27.2 Grading: Cut, Fill & Slopes
Key Takeaways
The average-end-area method computes volume as the average of two cross-section areas multiplied by the distance between them; 40 square feet and 60 square feet over 100 feet averages 50 square feet and yields 5,000 cubic feet, or 185 cubic yards.
Divide a volume expressed in cubic feet by 27 to convert it to cubic yards. Use loose cubic yards when comparing hauled soil with a truck’s loose-volume capacity.
If compaction reduces bank volume by 15 percent, 400 compacted cubic yards requires about 471 bank cubic yards. A 25 percent swell converts 300 bank cubic yards to 375 loose cubic yards.
2015 MRC R401.2 requires fill soils that support footings and foundations to be designed, installed and tested in accordance with accepted engineering practice, which is why structural fill is compacted in lifts and verified by density testing rather than simply pushed into place.
Set rough grade from the specified finish elevation minus the thickness of topsoil, pavement or other material still to be placed. Check the finished surface for drainage away from the building.
Grading is the controlled reshaping of a site to produce two things at once: a building pad at the elevation the plans call for, and a surface that sheds water to a legal outlet. A contractor who can move dirt is common; a contractor who can move the right amount of dirt, to the right elevation, and prove it with numbers is the one who stays in business. Part 91 defines an earth change as a human-made change in the natural cover or topography of land, including cut and fill activities (MCL 324.9101(9)), which is why the erosion-control requirements in Section 27.3 attach to exactly the work described here.
Cut, Fill and the Balanced Site
Cut is excavation: soil removed to lower the grade, form a basement, create a swale, or reach a bearing stratum. Fill is soil placed and compacted to raise the grade, build a pad, or backfill against a foundation. A balanced site has enough usable cut to supply the required fill after both quantities are expressed on the same volume basis. Exclude unsuitable material and track topsoil separately. An unbalanced site needs borrow (import) or waste (export), and both cost money twice: once for the earthmoving and again for the trucks, the haul route, and the dust and tracking control that a permitted earth change will require.
| Operation | Typical equipment | What the contractor must control |
|---|---|---|
| Strip topsoil | Dozer, scraper, excavator | Depth of strip, stockpile location, separation from subsoil |
| Cut / excavate | Excavator, dozer, scraper | Cut depth to design subgrade, slope stability, drainage during work |
| Place fill | Dozer, loader, plate or roller | Lift thickness, moisture, compaction density, testing |
| Rough grade | Grader, skid steer | Specified rough elevation, allowance for finish materials, positive drainage |
| Finish grade | Grader, hand tools, laser | Design elevation and tolerance, drainage slope, seedbed or pavement transition |
The finished floor elevation (FFE) comes off the plot plan or site plan, and it ties the whole site together: FFE drives the foundation height, the garage slab, the driveway approach, the swale inverts, and the minimum cover over the water and sewer laterals. Setting the pad from a stake that nobody checked against the survey benchmark is how a house ends up with a driveway that rises 3 feet in 40 feet or a rear yard that drains into the neighbor's crawlspace.
Measuring Volumes: The Average-End-Area Method
The standard estimating tool for linear earthwork is the average-end-area method:
where and are the cross-section areas at each end of a segment and is the distance between them.
Worked example 1. Two cross sections 100 feet apart have areas of 40 square feet and 60 square feet. Average area = (40 + 60) / 2 = 50 ft². Volume = 50 ft² x 100 ft = 5,000 ft³. Divide by 27 ft³ per cubic yard: 5,000 / 27 = 185.19, so 185 cubic yards.
Worked example 2. Three sections 50 feet apart with areas of 20, 55 and 45 square feet. First segment: (20 + 55) / 2 x 50 = 1,875 ft³. Second segment: (55 + 45) / 2 x 50 = 2,500 ft³. Total 4,375 ft³ / 27 = 162 cubic yards.
