43.1 Masonry Reinforcement

Key Takeaways

  • R606.3.4 requires at least 5/8 inch of mortar cover from the exposed face for horizontal joint reinforcement. Match the wire to the cell layout and the applicable corrosion schedule.

  • Keep ordinary bars at least 1/4 inch clear of units in grouted masonry. R606.3.5.3 also requires bars secured at top, bottom and at intervals no greater than 200 bar diameters.

  • Ordinary reinforcing bars need cover of at least one bar diameter and at least 3/4 inch, or at least 2 inches where exposed to weather or soil. The hollow-cell vertical steel area limit is 6 percent of the grout-space area.

  • R606.3.7.2 checks horizontal steel area and spacing for stack bond. R606.12 adds separate, category- and element-specific seismic requirements.

  • A 20-inch lap for a No. 4 bar equals 40 bar diameters. Use the specified project lap in the takeoff, accounting for one overlap at each splice.

Last updated: November 2026

Masonry carries compression efficiently. Where bending, in-plane forces or restrained movement create tension, steel can carry tension and limit cracking. The type and placement of that steel depend on the forces and the approved wall detail. Under 2015 Michigan Residential Code (MRC) R606.1, identify the prescriptive R606 route or the design route under TMS 402/ACI 530/ASCE 5 or TMS 403 before selecting reinforcement.

Horizontal Joint Reinforcement

Factory-welded joint reinforcement consists of longitudinal wires connected by cross wires. In ladder reinforcement the rungs can be selected and positioned to clear the grout cells while the long wires follow the face shells. Diagonal truss wires give greater in-plane rigidity and can obstruct vertical bars or grout. In a reinforced CMU wall, check the actual wire, cell and cross-web layout before placing either product. A 3/8-inch bed joint leaves little room for two overlapping welded assemblies and their mortar, so stagger the splices as the approved detail directs. Keep at least 5/8 inch of mortar between the joint reinforcement and the exposed face (R606.3.4). Follow the corrosion schedule in Table R606.3.4.1.

Wire numbers denote hundredths of a square inch of cross-sectional area. W1.7 has 0.017 square inch and is about 0.148 inch in diameter. W2.8 has 0.028 square inch and is about 0.189 inch in diameter. Common joint reinforcement details use a 6-inch wire lap. Use the specification for the selected assembly and keep that lap distinct from a reinforcing-bar splice.

Running bond under R606.3.7.1 uses a head-joint offset of at least one-quarter of the unit length, unless the wall is reinforced as stack bond. Under R606.3.7.2, when the offset is smaller, provide horizontal steel totaling at least 0.0007 times the vertical wall cross section, in bed joints or bond beams no more than 48 inches apart. Check steel area and spacing independently. An applicable seismic detail can add requirements.

Vertical Bars in Grouted Cells

Dry lay the specified CMU to confirm that the reinforced cells align with the foundation dowels. A nominal 8-inch course, made with a 7-5/8-inch-high unit and a 3/8-inch mortar joint, is a layout module. Cell locations still depend on the manufactured unit and bond pattern. Coordinate corners, openings and construction joints with the reinforcement schedule. A No. 4 bar is nominally 1/2 inch with 0.20 square inch of area. A No. 5 is 5/8 inch with 0.31 square inch. A No. 6 is 3/4 inch with 0.44 square inch.

R606.3.5.3 requires steel positioned at the top and bottom and at intervals no greater than 200 bar diameters. Maintain at least 1/4 inch of grout or mortar between ordinary bars and units, and fill cells containing reinforcement. Table R606.3.5.1 also limits vertical reinforcement to 6 percent of the grout-space area in hollow units. Under R606.3.4 the cover over ordinary bars is at least one bar diameter and at least 3/4 inch, or at least 2 inches where exposed to weather or soil. Clearance to the unit, cover over the steel and the allowable steel area each answer a separate inspection question. Check all three before pumping grout, especially at laps and congested openings.

Bond Beams and Lintels

A bond beam is a reinforced, grouted horizontal course that can tie the wall together or receive anchors. A masonry lintel spans an opening and must be designed to carry the loads above it (R606.10). Open-bottom or knockout bond-beam units let grout pass where the drawings call for continuity with vertical cells. Use the approved detail to keep grout out of cells that should remain open. Verify the number and size of bars, lap locations and end details from the approved drawings. Before grout placement, inspect corners for the specified bent or lapped bars, ties for the specified cover, and anchor locations for clashes with bars.

