21.1 Types of Construction Plans
Key Takeaways
Distinguish schematic, working, permit and fabrication drawings by their purpose. Check the issue and coordinate each shop drawing with the applicable construction documents.
The adopted 2015 R106.1 specifies two or more sets with the application, subject to its waiver provision. R106.1.1 allows electronic media where approved. Michigan Article 20 sets the applicable design professional and seal requirements.
Under R106.3.1, the building official retains one reviewed set and returns the site set. Under R106.4, work follows the approved documents and changes that depart from them go back for approval.
Michigan Rule 506 permits the truss design data sheet at application. The individual roof-truss design drawings still require approval before installation and must accompany the shipment to the jobsite.
Use the sheet index and legend for the particular set. Before bidding or ordering, resolve missing sheets, inconsistent dimension references and drawing/specification conflicts in writing.
Design, Permit and Fabrication Drawings
A plan set is a coordinated package of drawings describing one house: how it sits on the lot, how it is framed, what it looks like, and how the assemblies go together. Contractors call them the prints, the blueprints or the plans, but the documents inside that package serve different purposes, and identifying each document’s purpose helps the contractor coordinate pricing and construction.
Design drawings are produced while the project is still being shaped: schematic floor plans, a massing sketch, a kitchen layout. They answer what are we building but rarely carry enough specificity to price or permit, because beam sizes, insulation values and footing details are still undecided. Construction drawings, also called working drawings, are the dimensioned, detailed sheets a crew actually builds from: floor plans, elevations, sections, enlarged details and schedules. Combined with the written specifications and general notes, the code calls the whole package the construction documents. Permit drawings are the drawings submitted to the enforcing agency for review. They may include the same working sheets with supporting documents such as engineering information, truss data or energy compliance forms. Shop drawings are prepared by whoever fabricates a component, such as roof trusses, floor trusses, cabinets, stairs, windows or structural steel, and they translate the design into fabrication detail. Because a fabricator solves only its own piece, shop drawings must be compared back to the design drawings, never accepted on faith.
What Michigan Requires With the Application
Use the adopted 2015 Michigan Residential Code and the applicable Michigan amendments for the permit package.
- R106.1 and R106.1.1. Submit construction documents and supporting data in two or more sets under the adopted text. The official may waive documents and data that do not require preparation by a registered design professional if review is unnecessary for compliance. Electronic media can be submitted when approved. Show the work’s location, scope and applicable compliance information. Use a registered design professional when Michigan law requires one. The official may require additional documents prepared by a registered design professional when special conditions exist.
- R106.1.2 and R106.1.3. Keep required manufacturers’ installation instructions at the site for inspection. For a building using braced wall design, when the official requires it, identify braced wall lines, methods, panel locations and lengths, and the panel foundation requirements at the top and bottom.
- R106.1.4 and R802.10.1, Michigan Rule 506. The figure’s truss design data sheet may accompany the application in place of the roof-truss design drawings. The individual design drawings still go to the building official for approval before installation and must accompany the truss shipment.
- R106.2. Show the size and locations of new and existing structures and distances from lot lines. For demolition, identify the work that will be removed and the existing construction that will remain. The official can waive or modify the site-plan requirement for alterations, repairs or when otherwise warranted.
- R106.3.1, R106.4 and R106.5. When issuing the permit, the official approves the construction documents in writing or marks them REVIEWED FOR CODE COMPLIANCE. The official keeps one reviewed set and returns the site set to the applicant. Keep it at the site and accessible for inspection. Resubmit changes that depart from the approved documents as an amended set for approval. The official retains an approved set for at least 180 days after completion of the permitted work or as required by state or local law.
When the plans need a professional seal
MCL 339.2012(1)(d) exempts an unlicensed person planning, designing or directing construction of a detached one- or two-family residence with no more than 3,500 square feet of calculated floor area. The statute excludes the specified licensed adult foster care homes from this exemption. For this article, calculate area from the gross area intended as habitable space measured to the outside surfaces of exterior walls. The statutory definition lists areas outside that count, including garages, basements, bathrooms, halls and closets. A sales listing’s total square footage uses a different basis.
