28.2 Dewatering
Key Takeaways
Dewatering serves four purposes: keep the excavation and footing subgrade dry, keep slopes and sidewalls stable, prevent hydrostatic uplift and bottom heave, and allow concrete to be placed and cure without standing water.
Identify whether the water is storm runoff, pumped groundwater or contaminated water and where it will go. Use the sediment controls and treatment required for that water, confirm applicable Part 31 coverage or authorization, and get sewer operator approval for any sewer discharge.
Apply the Part 91 earth-change tests and exemptions to the work. Include dewatering facilities in a required SESC plan and keep sediment from leaving in runoff. Check discharge authorizations separately.
Lowering a water table raises effective stress in the soil, so dewatering near existing structures can cause settlement; monitoring points and a survey baseline should be established before pumping begins, and the geotechnical engineer sets the tolerable movement.
Conventional wellpoints are commonly limited to about 15 feet of drawdown per suction stage at sea level. Site conditions can reduce that capacity. Staged wellpoints, deep wells and ejector systems are alternatives when supported by design.
Quick Answer: Plan the dewatering method, monitoring, treatment and outlet before excavation. Part 91 governs applicable earth changes and runoff sediment. Pumped groundwater or other discharges may require separate authorization under Part 31 and from the system operator.
The depth and seasonal variation of groundwater are site-specific. Where seepage or groundwater can affect the excavation, size the dewatering system to the expected inflow and the pressure or water level that the construction sequence can tolerate.
Dewatering does five jobs on a residential site:
- Dry working conditions. Crews cannot form, place rebar or finish a footing in 6 inches of water, and a footing poured into water loses cement at the contact surface.
- Slope and sidewall stability. Water pressure reduces the effective stress that holds soil particles together. Seepage toward an excavation face causes piping and boiling - sand running like a liquid at the toe - which is both a MIOSHA hazard and a structural threat to anything nearby. MIOSHA Part 9 requires ongoing competent-person inspection and another inspection after each rainstorm or other hazard-producing event. Select sloping or support under Rule 941 and take the precautions required by Rule 932 before employees work with accumulated or accumulating water.
- Preventing uplift and bottom heave. Water pressure under a slab or an empty tank pushes up. A basement slab poured on a site where the water table rises after pumping stops can crack, and a buoyant structure can float if it is dewatered during construction and then refilled.
- Protecting concrete during cure. Concrete placed against flowing water is washed and weakened, and cold-weather protection is impossible with water running through the excavation.
- Protecting the finished waterproofing and drain system. A dry excavation lets the membrane be applied and inspected, and lets the drain tile be laid to grade before backfill.
Regulatory Hooks
| Requirement | Source | What it means on site |
|---|---|---|
| Erosion and sediment control | MCL 324.9112 and R 323.1703, 1704, 1705 and 1709 | Apply the earth-change threshold and exemptions. Include on-site drainage and dewatering in a required SESC plan and remove accelerated erosion sediment from runoff before it leaves. |
| Owner responsibility | MCL 324.9112(2) | The property owner is responsible for compliance with permit terms |
| Earth change definition | MCL 324.9101(9) | Human-made change in natural cover or topography, including cut and fill, that may contribute to erosion or sedimentation of state waters. Crop plowing and tilling are excluded. |
| Sediment definition | MCL 324.9101(16) | Solid particulate in suspension or being transported - which is what muddy pumped water is |
| Excavation safety | MIOSHA Part 9, Rule 932 | Protect workers from water accumulation and monitor water removal equipment through a competent person or monitoring system. |
| Discharge authorization | MCL 324.3112 and applicable Part 21 or Part 22 rules | Verify outlet approval, the type of water and any required EGLE authorization. |
Part 91 permits and local ordinances are administered by county enforcing agencies or municipal enforcing agencies, and the approved SESC plan documents the approved site controls. The general trigger is at least 1 acre disturbed or disturbance within 500 feet of the water’s edge of a lake or stream, subject to exemptions and any applicable local ordinance. Review water discharge requirements with EGLE and the outlet operator independently of Part 91.
