19.2 Plot Plans, Building Lines & Setbacks

Key Takeaways

  • A plot plan shows lot lines and dimensions, the building envelope, required setbacks, easements, utilities, well and septic locations, floodplain, and existing and proposed grades — it drives excavation, utility staking, and drainage.

  • For ordinary zoning yards, identify the local ordinance and zoning district under the Michigan Zoning Enabling Act, 2006 PA 110. Check independent plat, easement, water and site constraints before staking.

  • On a 75-ft-wide by 140-ft-deep lot with 25-ft front, 10-ft side, and 35-ft rear setbacks, the buildable envelope is 55 ft wide by 80 ft deep (4,400 sq ft) before lot-coverage limits are applied.

  • Under MCL 125.3604, the zoning board of appeals may grant a nonuse variance for practical difficulties under the applicable standards. Use variances require unnecessary hardship and local authority under the statute.

  • A zoning setback specifies a required separation from the ordinance’s stated line. The location and terms of a utility easement determine whether and how proposed work can coexist with the holder’s rights.

Last updated: November 2026

19.2 Plot Plans, Building Lines & Setbacks

The plot plan — also called a site plan or plot/site drawing — is the one sheet that ties the survey to the permit, the excavation, the utilities, and the drainage. A contractor who starts a machine without reading it is relying on the excavator operator's memory of where the pins were. For a residential building permit, R106.2 calls for a site plan showing new and existing structures and their distances from lot lines. The building official can waive or modify the plan requirement in the circumstances specified by the code. The local zoning ordinance and other approval processes may require additional site details.

What to check on a plot plan

ElementWhat to look forWhy the contractor cares
Lot lines and dimensionsBearings, distances, lot area, frontageSets every measurement that follows
Zoning dataDistrict, required front, side, and rear yards, height, lot coverageDefines what can legally be built
Building envelopeSetback lines, proposed footprint with dimensions, offsets to each lineGoverns staking and excavation limits
EasementsUtility, drain, ingress/egress, conservationCheck each grant for access, clearance and any limits on improvements or grading
UtilitiesWater service, sewer or septic, gas, electric, overhead linesConfirm utility sources, connection points, trench routes and clearances in the field
Well and septicLocations and isolation distancesLocal health approvals and required separation from site features
Floodplain and wetlandsFIRM zone, BFE, floodway, wetland flagsScreen distinct state and local approvals for the proposed disturbance
GradesExisting and proposed contours, spot elevations, finished floor, garage floor, flow arrowsCut and fill, drainage away from the foundation
Access and flatworkDriveway grade, walks, aprons, retaining wallsEquipment access and water management
Reference dataBenchmark, datum, north arrow, scale, revision and seal when requiredLets you reproduce elevations and dimensions in the field

Read the revision block before anything else. A surprising number of site errors trace to a crew building from a superseded sheet.

Parcel boundaries and building limits

A property line identifies the parcel boundary. A setback line locates the limit derived from a yard or separation rule. Use the line and building element named by that ordinance. A recorded building line can also affect placement, with restrictions or approvals specified in the underlying plat or other records.

Draw each applicable limit separately. For example, a local side yard can be satisfied while a recorded building restriction or easement still limits the proposed structure. Confirm the measurement origin, such as the property or right-of-way line, and independently check the rules for permissible projections.

Corner lots, through lots, and other geometry

An interior lot often has one street frontage. For a corner lot or a through lot with frontage on two streets, identify the yard assigned to each frontage by the local ordinance. A second front or street-side yard can reduce the usable width or depth significantly. A waterfront or flag lot can have separate yard definitions.

Also check how the ordinance measures the yard: to the foundation wall, to the wall framing, or to the roof eave or chimney projection. Check any allowed projections, which may apply to specific elements and extend only a limited distance. On a narrow lot, the difference between measuring to the wall and measuring to the eave can decide whether the house fits.

Where Michigan setbacks actually come from

The Michigan Zoning Enabling Act, 2006 PA 110, authorizes local zoning and land-development regulation under MCL 125.3201. For an ordinary zoning yard, use the ordinance for the parcel and district. A local unit may require submission and approval of a site plan under MCL 125.3501 and enforce conditions shown on the approved plan. The building official also reviews the construction documents for code compliance under the Residential Code. The building permit and zoning review answer different questions about the proposed work.

Variances: who can relieve a setback

When a lot cannot meet the ordinance as written, relief comes from the zoning board of appeals (ZBA). Under MCL 125.3604, a nonuse variance covers dimensional requirements — setbacks, height, lot coverage — and may be granted for practical difficulties in carrying out the strict letter of the ordinance, so that the spirit of the ordinance is observed, public safety secured, and substantial justice done. The ordinance must establish procedures and standards for review.

