 4 × 12 covers 48 sf. Calculate the surface area, check the cutting and joint plan, apply any remaining allowance and then round up to whole purchase units. A large opening may reduce the quantity, but a cutout made from a full sheet often leaves that sheet in the order. Use the specified measurement convention and actual layout to decide when to deduct.
Document how each allowance was estimated. Use material and layout information rather than copying a percentage between trades.
| Material | What affects the order |
|---|---|
| Framing lumber | Stock lengths, cut list, usable offcuts and culling |
| Flooring | Board lengths, direction, pattern and the manufacturer’s applicable guidance |
| Gypsum board | Sheet lengths, seam layout, backing, cuts and breakage |
| Field shingles | Plane layout, hips, valleys and rake cuts. Estimate separate starter and ridge products by linear coverage. |
| Concrete | Measured dimensions, actual section, subgrade variation and placing losses |
| Siding | Net installed exposure, cuts at openings and gables, usable offcuts and carton coverage |
Apply the allowance once. If a cut list already includes the required stock and unusable offcuts, check which losses remain before adding a factor. Extend the final purchase quantity by the applicable unit price.
Takeoff 1 — a 24 × 36 ft slab, 4 inches thick
- Area = 24 ft × 36 ft = 864 sf.
- Thickness = 4/12 ft = 1/3 ft.
- Volume = 864 × 1/3 = 288 ft³.
- Convert to cubic yards: 288 ÷ 27 = 10.666… CY.
- Apply the stipulated 5% allowance to the unrounded volume: (288 ÷ 27) × 1.05 = 11.20 CY before purchase rounding.
- Suppose the supplier orders in 0.25-CY increments. Round up to 11.25 CY. At $168 per billed CY the concrete costs $1,890.00, before any separately stated delivery, short-load or pump charges.
A uniform 4-inch compacted gravel base under that same slab has an in-place volume of 288 ft³, about 10.67 CY. Suppose the supplier confirms that one loose cubic yard of this material yields 0.80 compacted cubic yard under these conditions. Divide the unrounded compacted volume by 0.80 to allow about 13.33 loose CY before purchase rounding. For a quote in tons, use the supplier’s applicable bulk mass per loose cubic yard or verified project data. Yield and density depend on material and conditions.
Takeoff 2 — gypsum board for a 12 × 16 ft room with an 8-ft ceiling
- Perimeter = 2 × (12 + 16) = 56 lf.
- With no opening deductions, wall area = 56 × 8 = 448 sf.
- Ceiling area = 12 × 16 = 192 sf.
- Total board area = 448 + 192 = 640 sf.
- With 4 × 8 sheets, 640 ÷ 32 = 20 sheet equivalents before allowance.
- With the stipulated 10% allowance, round 640 × 1.10 ÷ 32 up to 22 sheets for the area-based estimate.
Review sheet direction, joint backing, access and cut reuse before ordering. If ceiling layout permits 4 × 12 sheets spanning the 12-ft room dimension, four sheets cover the 16-ft dimension before allowance. Changing sheet length can change seam length, labor and purchased quantities even though installed area stays the same.
Takeoff 3 — roofing squares for a gable roof
A 30 × 40 ft house with a 6/12 gable roof and 1-ft overhangs on all sides.
- Projected plan area including overhangs: (30 + 2) × (40 + 2) = 32 × 42 = 1,344 sf.
- Apply the pitch factor. For a slope of inches per 12, the multiplier is ; for 6/12 that is 1.118.
| Pitch | Multiplier |
|---|---|
| 3/12 | 1.031 |
| 4/12 | 1.054 |
| 5/12 | 1.083 |
| 6/12 | 1.118 |
| 8/12 | 1.202 |
| 10/12 | 1.302 |
| 12/12 | 1.414 |
- Use the unrounded factor for the takeoff. Actual roof surface = 1,502.6 sf, about 15.03 squares.
- With the stipulated 10% field allowance, carry 1,652.9 sf, about 16.53 squares.
- For shingles covering 100 sf per three bundles, 1,652.9 × 3 ÷ 100 ≈ 49.59, so buy 50 bundles if sold individually. For the Duration example in the roof materials section, three bundles cover 98.4 sf. The same roof then takes 51 bundles. Count starter and ridge caps separately.
- For an underlayment calculation covering the full deck, a selected roll with 400 sf net installed coverage after laps gives 1,502.6 ÷ 400 ≈ 3.76, so carry four rolls before any additional layout allowance. Follow the specified assembly where ice barrier replaces the normal underlayment and recalculate by the actual courses.
- For this asphalt roof in a jurisdiction requiring an ice barrier, locate the endpoint at least 24 inches horizontally inside the exterior wall line. With the 12-inch overhang, the 36-inch run gives about 40.2 inches along the 6:12 slope. Two 42-ft eaves total 84 lf, yielding roughly 282 sf of net protected deck. A 36-inch-wide course alone falls short. Select the roll width and quantity for the required installed reach after laps and cuts.
Siding and paint from the same measurements
For a rectangular siding scope with 140 lf of perimeter at 9 ft high and no included gables, gross area is 1,260 sf. Deduct 180 sf of openings under the stated takeoff method, for 1,080 sf net. Add the stipulated 10% allowance for 1,188 sf, or 11.88 squares. Buy 12 squares if the vendor sells only whole 100-sf units. Check actual carton coverage and count starter and trim by their separate purchase units.
For 2,320 sf of ready-to-coat surfaces, two finish coats require 4,640 sf of coating. At a stated 375 sf of coverage per gallon per coat, carry 4,640 ÷ 375 ≈ 12.37 gal and buy 13 one-gallon units. If the specified system also requires one primer coat and the primer has that same coverage, 2,320 ÷ 375 ≈ 6.19 gal so buy seven one-gallon units. Use the applicable coverage for each product and substrate, and check the actual purchase sizes.
Trace each quantity back to a drawing view or specification. Review differences between net quantity, purchase units and priced scope before checking the estimate against comparable work. An area check cannot replace the cut or placing plan.
A rectangular 24 ft × 36 ft slab is 4 inches thick. What is the concrete quantity with a 5% allowance, before rounding to supplier increments?
9.6 cubic yards
10.7 cubic yards
11.2 cubic yards
12.9 cubic yards
How many board feet does a supplier bill for thirty 2×8 pieces, each 14 ft long, using nominal board measure?
560 board feet
280 board feet
373 board feet
1,120 board feet
A 12 ft by 16 ft room has an 8-ft ceiling. Estimate 4 × 8 sheets for walls and ceiling using gross area, no opening deductions and a 10% allowance. Assume the resulting layout is feasible.
18 sheets
20 sheets
26 sheets
22 sheets