27.3 Soil Erosion & Sedimentation Control (Part 91)

Key Takeaways

  • Unless exempt, an earth change disturbing 1 or more acres or within 500 feet of the water’s edge of a lake or stream requires Part 91 authorization before work. An exemption from permitting still allows enforcement if the work results in a violation.

  • For Part 91, lakes include the Great Lakes and qualifying inland waters at least 1 acre in surface area. Streams have definite banks, a bed and visible evidence of continued flow or occurrence of water.

  • The SESC plan must map the site at no more than 200 feet per inch unless the agency sets another scale. Include soils, the limits and timing of work, drainage and dewatering, controls, and a permanent maintenance program with a responsible party.

  • Install temporary controls before or as work starts and maintain them daily. Remove sediment from runoff before it leaves. Complete permanent measures within 5 calendar days after final grading or the final earth change. If permanent stabilization cannot be completed, keep temporary controls in place.

  • Under MCL 324.9121, civil fines can reach $2,500 for an ordinary civil infraction, $10,000 per day for a knowing violation, and $25,000 per day for a knowing violation after a notice of determination. The agency can also order work to cease or revoke the permit.

Last updated: November 2026

When a bulldozer opens ground, the first rain moves soil. That soil is a pollutant: it fills road ditches, smothers gravel spawning beds, carries nutrients and oils into lakes, and costs public agencies millions to dredge. Michigan regulates it through Part 91 of the Natural Resources and Environmental Protection Act, 1994 PA 451 (MCL 324.9101 to 324.9123), implemented by administrative rules R 323.1701 to R 323.1714. For a residential contractor the practical content is narrow and very testable: when a permit is required, what the plan must contain, which practices hold soil on site, and what happens when they fail.

The Regulatory Frame

Part 91 is administered locally. A county enforcing agency is a county agency, or a conservation district, designated by the county board of commissioners under MCL 324.9105. Where a city, village, charter township, or a general law township in a county of 200,000 or more adopts its own ordinance, an EGLE-approved municipal program can enforce it through the municipal enforcing agency. MCL 324.9106 allows more restrictive local ordinances. EGLE oversees the programs and administers training and certification. An authorized public agency operates under approved procedures with notice to the enforcing agency under R 323.1706(4).

The trigger term is earth change: a human-made change in the natural cover or topography of land, including cut and fill activities, which may result in or contribute to soil erosion or sedimentation of the waters of the state (MCL 324.9101(9)). Plowing and tilling for crop production are excluded. Note the breadth: stripping, grading, excavating, stockpiling, and filling all qualify, and so does removing vegetation that was holding a slope together.

Permit Triggers: The Two Numbers

R 323.1704(1) is the sentence to memorize: a landowner or designated agent who contracts for, allows, or engages in an earth change must obtain a permit before commencing an earth change which disturbs 1 or more acres of land or which is within 500 feet of the water's edge of a lake or stream, subject to applicable exemptions and waivers.

The definitions in R 323.1701 decide what counts:

  • Lake — the Great Lakes and all natural and artificial inland lakes or impoundments with definite banks, a bed, visible evidence of a continued occurrence of water, and a surface area equal to or greater than 1 acre. Sediment basins and basins built solely for storm water retention, cooling water, or treating polluted water are excluded.
  • Stream — a river, creek, or other surface watercourse, whether or not it serves as a drain under 1956 PA 40, with definite banks, a bed, and visible evidence of the continued flow or continued occurrence of water, including the connecting waters of the Great Lakes.
SituationPart 91 permit?Why
1.4-acre subdivision gradingYesDisturbs 1 or more acres
0.3-acre disturbed area 300 ft from a qualifying lake with no exemptionYesWithin 500 ft of the water's edge
0.8-acre disturbed area more than 500 ft from any lake or streamGenerally noUnder both thresholds
Minor earth change stabilized within 24 hours, will not contribute sediment to a lake or streamNo, exemptR 323.1705(1)(c)
Normal driveway maintenance with no added width or length and no sediment contributed to lakes or streamsNo, exemptR 323.1705(1)(b)
Earth change under 225 square feet, with the landowner’s signed affidavit of area and no contribution of sediment to lakes or streamsWaiver possibleR 323.1705(2)

The 500-foot test is measured from the water's edge, not the property line and not the centerline of the stream. Exemptions are narrow and are not immunity: R 323.1704(2) and R 323.1705(3) both state that an activity not requiring a permit is still subject to enforcement if it violates Part 91 or the rules. MCL 324.9115a separately exempts certain work on owner-occupied residential property if it meets the statutory conditions, such as digging deck post holes without related grading and without erosion, sedimentation of state waters or off-site sediment discharge. There is also a building-permit link: R 323.1711 requires the building official to notify the enforcing agency of an application for a building permit involving an earth change of 1 acre or more or within 500 feet of a lake or stream, and requires the SESC permit before building permit issuance when the earth change requires it.