A use variance requires unnecessary hardship. MCL 125.3604 limits authority to cities and villages, townships and counties whose ordinance expressly allowed use variances as of February 15, 2006, and townships and counties that granted a use variance before that date. Where the authority is exercised, the ordinance must require approval by two-thirds of the ZBA members. Identify the conflict and obtain any necessary variance and associated approvals before staking and releasing the affected work.

Easements and what they prohibit

An easement is a legal right held by someone else to use part of the property. Utility easements let a power, gas, water, or telecom provider install and maintain facilities; drain easements let a drainage authority maintain a county drain; an ingress/egress easement gives a neighbor a travel route. Check the recorded grant and applicable requirements for permitted crossings, access, obstructions and maintenance. A shed, deck, fence or grade change can interfere with those rights. Review the proposed work and any required permissions before laying it out.

Encroachments run the other way: a fence, driveway, air-conditioning pad, or addition that crosses onto a neighbor's land. Document the location with the surveyor and obtain an appropriate resolution before relying on the affected area. An existing fence alone is insufficient for staking the parcel line.

Worked scenario: the buildable envelope

A rectangular lot is 75 ft wide and 140 ft deep. In this example the ordinance measures 25 ft from the front lot line, 10 ft from each side, and 35 ft from the rear.

  • Buildable width = 75 − 10 − 10 = 55 ft
  • Buildable depth = 140 − 25 − 35 = 80 ft
  • Envelope area = 55 × 80 = 4,400 sq ft

Now check the constraints that can override the envelope. If the local ordinance limits aggregate footprint coverage to 30 percent of the lot, the total cap is 0.30 × (75 × 140) = 0.30 × 10,500 = 3,150 sq ft. Subtract the coverage of any other counted improvements from that cap. For a corner-lot variant, assume the ordinance substitutes a 25-ft street-facing setback for one 10-ft side yard and keeps the other three yards. The width becomes 75 − 25 − 10 = 40 ft and the envelope is 40 × 80 = 3,200 sq ft. The footprint must fit within those dimensions and satisfy the coverage cap and any applicable easement, drainage or other siting restriction. A 45-by-65-ft footprint would be under the 3,150-sq-ft coverage cap but still too wide for that envelope.

The contractor's due-diligence checklist

  1. Obtain the recorded plat or legal description and a current boundary survey.
  2. Record the applicable ordinance and confirm the review requirements, yard dimensions, height limit and coverage calculation with the local zoning administrator.
  3. Confirm platted building lines and all recorded easements on the lot.
  4. Check the effective flood map, amendments, floodway and wetland screening. Resolve boundaries and regulatory requirements before finalizing the plan.
  5. Verify utility sources and connection points with the providers. If a private well or onsite sewage system is proposed, check the approved locations and separations with the local health department.
  6. Identify the benchmark and datum, and verify existing grades at the building corners.
  7. Submit the required MISS DIG notice at least 72 hours before the work, excluding nonbusiness days, and no more than 14 calendar days ahead. Verify the legal start, positive responses and applicable expiration separately. Arrange private locates as needed.
  8. Stake the envelope, verify the setback dimensions independently, and photograph the pins and stakes before excavation.

Keep the approved revision and documented site limits where the field crew can read them. Confirm any proposed relocation with the appropriate official before changing the stakes.

Test Your Knowledge

Which source supplies the ordinary zoning yard dimensions for a parcel in a Michigan district governed by a local zoning ordinance?

A

A statewide yard-dimension table in the Michigan Residential Code

B

The county drain commissioner for all lots

C

A statewide 25-ft front yard in the Michigan Zoning Enabling Act

D

The local zoning ordinance adopted under the Michigan Zoning Enabling Act

Test Your Knowledge

A rectangular 75-ft-wide by 140-ft-deep lot has a 25-ft front setback, a 10-ft setback at each side, and a 35-ft rear setback, all measured from the lot lines. What rectangle remains after applying these four setbacks?

A

55 ft wide by 80 ft deep

B

65 ft wide by 105 ft deep

C

50 ft wide by 80 ft deep

D

55 ft wide by 105 ft deep

Test Your Knowledge

How does a granted utility easement differ from a zoning setback?

A

The easement is a zoning distance and the setback gives the utility access

B

Both are enforced by EGLE and prohibit every fence

C

The easement gives the holder specified use rights, and the setback sets a separation under the zoning ordinance

D

The easement always expires as soon as the lines are installed