Methods Compared
| Method | How it works | Best for | Limits and cautions |
|---|---|---|---|
| Sump and ditch (open pumping) | Low point, sump pit lined with filter fabric and gravel, pump with float control | Glacial outwash, gravelly sand, limited inflow, small footings | Fines migrate and the sump silts up; boiling can develop at the sump; not adequate in fine sand or silty soils without filtering |
| Wellpoint system | Header pipe with closely spaced small risers (points) around the perimeter, connected to a vacuum-assisted pump | Sandy soils, granular deposits, basements and utilities 10 to 18 ft deep | About 15 ft of drawdown per conventional suction stage at sea level, affected by elevation and head losses. Design point spacing for soil conditions and inflow. |
| Deep wells | Large-diameter pumped wells with submersible pumps, spaced farther apart | Deep excavations, high permeability gravel, large drawdown, multi-stage needs | Higher cost and power demand; drawdown cone extends far, so off-site impacts are larger |
| Relief or horizontal drains | Perforated pipe or gravel drain installed to intercept seepage before it reaches the face | Cut slopes, hillside sites, controlling seepage through a specific seam | Passive; provide a stable outlet at a suitable elevation |
| Ejector (eductor) system | Water jet creates vacuum to lift water from deep points | Deep drawdown in tight soils, low clearance | Complex, high water consumption, usually a specialty subcontract |
Choosing a method is a soil decision. Gravel and coarse sand yield high inflow but release water readily, so open pumping with a filtered sump often works. Fine sand and silty sand are the dangerous soils: seepage carries fines, the face boils, and the surrounding ground loses volume, so wellpoints that draw the water down before it reaches the face are safer. Clay can yield little water through its matrix while sand lenses or fissures transmit significant seepage. Water pressure and stratification can affect stability in clay and rock as well. Assess the actual flow paths, groundwater pressure and outlet capacity before selecting a system.
Worked Scenario: A High-Water-Table Lot
A 1,800-square-foot ranch near Grand Rapids needs an 8-foot basement. Test borings show 4 feet of sandy loam over silty sand (SM) to 12 feet, then stiff clay till. The seasonal high water table is 30 inches below existing grade. The plan:
- Establish the baseline before digging. Install two piezometers at the perimeter and photograph existing cracks in the neighbor's driveway 25 feet away. The geotechnical engineer sets the tolerable settlement and the action level.
- Install perimeter wellpoints around three sides, with the header discharging away from the neighbor. In this example the design selects a target water level 10 feet below existing grade. From the starting 2.5-foot depth, the planned drawdown is 7.5 feet. The designer sets the point spacing and pump size for the soil and inflow to achieve that target.
- Keep a filtered sump at the low corner for local seepage and rain, lined with filter fabric and gravel, with a backup pump on site.
- Hold the water table below the footing subgrade at all times, and keep pumping through concrete placement and initial cure. Stopping the pump during a pour is how footings get undermined.
- Discharge through treatment. Route the header to a settling basin or filter bag sized for the flow, then to the approved outlet. Confirm applicable discharge authorization and sewer operator consent before using a storm structure. Include the dewatering facilities in the SESC plan if one is required.
- Monitor. Read piezometers daily and after every rain, have the competent person inspect as work proceeds and after rainstorms or other hazard-producing events, check the discharge for visible sediment, and survey the neighbor's structures weekly while pumping continues.
- Shut down in stages. After waterproofing, drain tile, backfill and slab are complete, reduce pumping gradually, and leave the permanent sump and drainage in service.
Pumping math matters for the discharge plan. A single 40-gallon-per-minute pump running 10 hours moves 40 x 60 x 10 = 24,000 gallons, roughly the volume of a small swimming pool. Two pumps each delivering 40 gallons per minute continuously for seven days would move 806,400 gallons, which is why a settling basin and a named outlet are part of the dewatering design rather than an afterthought. A 5-gallon-per-minute trickle is 7,200 gallons a day and still deposits a visible fan of silt if it is dumped on a bare slope.
Inspection Schedule for the Same Job
| Stage | What is checked | Frequency |
|---|---|---|
| Before excavation | Utility locates complete, erosion controls installed, piezometer baseline, neighbor survey and photos | Once, documented |
| During excavation | Competent person walk, protective system condition, seepage or boiling at the face, water level relative to subgrade | Ongoing and after every rainstorm or other hazard-producing event |
| Before concrete placement | Footing subgrade firm and dry, primary and backup pumps running, discharge treatment working | Each placement |
| During concrete cure | Pump running continuously, no water against fresh concrete | Continuous through initial cure |
| Backfill | Inflow response, settlement points re-read, lift thickness and grade | Each lift and each day |
| Post-construction | Sump and drain tile functioning, monitoring points stable, erosion controls removed only after the site stabilizes | Weekly, then monthly |
Discharging Pumped Water
The rules are simple and the violations are common:
- Control sediment. Size a settling basin, weir tank or approved filter for the actual flow and sediment load. Check for tears, bypass and a stable outlet. Sediment removal alone cannot address dissolved contaminants.