Under MCL 324.9112, transfer of the whole permitted property transfers its permit, obligations and responsibility for any existing violations. Transfer of one parcel passes the obligations and liability specific to that parcel. The seller must give the buyer the prescribed written notice and a copy of the permit. Both parties sign the notice and the seller submits it to the enforcing agency before transfer.

What the SESC Plan Must Contain

R 323.1703 lists the required plan elements, and exam questions love the specifics:

Plan elementRequirement detail
Site mapScale of not more than 200 feet to the inch (or as the agency allows), with legal description, site location sketch, proximity to lakes or streams, predominant land features, and contour intervals or slope description
SoilsA soils survey or a written description of soil types in the exposed area
Limits of workDescription and location of the physical limits of each proposed earth change
DrainageDescription and location of existing and proposed on-site drainage and dewatering facilities
SequenceTiming and sequence of each proposed earth change
Temporary controlsLocation, description, installation and removal of temporary measures
Permanent controlsDescription and location of permanent measures
MaintenanceProgram for continued maintenance of permanent measures after completion, with the responsible person named; responsibility passes with any sale

The plan must be available for inspection at the site at all times during the earth change (R 323.1702(3)), and the permit itself must be kept at the site (R 323.1707(3)). The enforcing agency must approve, disapprove, or require modification within 30 calendar days of receiving the application (R 323.1707(2)). Approval requires review by a person trained in erosion and sedimentation control methods.

Best Management Practices That Actually Work

The rules set performance standards, not a product list: reduce exposed area, keep water velocities nonerosive, and remove sediment before runoff leaves the site (R 323.1709). Specific installations follow applicable manufacturer, conservation district, EGLE, MDOT and formally adopted enforcing-agency standards under R 323.1710. The enforcing agency or authorized public agency resolves conflicting specifications.

BMPWhere it appliesInstallation essentialsMaintenance
Silt fencePerimeter of disturbed area, downslope of bare soilFabric on contour, bottom keyed into a trench and backfilled, posts on the downhill side, ends turned uphill (J-hooks) so flow cannot go aroundRemove accumulated sediment when it reaches about one-third to one-half of fence height; repair tears and blown-out sections
Check damSwales, ditches and channels carrying sedimentStone or approved material keyed into the channel; spaced so the upstream toe of one dam is level with the crest of the next downstream damRemove sediment, rebuild dislodged stone, keep the channel from scouring around the ends
Inlet protectionStorm drain inlets receiving site runoffFilter fabric, stone collar, or approved insert sized to the inlet; water must still be able to leave without flooding the workClean or replace filter media, remove sediment, never let a device cause ponding that threatens the excavation
Diversion swale or bermUpslope of the disturbed areaPositive grade to a nonerosive outlet; sized for the drainage areaKeep the channel clear, repair rills, verify the outlet is stable
Sediment basin or trapLow point before dischargeSized to the contributing area, with a controlled dewatering outletRemove sediment when capacity is reduced, maintain the outlet
StabilizationEvery disturbed area, temporary or permanentSeed, mulch, erosion control blanket, or sod appropriate to the season; Michigan seeding windows matterRe-seed bare spots, repair mulch, water as needed
Dust controlHaul roads, stockpiles, active cutsWater, approved palliatives, reduced speedReapply during dry, windy weather
Concrete washoutAny concrete truck on siteLined, contained area away from inlets, ditches and waterHaul off or cure and remove the hardened material
Tracking controlSite exitStone pad or approved device so mud does not leave on tiresMaintain stone depth, clean the road
Stockpile protectionAll stockpilesSilt fence around the toe, cover or stabilize the pileRe-cover after use, seed long-term piles

Timing, Inspection and Removal

R 323.1709 supplies the schedule that examiners test:

  1. Limit the exposed area for the shortest possible time (1709(1)). Clear and grade in phases; do not strip the entire lot on day one.
  2. Remove sediment from runoff before it leaves the site (1709(2)).
  3. Convey water at a nonerosive velocity around, through, or from the work area (1709(3)).
  4. Install temporary measures before or upon commencement and maintain them daily; remove them only after permanent measures are in place and the area is stabilized (1709(4)).
  5. Complete permanent stabilization within 5 calendar days after final grading or completion of the earth change; if permanent stabilization is not possible or significant earth change activity ceases, maintain temporary controls until permanent measures are in place and the area is stabilized (1709(5)).

Part 31 construction stormwater coverage generally applies to construction disturbing at least 1 acre, including qualifying smaller sites within a larger common plan, when there is a point-source stormwater discharge to state waters. Under EGLE’s Permit-by-Rule (R 323.2190), eligible sites from 1 to less than 5 acres automatically obtain coverage with Part 91 coverage. At 5 acres or more, submit a Notice of Coverage to EGLE with the required documents and fee. A certified stormwater operator inspects controls weekly and within 24 hours after each precipitation event that results in discharge from the site. These inspections supplement Part 91 daily maintenance whenever both programs apply.