MCL 339.2014(e) separately excludes residential buildings at or below the same calculated area from that paragraph’s penalty for submitting unsealed documents. MCL 339.2007 and .2008 govern a licensee’s seal and signature when issuing documents for public filing and who can seal them. A licensee in responsible charge seals the work they prepared or supervised. The Article 20 exemption does not supply an engineering design or waive required permit information. Check any special conditions and component design provisions separately.
One practical consequence: notes that simply say build per code are not a substitute for specific information. County plan-review checklists written on R106 say so outright; Grand Traverse County's 2015 MRC plan requirements, for example, state that per-code notes are not an acceptable alternative to specific compliance information.
What Each Sheet Shows
The labels below illustrate one possible sheet index. Some offices use a system such as the National CAD Standard, with a discipline prefix, sheet type and sequence. For example, an index might use A-101 for an architectural plan and S-101 for a structural plan. Read the actual index and use the same sheet and revision at each referenced location.
Cover or index sheet (G-0 or A-0). Look for the project and designer identification, required design criteria, index, notes and legend. In the Michigan code check the ground snow load by jurisdiction in Table R301.2(5), the wind and climatic criteria and their sources in Table R301.2(1), and the frost protection requirements for the design. If the index lists eleven sheets and you hold ten, stop and find the missing one before pricing anything.
Site or plot plan (C-1). Lot lines and dimensions, setbacks, easements, driveway and walks, utilities, well and septic locations, finish grades, drainage patterns, a benchmark and the north arrow. This is the excavation and layout sheet.
Foundation plan (S-1). Footing sizes and depths, foundation wall material and thickness, reinforcement, anchor bolts, piers and pads, slab thickness, underfloor drainage, window wells, areaway stairs, and stepped footings on a sloped lot. Michigan’s amended R403.1.4 sets 42 inches below actual grade for exterior footings and foundation systems, subject to the official’s permitted modifications and applicable R403.1.4.1 requirements. Use the foundation plan and details to identify the approved depth and method.
Floor plans (A-2, A-3). Room names and dimensions, wall locations and thicknesses, door and window sizes with swing direction, stair layout, cabinets, plumbing fixtures, beam and header callouts, and joist direction and spacing. Locate braced wall lines and panel information where R106.1.3 applies, and check the floor plan’s beam and header references against the structural sheets.
Framing plans (S-2). Joist size, species, grade and spacing; beams, hangers, rim board, blocking, subfloor sheathing and nailing. Framing plans are where a 16-inch versus 19.2-inch on-center layout changes your material takeoff.
Roof framing plan and truss erection documents (for example, S-3 and a supplier package). The building framing plan coordinates overall framing, bearings, girders, beams and connections. The supplier’s placement diagram identifies where each numbered truss goes and points to its individual truss design drawing. The design drawing shows the component’s geometry, loads and reactions, bearings, member and connection information, and required permanent member restraint locations. Metal-plate-connected wood trusses use the referenced ANSI/TPI 1 standard. Check required temporary erection restraint and bracing separately from permanent member restraint and building stability. Coordinate all documents before installation.
Elevations (A-4). Front, rear and two side views: roof pitches, eave and ridge heights, window head heights, siding, trim, foundation exposure above grade and the finished grade line. Elevations catch problems that plans hide, such as a window head that lands under a porch beam.
Sections and wall sections (A-5, A-6). A building section shows the assemblies and elevations intersected by its cut. A full-height section can show the footing, floor-to-floor heights, insulation and roof. Wall sections and details enlarge a window head, sill, deck ledger, footing or chimney.
Schedules (A-7). Window and door schedules with marks, sizes, type, glazing, hardware and rough openings; finish schedules; truss schedules; sometimes a plumbing fixture schedule.
