30.3 Foundation Installation, Moisture & Waterproofing
Key Takeaways
R406.1 dampproofing extends from finished grade down to the higher of the footing top and the point 6 inches below the basement floor top. Masonry generally needs at least 3/8 inch of cement parging unless the coating is approved for direct application.
Waterproofing is required where a high water table or other severe soil-water conditions are known to exist; organic-solvent-based products are prohibited on insulating concrete form walls with expanded polystyrene foam.
R405.1 places the required drain at or below the area protected. Gravel or stone drain dimensions, pipe bedding and membrane details are distinct. R405.1.1 gives the specific pipe location and outlet for precast walls on crushed stone footings.
Anchor bolts are 1/2 inch minimum diameter, embedded 7 inches, spaced no more than 6 feet on center, at least two per plate section, with one within 12 inches of each end but not closer than 7 bolt diameters to it.
A ventilated crawl space without ground cover needs 1 sq ft of net opening per 150 sq ft. The 1:1,500 reduction uses an approved Class I ground cover and cross-ventilation. The common R408.3 unvented options use a sealed ground retarder, air pathway and insulated perimeter.
The order of operations
For a concrete or masonry basement, coordinate the following work with the plans, permit inspections and wall system:
- Excavate to suitable undisturbed soil or approved engineered fill, confirm the required inspection and place the footing. The Michigan minimum-depth rule generally requires 42 inches below actual grade, subject to approved modifications and applicable frost protection.
- Build the wall, locate any cast-in anchors before placement and allow the wall to gain the required strength.
- Strip forms, patch tie holes, and apply dampproofing or waterproofing.
- Install drainage: footing drain, gravel, filter fabric, discharge.
- Provide floor anchorage or temporary bracing as required before placing backfill. Coordinate sill and framing installation with that support sequence.
- After the required inspections and approvals, backfill and grade away from the wall.
Steps 3 through 5 are the choke points. Once soil is against the wall, nobody can verify the membrane, the filter fabric or the drain elevation without digging it up.
Sill plates, anchors and structural connections
R404.3 requires a sill plate of at least 2 by 4 nominal lumber. Anchorage comes from R403.1.6:
| Requirement | Value |
|---|---|
| Bolt diameter | 1/2 inch minimum |
| Maximum spacing | 6 feet on center |
| Embedment | 7 inches minimum into concrete or grouted cells of CMU |
| Position in plate | middle third of the plate width |
| Bolts per plate section | at least 2 |
| End distance | one bolt not more than 12 inches from each end, and not less than 7 bolt diameters from the end |
| Hardware | a nut and washer tightened on every bolt |
Approved anchors or straps providing equivalent anchorage may replace bolts. R403.1.6.1 addresses braced-line plate washers for wood light-frame D0, D1 and D2 structures and Category C townhouses, with an approved-strap alternative. Its model washer detail references R602.11.1, under the R602.11 provision excluded by Michigan’s adoption rule. Confirm the state-adopted and approved design details for specialized anchorage. Note the two separate limits at each plate end: within 12 inches of the end, and at least 7 bolt diameters away from it — for a 1/2-inch bolt, 3-1/2 inches.
Worked count. A 28-by-44-foot rectangle uses two 14-ft plate pieces on each short side and four 11-ft pieces on each long side. Assume 1/2-in bolts with a 12-in end setback at both ends of each piece. A 14-ft piece has a 12-ft distance between end bolts, which needs two spaces and three bolts. An 11-ft piece has 9 ft between end bolts, also two spaces and three bolts. Four 14-ft and eight 11-ft pieces need 36 bolts in this example. Count each actual plate piece before adding any design-specific anchors.
Other connections matter as much as the bolts: joist to sill, rim joist to sill, and the continuous uplift path required by R602.3.5 where net uplift exceeds the prescriptive threshold. Fastening schedules live in Table R602.3(1).
Dampproofing versus waterproofing
These are different products with different triggers, and the code is precise about both.
Dampproofing (R406.1) is required on foundation walls that retain earth and enclose interior spaces and floors below grade, unless waterproofing is required. It covers from the higher of the top of the footing or 6 inches below the top of the basement floor, up to finished grade. Approved materials include bituminous coating, 3 pounds per square yard of acrylic modified cement, a 1/8-inch coat of surface-bonding cement complying with ASTM C887, any waterproofing material listed in R406.2, or another approved method. Masonry walls must receive at least 3/8 inch of portland cement parging on the exterior before dampproofing, unless a material is approved for direct application to the masonry. On concrete walls, repair holes and prepare the surface as specified for the selected coating.
Waterproofing (R406.2) is required where a high water table or other severe soil-water conditions are known to exist. The vertical extent is the same. Approved systems include listed roll, sheet or liquid-applied systems, such as 6-mil PVC, 40-mil polymer-modified asphalt or 60-mil solvent-free liquid-applied synthetic rubber. Use the listed material and thickness for the chosen system. All membrane joints must be lapped and sealed with a compatible adhesive.
The ICF exception is worth remembering: organic-solvent-based products — hydrocarbons, chlorinated hydrocarbons, ketones, esters — may not be used on ICF walls with expanded polystyrene form material, because the solvent attacks the foam. Plastic roofing cements, acrylic and latex coatings, mortars and pargings are permitted on ICF, and hot asphalt must be Type C of ASTM D449 applied below 200 degrees F.
Foundation drainage
R405.1 requires drains around concrete or masonry foundations that retain earth and enclose habitable or usable spaces below grade. The details are dimensional and testable:
- Drains go at or below the area to be protected and discharge by gravity or mechanical means into an approved drainage system.
