24.2 Construction Techniques: New Construction vs Remodeling
Key Takeaways
R102.7.1 generally applies new-construction requirements to additions, alterations and repairs, subject to specific code provisions. Evaluate the existing structure so the work preserves its safety and performance.
Under 2015 MRC R104.9.1, the building official must approve reuse of used materials, equipment and devices.
Michigan's R109.1.4 amendment sets distinct framing and masonry inspection triggers. R109.4 requires approval to proceed past the applicable inspection point.
EPA administers the federal RRP rule in Michigan for covered renovations in pre-1978 target housing and child-occupied facilities. Verify the work scope and any exception. MDHHS lead abatement certification is a separate program.
A private residential building of four or fewer units is generally excluded from NESHAP, subject to site and project scope. MIOSHA worker protections and state asbestos rules can still apply.
24.2 Construction Techniques: New Construction vs Remodeling
New construction starts on an empty lot with documents you control. Remodeling starts inside someone else's decisions: sixty-year-old framing, three generations of wiring, a bearing wall that is not where the drawing says, and a family living two rooms away. The carpentry overlaps. The risk does not. On the exam, the remodel questions are almost never about how to hang drywall — they are about what you must verify before you cut, what you must not assume about the existing structure, and which permits and inspections the work triggers.
The sentence that governs every remodel
Under R102.7.1, an addition, alteration or repair must meet the requirements for new work. Existing portions generally need only the upgrades a specific provision requires. The work must preserve the existing structure's safety and performance.
Apply the code in effect to the proposed work, including provisions specific to alterations. Evaluate the existing structure for its actual loads and condition. For example, a second-story addition adds load to existing walls and footings. Verify capacity and provide a designed load path before relying on them.
Differences that change the method
| Issue | New construction | Remodel / addition |
|---|---|---|
| Structure | Design from tables or engineer | Verify existing size, species, grade, condition, load path |
| Dimensions | A modern dressed nominal 2×4 is typically 1-1/2 × 3-1/2 inches | Measure actual old lumber and openings |
| Hazards | Assess site and materials, including silica and buried utilities | Also assess existing finishes, assemblies and services for hazardous materials |
| Envelope | One continuous assembly | New assembly tied into an old one with unknown drying direction |
| Weather protection | Dry-in on your schedule | Roof opened over a furnished house |
| Occupancy | Generally unoccupied during construction | Possibly occupied, with active systems and egress needs |
| Permits | New building permit, full inspection sequence | Alteration or addition permit, plus existing-structure questions |
Structural verification before the saw
A remodel begins with investigation, not demolition. After the hazardous materials review and verification of safe access, investigate ceilings and crawl spaces. Trace the actual support from joists, posts, beams and other members. Indicators such as joist direction or a double plate can guide the investigation but cannot establish the load path alone. Confirm actual member sizes and spans; look for notches and bored holes that exceed the code limits for joists and studs; check for cut or modified trusses in the attic (a cut bottom chord is an engineered repair, not a field fix); check sills for rot, foundations for cracking and frost depth, and framing for termite damage and old water stains. Balloon-framed walls need fireblocking at floor levels, and old chimneys need clearance verification before anything combustible goes near them.
Before removing a bearing wall, establish temporary support and verify the permanent beam, post, footing and connection load path. Use the R602.7 tables only where their scope and assumptions fit. Do not assume an ordinary basement slab can carry a new concentrated load. When the existing structure cannot be verified, the honest options are an engineer's evaluation, a design that reduces or bypasses the existing load path, or new framing and foundation independent of the old. What is not an option is nailing a new beam to a "probably fine" header and hoping the inspection passes.
Envelope tie-ins are where remodeling becomes building science. Where an insulated assembly meets older construction, carry its air and water control layers across the junction. Use flashing integrated with the drainage plane at roof-to-wall junctions, and check how the existing assembly dries before adding a low-permeance layer. Transitions in insulation and air sealing can contribute to ice dams. Evaluate roof loads for the proposed geometry.
Hazardous materials are a scope item, not a surprise
Lead paint. EPA administers the Renovation, Repair and Painting (RRP) Rule in Michigan. Covered paid renovations in pre-1978 target housing and qualifying child-occupied facilities require a certified firm and assigned certified renovator. Check the minor-repair limits and exceptions before work. EPA also applies the rule to covered renovations of properties bought, renovated and sold for profit. Michigan builder licensing is a separate question. The specific purchase, substantial rehabilitation and resale clause in MCL 339.2401(b)(ii) refers to activity on the same structure more than twice in one calendar year and has statutory exceptions. MDHHS separately certifies lead abatement, which is work designed to permanently eliminate lead hazards.
Asbestos. A private residential building with four units or fewer is generally excluded from the federal asbestos NESHAP facility definition. A group of structures at one site under common control or small homes in a larger demolition project can be covered. MIOSHA construction-worker protections and Michigan's asbestos accreditation, contractor licensing and notification rules apply according to their own scope. Survey suspect materials before disturbance and use the required qualified professionals and waste procedures.
The pre-demolition checklist also includes moisture damage and possible radon, PCB-containing caulk, lead water service lines, abandoned heating-oil tanks, old septic systems and abandoned wells. EGLE recommends radon testing. Table AF101 as amended by R 408.30547a lists nine counties for the Appendix F requirements. Check the scope for the proposed new construction. A measured indoor level is a separate question.