The method assumes the cross sections are parallel and the change between them is gradual. Where the ground changes abruptly, or where a single long segment is used across irregular terrain, the result drifts; surveyors then break the work into shorter segments or use the prismoidal formula, which weights the mid-section. For exam purposes, the average-end-area calculation is the one being tested, and the arithmetic error candidates make is forgetting to divide by 27.
The grid (borrow pit) method
For areas rather than corridors — a building pad, a parking lot, a borrow pit — the grid method overlays a square grid on the site, records existing and proposed elevations at each node, and treats the difference as a depth of cut or fill. For each rectangular cell, average its four corner depths, multiply by the cell area, and add the cell volumes. Shared nodes contribute to each adjacent cell. Split mixed cut-and-fill cells along the estimated zero-depth line so excavation and fill quantities remain separate. Divide the resulting cubic feet by 27 for cubic yards.
Worked example 3. A 120 × 100 ft pad has two 60 × 100 ft cells. Read the top row of cuts from left to right as 0.3, 0.5 and 0.7 ft, and the bottom row as 0.5, 0.7 and 0.3 ft. The left cell averages (0.3 + 0.5 + 0.5 + 0.7) ÷ 4 = 0.50 ft and the right cell averages (0.5 + 0.7 + 0.7 + 0.3) ÷ 4 = 0.55 ft. The estimated cut is 6,000 × (0.50 + 0.55) = 6,300 ft³, or about 233 bank cubic yards. The two middle readings each serve both cells.
Shrinkage, Swell and the Three Cubic Yards
Soil volume is quoted in three different states, and mixing them up is the classic estimating failure:
- Bank cubic yards (BCY) — in place, undisturbed, as measured in the ground.
- Loose cubic yards (LCY) — excavated and broken, as it sits in a truck or stockpile.
- Compacted cubic yards (CCY) — placed in lifts and densified, as it exists in the finished fill.
Shrinkage in this example measures compacted volume lost as a percentage of the starting bank volume. Excavation swell measures loose volume gained as a percentage of that bank volume. Confirm the starting and ending states and the direction of any conversion multiplier in the geotechnical report.
Worked example 4. A pad needs 400 CCY. Compaction reduces the starting bank volume by 15 percent, so 1 BCY yields 0.85 CCY. Divide 400 by 0.85 to get 470.59 BCY, or 471 BCY to the next whole yard. Check: 471 × 0.85 = 400.35 CCY. Allowing just 460 BCY would yield only 391 CCY.
Worked example 5. A basement excavation yields 300 BCY of clay that must be hauled off. At 25 percent swell, the loose volume is 300 x 1.25 = 375 LCY. At 12 LCY per truck, that is 375 / 12 = 31.25, so 32 loads — always round truck counts up.
Rough Grade Versus Finish Grade
Rough grade establishes the building pad and drainage and leaves room for the thickness of finish materials. For example, allow 0.5 foot below the planned finish surface where the plan calls for 6 inches of topsoil. Strip and stockpile the topsoil separately from structural fill. Finish grade is the design elevation of the completed surface. Check elevations, drainage and transitions to walks and driveways against the approved plans and applicable local verification requirements.
Worked example 6. The plot plan sets FFE at 100.00. The assembly is a 4-inch slab over a 10-inch compacted base. The top of the base is 100.00 − 4/12 ≈ 99.67. The top of the subgrade is 100.00 − 14/12 ≈ 98.83. If the excavator cuts to 98.20, the pad is about 0.63 foot low and needs structural fill — not a bucket of loose dirt pushed around with a skid steer.
Grade Stakes, Elevations and Machine Control
Grade is communicated three ways: cut-and-fill stakes (a lath marked with the cut or fill at that point), offset stakes set outside the work area so equipment does not destroy them, and laser or GPS machine control that reads a design surface directly. All three depend on a benchmark tied to the survey. On foundations, the critical checks are depth of excavation to the bearing stratum, top-of-footing elevation, and the relationship between FFE, garage slab and driveway. Check the garage floor elevations and drainage on the approved plans and compare the driveway profile with the applicable local limits.