Structural and general notes (S-0). Lumber species and grade, fastener and connector schedules, nailing, hold-downs, sheathing, and code references the designer is relying on.
| Sheet | Typical ID | What the builder uses it for |
|---|---|---|
| Cover / index | G-0, A-0 | Code edition, sheet index, design criteria, symbol legend |
| Site / plot plan | C-1 | Setbacks, grades, utilities, drainage, excavation limits |
| Foundation plan | S-1 | Footings, frost depth, wall type, anchor bolts, slab, drain tile |
| Floor plans | A-2, A-3 | Wall layout, room sizes, doors and windows, stairs, fixtures, beams |
| Framing plans | S-2 | Joist and beam size, spacing, hangers, blocking, sheathing |
| Roof framing / erection documents | S-3 and supplier package | Coordinate building framing with the placement and individual design drawings |
| Elevations | A-4 | Roof pitches, heights, siding, window heads, finish grade |
| Sections | A-5 | Floor-to-floor heights, assemblies, insulation, foundation |
| Wall sections / details | A-6 | Flashing, water-resistive barrier, deck ledger, window head and sill |
| Schedules | A-7 | Window and door sizes, rough openings, finishes, hardware |
| Structural notes | S-0 | Lumber species and grade, connectors, nailing, hold-downs |
What the Contractor Must Verify Before Bidding
Plan review under R106.3 checks code compliance. Before pricing, independently verify that the issued documents cover the work, that dimensions and references reconcile, and that any design still required is assigned to the appropriate party.
1. Completeness. Match the sheet index against the pages you actually received, check revision dates, and confirm you have acknowledged every addendum. A set missing the foundation sheet is not a set you can price.
2. Dimension closure. Add the room dimensions and wall thicknesses along each direction and compare them with the overall dimension. When a chain appears inconsistent, first verify the dimension endpoints and which segments already include wall thickness. Ask for written clarification if the mismatch remains.
3. Cross-reference resolution. Every section mark, elevation marker, detail bubble and keynote must land on a sheet or note you possess. A detail referencing sheet A-6 that you were never sent is a gap, not a rounding error.
4. Drawing versus specification conflicts. If one sheet shows a 6-inch framing depth and the specification calls for nominal 2x4 studs at that location, verify the measurement references and request a coordinated answer. Read the front-end documents for a precedence clause. If none exists, ask in writing before the bid deadline.
5. Deferred design. Identify missing design or submittals, such as a truss package or a designed beam. Check who is responsible under the contract and which information and approvals are required by each phase. Separately confirm who obtains utility permits or provides energy documentation. Use an agreed allowance or exclusion if the bid rules allow it.
6. Print size and scale. A reduced print can invalidate the original numeric scale. For a proportional copy, a graphic scale for the view can support an approximate measurement. Use stated dimensions for layout and check for distortion before relying on scaled quantities.
Scenario: The Missing Foundation Sheet
You are bidding a 1,900-square-foot two-story. The index lists eleven sheets; the file contains ten, and S-1 is absent. The ordinary frost depth alone supplies neither footing width nor reinforcement, step locations or elevations. Request the missing foundation drawing and structural references in writing. Hold the affected price until the information arrives, or identify the unresolved work in a qualified bid if the bidding rules allow it.
The Same Discipline Applies at Framing Time
The crew on site reads the same sheets you bid, so the conflicts you resolved by email never reach them unless you transfer the answers onto a marked-up set. Keep the reviewed set at the site and open for inspection under R106.3.1. Record project clarifications and approved revisions with their dates on controlled copies. Resubmit changes that deviate from the approved documents under R106.4 and confirm approval before proceeding with the changed work.
After a Michigan building official issues a permit for a new house, what happens to the reviewed construction documents under 2015 MRC R106.3.1?
All sets are returned to the applicant
The enforcing agency retains every set for the life of the structure
The official retains one set and returns the other to the applicant for keeping at the work site and making available for inspection
The state receives both sets and the local agency keeps the permit card only
The permit applicant proposes using Michigan’s truss design data sheet for roof trusses at application. What is still required under 2015 MRC R106.1.4 and R802.10.1 as amended?
Provide the truss design drawings for building official approval before installation and include the drawings with the truss shipment
The data sheet is barred and the drawings always have to accompany the initial permit application
The data sheet permanently replaces the individual drawings once the permit issues
The data sheet is permitted only for roof spans under 24 feet
Which roof-framing document typically comes from the truss manufacturer to identify where each numbered truss is installed?
The building exterior elevation
The building foundation plan
The architectural section through the entry
The truss placement diagram keyed to the individual truss design drawings