Seismic Detailing Under R606.12

The prescriptive seismic provisions apply in Categories D0, D1 and D2, and R606.12.2 applies to townhouses in Category C. The section excludes qualifying glass-unit masonry, anchored veneer and adhered veneer, which have separate provisions. R606.12.1 also allows the designated TMS design alternatives.

In the R606.12.2 example of a masonry partition outside the lateral force-resisting system, isolation joints and connectors accommodate story drift. For the horizontal option, use W1.7 longitudinal wires in bed joints no more than 16 inches vertically apart, two or more wires where the wall is wider than 4 inches and one or more otherwise, or a No. 4 horizontal bar at up to 48 inches. Provide horizontal steel within 16 inches of the top and bottom. The vertical option uses No. 4 bars at up to 48 inches and within 16 inches of each wall end. These limits describe that partition detail.

For masonry shear walls under R606.12.2.3.3, locate vertical No. 4 bars at corners, within 16 inches of each side of openings, within 8 inches of each side of movement joints and within 8 inches of wall ends, at no more than 10 feet on center. Horizontal reinforcement uses two or more W1.7 wires at up to 16 inches vertically, or at least one No. 4 bond-beam bar at up to 10 feet. Install it at the top and bottom of openings, at floor and roof connections and within 16 inches of the wall top. At openings the bars extend past the opening by at least 24 inches or 40 bar diameters, whichever is greater. That extension and a bar splice serve different purposes. In D0 and D1, R606.12.3.2 also prescribes steel ratios for the walls it covers, with 0.002 combined and at least 0.0007 in each direction. Its 48-inch spacing allowance depends on the specified solid-grouted wall construction. Other masonry under that provision has a 24-inch cap, and R606.12.3.2.1 separately limits shear reinforcement spacing to the least of one-third the length, one-third the height and 48 inches.

Worked Example: Lapping Bars in a Bond Beam

An approved detail specifies a 20-inch lap for No. 4 bars in a 36-foot straight beam run. For a 1/2-inch bar that lap is 40 bar diameters. A comparable 40-diameter label appears in a particular 2015 MRC seismic figure. TMS 402-13 Section 8.1.6.7.1 likewise has its own design-based splice provisions for allowable stress design, so confirm the actual project lap before doing the takeoff.

With two 20-foot bars and one lap, the net continuous run is 40 feet minus 20 inches, or 38 feet 4 inches. That covers the illustrated run. With 10-foot stock, four bars have three laps, totaling 60 inches, so the net run is 35 feet. Five bars have four laps, totaling 80 inches, so the net run is 43 feet 4 inches before cutting. Check the actual straight lengths, required ends and splice locations before cutting or ordering.

Reinforcement Checks Before Grout

SystemWhat it doesWhat to inspect
Joint reinforcementDistributes restrained movement and can supply specified horizontal steelWire size and spacing, mortar cover, splice and corrosion protection
Vertical barsCarry the tension required by the wall designBar size, dowel alignment, approved splice, unit clearance, supports and grout space
Bond beam or reinforced lintelSupplies horizontal continuity, anchorage or spanning action according to its designContinuous grout path, bar schedule, corners, bearings and anchor alignment

A long bar that bears against the inside of the unit has insufficient clearance for grout to surround it. Correct the supports and alignment before pumping. If an unapproved splice or offset is found, get an accepted detail while the work is accessible. Photographs before grout help record the positions, but the wall still needs any required inspections.

Test Your Knowledge

Why is horizontal joint reinforcement (ladder or truss wire) placed in masonry mortar bed joints?

A

To replace the vertical bars that would otherwise be required in grouted cells

B

To increase the compressive strength of the concrete masonry units themselves

C

To control shrinkage and temperature cracking and to tie the wall together

D

To fasten brick veneer to the wood framing behind it

Test Your Knowledge

Under 2015 MRC R606.3.4, what is the minimum mortar cover from the exposed face for horizontal joint reinforcement in a mortar bed joint?

A

5/8 inch

B

1/4 inch

C

3/4 inch

D

2 inches

Test Your Knowledge

Which statement correctly compares ladder and truss joint reinforcement?

A

Truss reinforcement leaves the block cores open so vertical bars can be dropped through it

B

Ladder reinforcement uses continuous diagonal cross wires for shear stiffness

C

The two types are identical in geometry and differ only in wire gauge

D

Ladder reinforcement has straight cross wires that can align over the webs, keeping the cells clear for bars and grout