23.1 Cost & Labor Estimating

Key Takeaways

  • Keep direct job costs, site general conditions and company overhead distinct. Estimate each from its own driver, such as work quantity, a fixed fee, equipment rental time or job duration.

  • Convert crew-days to paid worker-hours using crew size and shift length. A two-person, eight-hour crew producing 180 linear feet per day requires about 17.8 worker-hours for 200 feet at the stated productivity.

  • Use actual employer payroll tax bases and rates, insurance classifications and benefit costs. Convert fixed-period costs to the hours they support and handle subcontract pricing separately.

  • On covered public work, price from the applicable classification and wage and fringe determination. Federal Davis-Bacon and Related Acts and Michigan 2023 PA 10 have separate coverage and reporting tests.

  • Apply a stated reserve once. Compare forecast contract revenue with the stated job costs for gross profit, variable costs for contribution and allocated company overhead for the after-allocation job result.

Last updated: November 2026

Direct costs, general conditions and company overhead

Direct job costs can be traced to the work or project under the company’s cost policy. Examples are installed products, craft hours, equipment assigned to an operation and subcontracted scope. Job general conditions are costs of running that site, such as temporary utilities and projectwide supervision. Company overhead supports multiple projects or the business as a whole. The company can allocate overhead to jobs for pricing and review using its stated cost base.

Quantity and productivity drive many direct costs, but a permit or mobilization can be fixed for a job. Some job general conditions vary with time and others are fixed or triggered by usage. A toilet rental may follow a weekly rate while a dumpster contract may charge per pull or by weight. Identify the driver before applying a change in duration or quantity.

Cost bucketExampleHow to estimate it
Direct materialLumber, sheathing, windows and finishesOrder quantity after cut allowance and purchase rounding × delivered unit price, accounting for applicable tax
Direct laborCarpenter, hanger, finisher and painter timeRequired worker-hours × applicable burdened rate
Direct equipmentExcavator, concrete pump or liftScheduled billable period × quoted rate plus separately priced delivery, pickup, fuel and operator where applicable
Direct subcontractElectrical, plumbing or HVACFirm scope and price including exclusions, plus allowance for any unbought scope
Job general conditionsSite supervision, temporary utilities and waste handlingLump sum, usage or scheduled duration as the cost requires
Company overheadOffice rent, administrative salaries and other pooled costsAllocate from the operating budget over the company’s stated sales, labor or other pricing base

A permit for this address is a traceable job cost. Under this estimate’s convention, the crew’s jobwide dumpster is in general conditions and the office lease is company overhead. A dumpster dedicated to one trade could be assigned to that work. Include any rental minimum, delivery, standby or premium shift charge if the quote requires it. Check whether the trade quote already includes that equipment or operator.

Labor productivity: units per hour

Use a production rate for the same operation, crew makeup and working conditions. Historical hours and installed units help establish a baseline. Adjust for conditions that change achievable output, such as occupied rooms, handling distance, access or cleanup. An exam scenario may stipulate a rate and shift length.

The three conversions you need:

Labor-hours = Quantity ÷ Production rate (units per labor-hour)
Crew-days   = Quantity ÷ Crew daily production (units per crew-day)
Labor-hours = Crew-days × Crew size × Hours per day

Worked example — wall framing. A two-person framing crew sets and frames 180 linear feet of wall per day. The addition has 200 linear feet of wall.

  1. Crew-days = 200 lf ÷ 180 lf per crew-day = 1.111… crew-days.
  2. At eight hours per worker per day, multiply the unrounded result by 2 × 8. This gives about 17.8 worker-hours.
  3. As a cross-check, 180 lf ÷ 16 worker-hours = 11.25 lf per worker-hour. Dividing 200 lf by 11.25 gives the same result.

With two identical independent crews working at the same rates in separate work areas, elapsed working time falls to about 0.56 working day. The job still uses 1.11 crew-days of effort and about 17.8 worker-hours in total. Shortening the actual project can reduce time-dependent costs if the critical path changes and charges can be avoided. Congestion, extra mobilization or a loss of productivity can change worker-hours.

Labor burden: the wage is not the cost

The wage is the starting point. Add employer taxes, insurance and benefits that apply to the employee and work. Estimate payroll taxes on the correct taxable wage bases, including any remaining year-to-date limit. An employee’s income tax withholding and share of FICA are withheld from pay, so they are separate from employer burden.

Employer componentEstimating basis
Social Security and MedicareOrdinary employer rates are 6.2% of covered wages within the $184,500 Social Security wage base for 2026 and 1.45% of covered Medicare wages without a ceiling.
FUTA6.0% on the first $7,000 of FUTA-taxable wages per employee. Use 0.6% only if the full 5.4% credit applies.
Michigan unemploymentUse the assigned rate and applicable per-employee taxable wage base. UIA lists 2.7% for general new employers and 5.0% for new construction in 2026. The regular 2026 base is $9,500 and the reduced base is $9,000 for eligible employers.
Workers’ compensationUse the insurer’s applicable classifications, payroll basis and rating factors. Check how hours or payroll are documented.
Benefits and paid nonproductive timeUse employer plan costs, policies and expected paid versus productive hours. Allocate fixed monthly costs on a stated hour base.

When all percentage items apply to the same base wage, the burdened rate is base wage × (1 + sum of the rates). With different bases or fixed costs, add the separately calculated employer costs and divide by the hours the estimate uses.

