6.2 Addenda & Change Orders

Key Takeaways

  • Issue bid changes as addenda, follow the solicitation’s acknowledgment rules, and identify the applicable addenda in the agreement.

  • An agreed change order records the scope, pricing and any time adjustment. A directive or minor change needs authority under the governing contract and law.

  • Under the federal differing-site-conditions example, Type I compares actual latent or subsurface conditions with affirmative contract indications. Type II compares unknown, unusual conditions with what work of that type normally encounters.

  • For a post-signing oral instruction, verify authority, obtain the required signed change, and comply with notice and claim procedures.

  • Price the changed work using the applicable rates and contract terms. Measure schedule impact against the current schedule, using critical path, float and the applicable calendar.

Last updated: November 2026

Before execution, a bid addendum changes what bidders price. After formation, a signed change order or amendment changes what the parties owe one another. Identify which document applies, who may issue it, and whether the applicable rules require a signature or acknowledgment.

The bid document package

A complete bid set typically contains:

  1. Invitation to bid or advertisement solicits offers.
  2. Instructions to bidders address submission, deadlines, addenda acknowledgment, bid form, withdrawal and evaluation.
  3. Bid form records the bidder’s offer, often with unit prices, alternates and allowances.
  4. Drawings and specifications define the scope.
  5. General and supplementary conditions describe how to administer the contract.
  6. Addenda record revisions to the bid set.
  7. Bid opening, award and execution follow the procurement and agreement requirements. A signed bid and its attachments become contract documents to the extent incorporated.

Addenda during bidding

An addendum corrects, explains or changes bidding documents before execution, typically before the bid submission deadline. Identify the addenda in the final agreement so the scope can be traced back to the bid.

  • Timing. Distribute the updated bid information while bidders can respond. If the change arrives too late for bidders to account for it, follow the rules for extending the deadline or reopening or resoliciting.
  • Acknowledgment. Use the method in the instructions. Omission of acknowledgment for a material change can make a bid nonresponsive. For example, FAR 14.405(d) treats omitted acknowledgment as a minor informality only where receipt is clear from the bid or the change has at most negligible effect under the stated criteria.
  • Uniform distribution. Make the same revision available to all affected bidders under the procurement procedure. A private answer to one bidder can leave the bids pricing different scopes.

Scenario. At the pre-bid meeting, a bidder asks whether the garage door is insulated. The architect answers no, verbally. That answer changes a specification, so it must be formalized in an addendum; otherwise some bidders price insulated doors and others do not, and the bids are no longer comparable. Pre-bid meeting minutes and RFI responses that change price, scope, or quality should be converted into addenda.

Offer and acceptance in bidding

A definite, responsive bid can be an offer. Before treating an award as acceptance, verify the authority of the party making it, the date and method of notice, and any condition such as board approval, signatures or delivery. A bidder’s reservation or exception may make the bid nonresponsive. Check the applicable rules for permitted conditions, mistakes and withdrawal before assuming the owner can disregard a qualification or allow a correction.

Change orders after contract formation

A change order describes the revised work and the agreed price and time adjustments, including zero adjustments where appropriate. State the pricing basis and the unit of time the contract uses. Obtain the required signatures before performing or ordering the changed work. In an AIA A201–2017 contract, Article 7 distinguishes a change order signed by the owner, contractor and architect, the owner-and-architect-signed construction change directive when price or time is still unresolved, and an architect’s written order for a minor change with no adjustment to price or time. Confirm the actual agreement and Michigan signing requirements before relying on authority under a form.

Differing site conditions

FAR 52.236-2 illustrates the two categories on contracts that include it. Type I is a subsurface or latent physical condition materially different from an affirmative indication in the contract. Type II is an unknown, unusual physical condition materially different from those ordinary for that work. The federal clause requires prompt written notice to the contracting officer before disturbing the condition and calls for an equitable adjustment if the investigation confirms the material difference and it affects performance cost or time. On a private residential job, use the actual contract’s condition, notice and authorization provisions.

Suppose the incorporated geotechnical report identifies uniform clean fill at the footing location and excavation exposes a substantial buried debris pit instead. The conflict with that affirmative indication makes this a potential Type I claim. If the documents are silent, the same facts do not establish Type I. A Type II analysis would require proof that the condition was unknown, unusual and materially different from what this class of work normally encounters. Secure the affected area, preserve the evidence and give the required notice before further disturbance. Uncovering rot during remodeling similarly requires checking the actual pricing assumptions and notice provisions before treating its repair as an authorized extra.

Constructive changes and the oral-directive trap

A constructive change is an asserted departure from the agreed scope without a formal change order, for example when an owner directs work beyond what the specifications require. Ask whether the instruction comes from a person with authority and whether it changes a contractual requirement. Under Michigan R 338.1533 the covered builder and customer must sign written changes and the customer gets a copy. For a contractor’s residential lien, MCL 570.1114 separately requires written amendments and additions. A same-day record is evidence of what was said, but does not supply the required signatures. The parol evidence rule concerns earlier or contemporaneous terms. Under Quality Products & Concepts Co v Nagel Precision, Inc, parties may mutually modify a contract or waive a contractual writing condition if the required proof exists, even where the contract bars oral modification. With such a clause, evidence of an oral or written agreement or affirmative conduct must clearly and convincingly show mutual assent. A one-sided instruction or silence alone is insufficient, and common-law waiver of a contractual term is distinct from a statutory or licensing requirement.