- Gravel or crushed stone drains extend not less than 1 foot beyond the outside edge of the footing and 6 inches above the top of the footing, and are covered with an approved filter membrane.
- Perforated pipe sits on at least 2 inches of washed gravel or crushed rock no less than one sieve size larger than the perforations, and is covered with at least 6 inches of the same material.
- Protect open drain-tile joints with building paper. Unless the drain manufacturer recommends otherwise, use approved filter membrane around perforated drainage or over the aggregate covering it.
- The R405.1 exception covers well-drained ground or qualifying sand-gravel Group I soils.
Filter material helps keep fines out of the drain. For a retaining precast wall on a crushed stone footing enclosing usable or habitable below-grade space, R405.1.1 specifies a perforated pipe below the wall base. It can be inside or outside, at least 1 ft beyond the wall edge. Cover an exterior pipe with approved filter membrane and discharge to daylight or an approved sewer system.
Joints, penetrations and sealants
Inspect transitions and penetrations while keeping the membrane continuous across the wall field:
- Cold joints between footing and wall, and construction joints in the wall. R404.1.3.3.7.8 requires construction joints in plain concrete walls to be located at points of lateral support, with at least one No. 4 bar crossing the joint at no more than 24 inches on center and 12 inches of embedment on each side; reinforced wall joints go in the middle third of the span between supports or follow the plain-wall detail. The section also permits the specified vertical reinforcement to satisfy the joint steel requirement when the spacing conditions are met.
- Form tie holes, which must be repaired in accordance with the approved coating or membrane details.
- Pipe penetrations and electrical sleeves, which need boots or a sealant compatible with the membrane rather than a smear of mastic.
- Window wells, which drain to the foundation drainage system or an approved alternative under R310.2.3.2, subject to its well-drained soil exception. A cover, if installed over an escape opening, must satisfy the applicable operation and clearance requirements.
- The sill line, where the wood plate meets concrete. A sill seal gasket plus anchorage keeps air and capillary moisture out, and the plate must be decay resistant where R317 requires it.
- Wood panel joints, sealed full length with caulking per R406.3.1, and precast panel joints sealed per R406.4.1 with an ASTM C920 sealant.
Basement versus crawl space moisture control
Separate bulk-water control from energy and vapor control. In Michigan’s prescriptive energy path, conditioned basement walls in Zone 5A use R-10 continuous or R-13 interior cavity insulation. Zones 6A and 7 use R-15 continuous or R-19 interior cavity, or the permitted combination of R-13 interior cavity plus R-5 continuous. R601.3 as amended includes specific below-grade vapor-retarder provisions. Coordinate those with the wall’s insulation and drying strategy.
A crawl space has two code-approved strategies:
- Ventilated. R408.1 and R408.2 require net ventilation area of 1 square foot per 150 square feet of under-floor area, with one opening within 3 feet of each corner, and openings covered with corrosion-resistant mesh or plates whose openings are no larger than 1/4 inch. Where the ground is covered with an approved Class I vapor retarder and cross ventilation is provided, the required area drops to 1 square foot per 1,500 square feet.
- Unvented. R408.3 requires continuous Class I ground cover with 6-inch sealed or taped laps and edges sealed to the stem wall or insulation at least 6 inches up the wall. For new work, provide either continuously operated exhaust or conditioned supply at 1 cubic foot per minute per 50 square feet, with the corresponding air pathway to the common area and perimeter insulation under the applicable energy provisions. R408.3 also has a compliant existing-plenum option.
A ground retarder limits moisture migration from exposed soil. Verify the planned ventilation or conditioning and follow the applicable ground-cover details.
Inspection and backfill timing
Before the excavator returns, walk the wall with a checklist in hand:
- Required wall treatment continuous over the specified extent, with membrane laps sealed and top edge terminated as detailed.
- Tie holes and penetrations patched.
- Footing drain at the correct elevation, pipe orientation per the approved detail, with gravel and filter material as required, discharge confirmed.
- Concrete or masonry wall has sufficient strength and required floor anchorage or bracing under R404.1.7. That section exempts walls with less than 4 ft of unbalanced backfill from bracing.
- For wood foundations: basement and first floors framed or bracing installed, panel joints caulked, poly membrane and grade strip complete.
- Sill anchors set at the correct spacing and embedment before the wall is loaded.
Backfill in lifts, keep heavy equipment off the wall face, and meet R401.3. Generally provide 6 inches of grade fall in the first 10 feet. Where a physical barrier precludes that fall, provide a drain or swale. Keep nearby impervious surfaces sloped at least 2 percent away from the building. A foundation that is dry in October can still fail in March if the grade drains toward the wall or a downspout dumps at the corner.
An 8-foot concrete basement wall needs dampproofing under MRC R406.1. From finished grade down, how far must the dampproofing extend?
To the higher of the top of the footing or 6 inches below the top of the basement floor
To the top of the footing in every case
To a point 12 inches below finished grade
Only to the top of the perimeter drain pipe
Under what condition may the foundation drainage system required by R405.1 be omitted?
The wall is dampproofed with bituminous coating
The wall is at least 10 inches thick
The backfill is clay rather than sand
The foundation is installed on well-drained ground or sand-gravel Group I soils
A crawl space has bare earth with no ground cover. What minimum net ventilation area does MRC R408.1 require?
1 square foot per 1,500 square feet of under-floor area
1 square foot per 500 square feet of under-floor area
1 square foot per 150 square feet of under-floor area
1 square foot per 50 square feet of under-floor area