Worked example 7. A driveway rises 5 feet over 60 feet of run. Grade = 5 / 60 = 0.083, or 8.3 percent. If the local maximum for the run is 12 percent, it meets that limit. Check the transitions at the apron and crest separately for vehicle clearance.
Slope Rules: Minimums for Water, Maximums for Use
Slope is a two-sided constraint. Too flat and water ponds; too steep and the surface erodes, mowers cannot operate, and vehicles scrape.
| Element | Minimum or maximum | Basis |
|---|---|---|
| Grade away from foundation | 6 in within the first 10 ft (5%) | 2015 MRC R401.3 |
| Impervious surface within 10 ft of foundation | 2% minimum away from building | 2015 MRC R401.3 exception |
| Swales and ditches | Positive drainage at a nonerosive velocity per approved design | 2015 MRC R401.3 drainage intent; Part 91 rule R 323.1709(3) |
| Lawn areas | Avoid steeper than about 3:1 for maintainability | Industry practice, not code |
| Driveways | Check applicable local limits and approved profile | Verify with the enforcing agency |
| Cut and fill slopes | Designed for soil type, slope geometry and water conditions | Site design and geotechnical criteria |
Two code hooks deserve emphasis. First, R401.2 states that fill soils that support footings and foundations shall be designed, installed and tested in accordance with accepted engineering practice. The accepted design and specifications determine lift thickness, moisture control and the tests used to accept structural fill. Second, R401.3 requires the finished grade to carry water away from the wall, which means the final pass of the grader is the one that determines whether the foundation stays dry.
For a prescriptive concrete slab-on-ground, R506.2.1 requires clean fill compacted to support the slab uniformly. Without approval, total fill depth is limited to 24 inches for clean sand or gravel and 8 inches for earth. Those limits are total depths. The design or project specifications may set separate lift thicknesses, moisture ranges and density tests. Confirm the approved repair if the crew over-excavates a building pad.
Exam Traps
- Computing cubic yards and forgetting the 27. Volumes arrive in cubic feet and leave in cubic yards.
- Using the wrong end areas. Average the two cross-section areas first, then multiply by length; sum the individual segment volumes once each has been calculated.
- Treating shrink and swell as the same number. Shrinkage reduces bank volume into a compacted fill; swell increases bank volume when loosened for hauling.
- Grading the finish surface toward the house. A yard that looks perfect and ponds at the wall fails R401.3 and will produce a wet basement.
- Leaving topsoil under fill. Organic material settles for years; the resulting depression becomes a swale pointed at the foundation.
- Setting the pad from a single stake. Always verify against the benchmark and the plot plan, and check FFE against garage slab and driveway geometry.
- Assuming the fill under a slab does not need testing. Check R506.2.1 for slab-support fill and R401.2 wherever the fill supports footings or foundations. Follow the approved testing requirements for the specific application.
A reliable workflow ties the section together: read the plot plan for FFE and drainage, strip and stockpile topsoil, cut and fill to rough grade in lifts with moisture and density control, verify elevations against the benchmark, cut the swales to positive fall, then finish grade to provide the required fall or drainage separately for earth grade and nearby impervious surfaces — and document the elevations that prove it.
Two cross sections 100 feet apart have areas of 40 square feet and 60 square feet. Using the average-end-area method, what is the volume in cubic yards?
148 cubic yards
185 cubic yards
222 cubic yards
370 cubic yards
A contractor needs 400 cubic yards of compacted fill and the geotechnical report says compaction reduces the starting bank volume by 15 percent. How much bank cubic yardage must be excavated or imported?
340 bank cubic yards
400 bank cubic yards
471 bank cubic yards
460 bank cubic yards
For an ordinary concrete slab-on-ground built under 2015 MRC R506, what is required for the fill beneath the slab?
Fill under slabs needs no compaction if the slab is reinforced
Stripped topsoil can remain under 6 inches of gravel
Only a post-tensioned slab requires uniform support
Fill must be free of vegetation and foreign material and compacted for uniform slab support