Matching existing work
Matching is where remodel schedules go to die. Older lumber dimensions vary. Measure the existing plane and specify a transition that preserves the capacity of structural members. Siding profiles, exposures and fade never match a new bundle to a 15-year-old wall — plan the transition at a corner or a break. For masonry restoration, match appearance and verify material compatibility, especially the mortar used with older masonry. Windows arrive in stock sizes that do not fit 1940s rough openings, so expect custom units or framing changes, and jamb depth changes the interior trim. Trim profiles may need custom knives. Drywall thickness and texture (orange peel versus knockdown) show under raking light. Floor transitions need a threshold or a reducer, not a shim. And new lumber shrinks: set cabinets and trim after framing has dried, or plan on callbacks at every joint.
Sequencing a remodel
| Step | Work | Inspection / hold point |
|---|---|---|
| 1 | Survey, hazard testing, protection and utility checks | Document existing conditions and establish controls before disturbance |
| 2 | Selective demolition and disposal | Complete applicable lead and asbestos preparations and use approved handling |
| 3 | Structural: shoring, beams, posts, new framing | Engineer's letter where required |
| 4 | Rough-ins: HVAC, plumbing, electrical | Rough inspections before cover |
| 5 | Envelope and framing hold points | Coordinate rough approvals and framing inspection. Apply the separate masonry conditions where relevant. |
| 6 | Insulation and air sealing | Insulation/energy inspection |
| 7 | Drywall, then finishes, trim and cabinets | Final inspection and any required occupancy approval |
Under R 408.30509, the framing inspection follows roof, framing, firestopping, draftstopping and bracing installation and approval of the applicable rough plumbing, mechanical and electrical work. The same rule separately sets masonry inspection after the required base-course flashing, water-resistive barrier and completed masonry construction. Coordinate visibility with the enforcing agency. Under R 408.30509a amending R109.4, obtain approval before proceeding past the inspection point or covering noncomplying work.
Permits for existing structures
R105.1 requires a permit to construct, enlarge, alter, repair, move, demolish or change the occupancy of a structure, and to install or alter electrical, gas, mechanical or plumbing systems. R105.2 exempts a defined list that matters on remodels: one-story detached accessory structures not over 200 square feet; fences not over 7 feet; retaining walls not over 4 feet from footing bottom to wall top, unless supporting a surcharge; decks, porches, patios and landings up to 200 square feet and no more than 30 inches above grade at any point, with all three separation conditions: no attachment to the dwelling or its accessory structures, no location within 36 inches of either, and no service to an ingress or egress door of either; and finish work such as painting, papering, tiling, carpeting, cabinets and counter tops. The opening sentence of R105.2 is the trap: exemption from a building permit does not authorize work that violates the code and does not waive electrical, plumbing or mechanical permits. A basement finish with new circuits and a new bathroom needs those permits even though the drywall and paint do not.
Working in an occupied house
An occupied remodel is a logistics project with carpentry attached. Plan barriers, cleaning and dust capture for the work. In covered interior RRP work, close and cover ducts opening into the work area as required by 40 CFR 745.85 and keep occupants out of it. A mechanical containment system, where needed, is designed for the work and any affected combustion appliances. Protect floors and contents, post a daily cleanup standard, and give the owners a written schedule for water and power shutdowns and a working temporary kitchen or bath. Keep a clear egress path at all times, keep chemicals and sharp debris away from children and pets, and treat lead-safe containment as a work rule, not a courtesy. Weather protection deserves its own plan: a tarped roof over a furnished living room is a schedule risk and an insurance claim waiting to happen, so dry in the same day whenever the scope allows it.
The traps this section is built to catch
- Assuming existing framing meets current code. It was built to the code of its year, if any, and may have been altered since. Verify, do not assume.
- Changing a load path without design. Removing a wall, notching a beam, cutting a truss chord, or adding a heavy tile floor over undersized joists all redistribute load.
- Starting paint disturbance before evaluating RRP. Identify whether the project requires certification, notices and lead-safe methods.
- Assuming a small residential project is outside every asbestos rule. Evaluate the facility, the project and the separate worker-protection and disposal requirements.
- Covering work before inspection. R109.4 makes concealment without approval a violation, and it is the most expensive kind because the fix is demolition.
- Reusing salvage without approval. Under 2015 MRC R104.9.1, obtain building-official approval before reusing materials, equipment or devices.
- Assuming a permit exemption means no code and no other permits. R105.2 says the opposite in its first sentence.
- Ignoring the envelope junction. The new assembly must connect to the old one with a continuous air barrier, a continuous drainage plane, and one vapor control strategy — not two.
A homeowner wants to add a 400 square foot family room to a 1962 house. How does R102.7.1 treat the existing structure?
The entire existing house must be upgraded to current energy and egress requirements before the addition is approved
The addition must comply with the new-structure requirements that apply. The existing house generally need not be upgraded solely because of the addition, but the work must preserve its safety and performance.
The existing structure must be brought into compliance only for the portions physically touched by the addition
No code requirements apply to the existing structure under any circumstance, including structural capacity
A crew is hired to strip and sand 80 square feet of painted wood siding on a house built in 1958. No lead-free determination or other exclusion applies. Which rule governs the paid renovation?
Nothing beyond normal dust control, because single-family homes are exempt from all lead rules
Only an MDHHS lead abatement contractor certification, because sanding is abatement
A Michigan Department of Environment, Great Lakes, and Energy asbestos notification
The federal RRP Rule, administered by EPA in Michigan, requiring a certified firm and a certified renovator using lead-safe work practices
Which of the following is exempt from a building permit under 2015 MRC R105.2?
A one-story detached storage shed with 180 square feet of floor area
Removing a load-bearing wall and installing a new beam
Finishing a basement bedroom with a new egress window
Adding a second story over an existing garage
Sections you finish are checked off in the contents.