Disputed and unilateral changes

Check who may direct work before agreement on price or time and what the contract requires on receipt of that direction. Use the notice and claim deadlines to record both entitlement and the amount sought. A cost record shows what the work cost, while the contract and directive establish whether it is compensable. Preserve the scope, date, authorizing person, cost records, schedule impact and disposition in the change log. A builder handling a customer’s nonurgent oral request should obtain the signed change before doing the extra work.

Pricing methods

MethodHow it worksBest used whenMain risk
Lump sum (negotiated)One fixed price for a fully defined changeScope is clear and smallScope creep reopens the debate
Unit pricesPre-agreed price per unit from the contractRepetitive, measurable work such as concrete, drywall, or excavationQuantity measurement disputes
Time and materialsActual hours at agreed labor rates plus materials at cost plus an agreed markupUndefined or emergency workHours expand without a cap
Cost plus feeReimbursable cost plus a fixed or percentage feeComplex renovations with unknown conditionsAudit burden and fee disputes

Whichever method applies, the change order should state the markup on subcontractor changes, whether overhead and profit are included, whether permit fees and bond costs pass through, and who pays for extended general conditions. Vague markups are a frequent source of disputes that cost more than the change itself.

Time impact analysis basics

Insert the change and its dependent activities into the accepted schedule update just before the event. Compare the projected dates with and without that change using the applicable calendars, activity logic and available float. Check concurrent delays and the affected milestone before requesting a time adjustment. Use the units the contract requires. A schedule impact can support an extension under a time clause, and compensation is a separate question under the contract.

Worked example: the larger window

The signed residential contract includes a 4-foot by 5-foot double-hung window. Before framing its opening or ordering the stock unit, the homeowner asks for a 6-foot by 5-foot picture window. Owner and builder agree to price the net scope difference with a 20% markup on direct change costs and no applicable unit rate.

  1. Classify. The owner is proposing a design change. Determine the new opening, structural support and scope for restoring finishes before pricing.
  2. Price. The parties estimate incremental material costs of $950 for the window, $240 for framing, $210 for siding and trim and $90 for drywall and paint. The material total is $1,490. At 14 hours × $62, labor adds $868. Apply $471.60 of markup (20% × $2,358) to the $2,358 direct cost. The change order is $2,829.60. If the contract instead specifies an applicable unit rate or method, use that rule.
  3. Assess time. Use a common order date and calendar. In the schedule update the original unit is available and installation can start on day 7. The revised unit is available on day 21. The original schedule has four calendar days of float on this sequence, so day 11 is the latest installation start that protects the agreed completion date. Assuming no mitigation, concurrent delay or other logic changes, installation on day 21 projects a 10-calendar-day completion impact. The builder documents that forecast and the parties agree how to adjust the contract date.
  4. Document. Obtain signatures on the revised scope, price and agreed time adjustment before ordering. Confirm the larger opening’s load path and header sizing against the applicable design and permit requirements, and confirm the window’s applicable glazing and energy specifications.
  5. Administer. Update the window schedule, submittal log, change log and payment schedule to match the signed change order.

This change modifies an existing residential agreement. The signed change order records both the authorized work and the terms used to price and schedule it.

Test Your Knowledge

Five days before bid opening, the architect revises the window schedule and the bid instructions require receipt of revisions to be acknowledged with each bid. Which instrument and bidder action are appropriate?

A

A change order the low bidder signs before starting work.

B

An amendment to the future contract signed by every bidder.

C

An addendum to the bid package, acknowledged as the instructions require.

D

An oral announcement to bidders who attend the pre-bid meeting.

Test Your Knowledge

Before the original window is ordered, the homeowner asks for a wider picture window under a signed residential construction contract. The contract has no applicable unit rate. What should the builder do?

A

Negotiate the scope, price and any supported schedule adjustment in a signed change order before ordering.

B

Submit a Type I site-condition claim because the window dimensions differ from the drawings.

C

Order the window on the homeowner’s oral request and skip the change procedure.

D

Submit a product warranty claim to cover the upgrade.

Test Your Knowledge

After signing an integrated residential remodeling contract that requires signed written changes, the homeowner orally asks the builder to add a nonurgent beam outside the agreed scope. What should the builder do before committing the extra work?

A

Rely on the homeowner’s oral request as automatic approval of its price and time.

B

Record the instruction in the daily log and proceed without the customer’s signature.

C

Treat the request as inadmissible because the integration clause bars all statements made after the contract.

D

Document the directive and obtain the required signed change covering scope, price and time, with a copy to the homeowner.