Worked example. A $28.00 wage with a stipulated combined burden equal to 35% of that wage gives $28.00 × 1.35 = $37.80 per worker-hour. The gap is $9.80, about 25.9% of the $37.80 cost. Apply actual burden to company employee hours, including chargeable punch-list work. Price subcontracted work from its quote and scope, and account for company costs of coordinating it separately.

A full labor estimate for a 1,200 sq ft addition

The 30 × 40 ft single-story addition has 1,200 sf of ceiling, 140 lf of exterior perimeter, 200 lf of framing and 12 doors. The gypsum scope here is the interior face of 140 lf of 8-ft wall plus the ceiling, or 1,120 + 1,200 = 2,320 sf. No opening deduction is used for this labor basis. The roof crew’s illustrative production is per square foot of plan area for this specified roof shape. All shifts are eight hours.

Work itemQuantityProduction basisWorking days for the listed crewWorker-hours
Wall framing200 lf180 lf/day, two workers1.1117.8
Roof framing and sheathing1,200 sf of plan area400 sf/day, two workers3.0048.0
Hang and finish gypsum board2,320 sf600 sf/day, two workers3.8761.9
Hang doors and install trim12 doors6/day, two workers2.0032.0
Paint walls and ceiling2,320 sfOne painter at 175 finished sf per hour for the specified two coats1.6613.3
Unrounded hours summed, then shown to one decimal172.9

Each row displays rounded figures. Carry exact time through the sum so the sum of the rounded displays does not set the bid. For this budget, round total hours up once to 173 paid worker-hours.

Apply the stipulated blended burdened rate to the payroll budget: 173 × $37.80 = $6,539.40 of direct labor.

The same job has the following general conditions. Supervision is priced at the stated loaded hourly cost and is separate from the production hours.

Indirect itemAmount
20-yard roll-off dumpster, two pulls$650
Portable toilet, six weeks$250
Temporary power and water$300
Supervision, 24 hours at $45$1,080
Small tools and consumables$420
Indirect total$2,700

Labor plus general conditions is $6,539.40 + $2,700 = $9,239.40 before contingency. In the full bid below, apply the reserve once to the entire base job budget. Do not price a separate reserve on this subtotal as well.

Rolled into the whole bid, the same addition looks like this:

Cost layerAmount
Quoted materials$46,800.00
Subcontracts including their quoted equipment$38,500.00
In-house burdened labor$6,539.40
Direct job cost subtotal$91,839.40
General conditions$2,700.00
Base job cost$94,539.40
Reserve at the stipulated 8% of base job cost$7,563.15
Budgeted job cost before company overhead and profit$102,102.55

The budgeted job cost is about $85.09 per square foot. Compare this with similar recent work only after aligning scope, location, pricing date and cost layers. Suppose the fixed-price job earns its $125,000 contract amount and the full reserve is spent on variable direct work. Revenue less all job costs gives $22,897.45 project gross profit, or about 18.32% of revenue. With all direct work treated as variable and the $2,700 in general conditions fixed for this case, contribution is $125,000 − $99,402.55 = $25,597.45. After deducting the $2,700 and a stipulated $12,000 allocation of company overhead, the job result is $10,897.45. These are different denominators or cost layers from a markup on cost. An unspent reserve is a budget variance. Draws, receipts and recognized revenue can occur at different times.

Duration, contingency and escalation

The four two-person operations have about 9.98 working days of crew effort in total. Painting adds 1.66 painter-days. In a stipulated serial schedule with no other constraints, that is about 11.6 working days of elapsed time, counting painting once. Plan the real sequence separately using dependencies, weather, inspection and curing constraints, procurement and trade availability. Some activities can overlap once their own predecessors are complete.

Set contingency from identified uncertainty in the work the bid includes, such as undocumented existing framing. Record what costs the reserve covers and the base to which it applies. Escalation accounts for price movement between estimating and buying. Use quote validity, expected purchase dates, any price protection and the contract’s price adjustment terms. A current firm quote may lock a cost even if the estimate is older. Carry neither allowance as earned profit.

Prevailing wage and certified payroll

The Davis-Bacon Act applies to covered federal construction contracts in excess of $2,000. Separate Related Acts can cover certain federally assisted work. For covered work, price the mechanics and laborers by the applicable wage determination and fringe obligations. Include the administration of weekly certified payrolls under federal rules.

Michigan’s Prevailing Wages on State Projects Act, 2023 PA 10 as amended, applies to covered state projects. The earlier state law’s 2018 repeal does not answer current coverage. Confirm the statute, contracting body, financing and bid documents before pricing wages and fringes, obtaining required registration and arranging certified payroll. A state funding source alone establishes no federal trigger.

Test Your Knowledge

A carpenter earns $32.00 per hour. For this estimate, employer payroll taxes, workers’ compensation and benefits are 9%, 14% and 8% of the same base wage, respectively. What fully burdened hourly rate should the estimator carry?

A

$34.88 per hour

B

$41.92 per hour

C

$44.80 per hour

D

$38.40 per hour

Test Your Knowledge

A two-person crew working eight hours per person per day frames 180 linear feet of wall per day. At that rate, how many worker-hours are required for 540 linear feet?

A

24 worker-hours

B

32 worker-hours

C

96 worker-hours

D

48 worker-hours

Test Your Knowledge

Which project clearly triggers federal Davis-Bacon wage and weekly certified-payroll requirements under the stated facts?

A

A $450,000 federal agency construction contract for a veterans clinic addition

B

A county road job paid entirely with state funds and no federal assistance

C

A private kitchen remodel financed with a home equity loan

D

A township park restroom built with local funds and no federal assistance