Worked Example: Sequence for a Lakefront Lot

A standalone house project will disturb 0.8 acre. The closest disturbance to the water’s edge is 260 feet from a qualifying inland lake. No exemption applies, so proximity triggers the Part 91 permit and SESC plan.

StageActionWhy
Before clearingObtain SESC plan approval and permit; keep permit and plan available for inspection on siteR 323.1702(3), R 323.1707(3)
Before clearingInstall silt fence along the downslope perimeter with J-hooks at the ends; protect any storm inlet; install stone tracking pad at the exit; designate a lined concrete washoutR 323.1709(4) requires installation before or upon commencement
During gradingClear in phases, cover or stabilize stockpiles and maintain temporary controls dailyR 323.1709(1), 1709(2), 1709(4)
At final gradeSeed, mulch or blanket all disturbed areas within 5 calendar daysR 323.1709(5)
After stabilizationRemove temporary controls, repair any ruts, document with dated photosControls are removed only after permanent measures are in place

If the project disturbed 1.3 acres and discharged stormwater to the lake through a pipe, it would also need Part 31 NPDES construction stormwater coverage. With eligible Part 91 coverage at that acreage, EGLE’s Permit-by-Rule provides automatic coverage. The certified operator’s inspections remain required.

Enforcement and Penalties

R 323.1712 lets the enforcing agency issue a cease and desist order or revoke a permit for a violation of Part 91, the rules, a local ordinance, a permit condition, or an approved plan. That is the immediate operational risk: a stop-work order on a foundation excavation costs far more than the fence that was skipped.

MCL 324.9121 sets the money:

ViolationExposure
Violation pursued by an enforcing agency with a local penalty ordinance, or by the stateCivil infraction, civil fine up to $2,500
Knowing violation, or knowingly false statement in an application or SESC planCivil fine up to $10,000 per day of violation
Knowing violation after a notice of determination under MCL 324.9112 or 324.9117Civil fine of $2,500 to $25,000 per day of violation

Beyond fines, the violator is liable for damages for injury to, destruction of, or loss of natural resources, and a court may order restoration of the affected area to its prior condition. The property owner is responsible for compliance with permit terms that apply to the property (MCL 324.9112(2)), which is why a general contractor should confirm the owner has the permit before mobilizing.

Traps and Field Judgment

  • Reading the acre trigger and forgetting the water trigger. Either one requires a permit; the 500-foot test is measured from the water's edge.
  • Assuming a roadside ditch is not a stream. If it has definite banks, a bed, and visible evidence of continued flow or occurrence of water, it may qualify — and only the enforcing agency decides.
  • Removing silt fence right after seeding. Temporary controls come out after the permanent measures are established, not after the last truck leaves.
  • Installing silt fence on the uphill side or across a concentrated flow path. Fence belongs downslope, on contour, with ends turned uphill; concentrated flow needs a check dam or a stable channel, not fabric.
  • Pumping sediment-laden water to the street or storm drain. That moves the violation off site and onto the record.
  • Leaving stockpiles uncovered through the winter. Spring snowmelt delivers the pile to the nearest waterbody.
  • Skipping the maintenance program. The plan must name who maintains permanent measures after the project; that responsibility transfers with a sale.

The exam pattern here is simple: identify the trigger, name the plan elements, place the BMP correctly, and know the stabilization and inspection deadlines. Those four answers cover most Part 91 questions a residential contractor will see.

Loading diagram...
SESC sequence for a permitted earth change
Test Your Knowledge

Assume a private project has no exemption or waiver. Under R 323.1704, what triggers a Part 91 earth-change permit?

A

It disturbs 1 or more acres of land, or it is within 500 feet of the water's edge of a lake or stream

B

It disturbs 5 or more acres of land, or it is within 1,000 feet of any drainage ditch

C

It involves any excavation deeper than 5 feet, regardless of area

D

It costs more than $10,000 in earthwork, regardless of area

Test Your Knowledge

According to R 323.1709, when must permanent soil erosion control measures be completed on disturbed areas after final grading?

A

Within 24 hours of the first rain event

B

Within 5 calendar days after final grading or completion of the earth change

C

Within 30 calendar days, matching the plan review period

D

Only after the certificate of occupancy is issued

Test Your Knowledge

Under MCL 324.9121, what is the civil fine range for a knowing Part 91 violation committed after the person has received a notice of determination?

A

A flat $500 civil infraction

B

Up to $2,500 total for the project

C

Up to $10,000 per day of violation

D

$2,500 to $25,000 per day of violation