- Check the discharge pathway. Construction stormwater coverage under R 323.2190 addresses the stormwater discharge. For pumped water, ask EGLE what authorization applies to the source, quality and receiving water. Before using a storm or sanitary sewer, verify that the operator accepts the proposed discharge and identify any separate state requirements.
- Check any groundwater exception. R 323.2210(e) can allow a discharge to the ground or groundwater from a temporary construction dewatering well without a Part 31 permit for that pathway, if it meets R 323.2204 and the water pumped does not create a Part 201 contamination site. Check the rules for the well itself and any other applicable approvals.
- Control energy and route. Use an approved stabilized outlet and protect adjoining land. Confirm separate requirements before any use of a wetland, waterbody or off-site outlet.
- Watch the temperature and the season. Discharge onto frozen ground creates an ice sheet and a liability; discharge into a stream can be limited by temperature and flow rules during low-flow periods.
Dewatering Near Existing Structures
Lowering a water table removes buoyancy support and increases effective stress in the soil below. In loose granular soil movement can occur quickly. In compressible clay or peat it may continue over time. The affected area can extend beyond the property line. Prevention is procedural:
- Survey and photograph adjacent structures, walls, walks and utilities before pumping.
- Place monitoring points between the excavation and the structure at risk.
- Consider recharge wells between the excavation and the structure to maintain the water table where it is needed.
- Operate at the designed drawdown and use the project’s standby and shutdown procedures.
- Treat a settlement reading that exceeds the engineer's action level as a stop-work event, not a data point.
Winter Dewatering and Shutdown
Michigan winter adds failure modes: discharge lines freeze and back up into the excavation, hoses crack, and frozen outlets can block flow. Inspect outlets and protect the installed sediment controls from damage or bypass. Pumps need a heated enclosure or freeze protection, discharge lines need continuous fall with no low spots, and the excavation needs to be shaped so meltwater runs to the sump instead of into the footing trench. Concrete placed in cold weather needs the water controlled so blankets and heaters can do their job.
Shutdown is planned, not improvised. End pumping when the design and site monitoring show the structure and permanent drainage can handle groundwater recovery. Arrange closure of temporary points and monitoring holes under the applicable rules. R 325.1761 through R 325.1766 govern plugging of dewatering wells.
Exam Traps
- Pumping muddy water straight to a storm drain bypasses sediment control and can be an unauthorized discharge. Provide treatment and confirm approval for the outlet and discharge.
- Stopping the pump during a footing pour undermines fresh concrete and is never the money-saving choice.
- Assuming a sump is enough in fine sand ignores boiling and piping, which is precisely where wellpoints belong.
- Ignoring the neighbor’s foundation leaves the contractor without pre-pumping measurements for detecting settlement.
- Dewatering a site, then letting the water table rebound against fresh waterproofing and an empty basement can expose the structure to uplift or water entry that the design must account for.
- Treating the SESC plan as the only approval can overlook separate discharge requirements. MCL 324.9112 makes the owner responsible for applicable permit terms.
Which dewatering method is commonly limited to about 15 feet of drawdown per conventional suction stage at sea level?
Relief drains daylighted at the slope face
Deep wells with submersible pumps
Wellpoint systems
Filtered sump pits
A crew plans to pump clear-looking water from a foundation excavation into the street storm sewer. What is the correct guidance?
It is acceptable because groundwater is clean and the storm sewer carries rainwater
Verify the outlet operator’s approval and the applicable discharge authorization, and provide the treatment required for the water.
It is acceptable only if the pump runs at less than 10 gallons per minute
It is acceptable if the discharge is screened with a filter bag at the hose end
Why is settlement monitoring specified when dewatering next to an existing house?
Pumping is prohibited within 50 feet of any structure
Dewatering always raises the water table under the neighbor's foundation
Lowering the water table increases effective stress and removes buoyancy support, which can consolidate soil under nearby foundations
Monitoring is only needed where the neighbor has a basement
Sections you finish are checked off in the contents.