5.3 Construction Contract Types
Key Takeaways
For a fixed scope and price without a price adjustment, the contractor bears ordinary estimating and productivity variance and keeps ordinary savings.
Cost-plus reimburses allowable costs plus a fee. A fixed fee does not increase just because allowable costs rise.
A GMP caps cost plus fee at the applicable adjusted ceiling. Compute shared savings after fee and only if the parties agreed to share.
Time and materials uses agreed labor rates and eligible material charges. An authorized not-to-exceed amount limits payment unless changed under the contract.
Unit pricing pays the accepted measured quantity at the applicable unit rate. Check any quantity-variation clause before using that rate for all units.
Quick Answer: Read the payment basis and adjustment clauses together. A fixed price places ordinary cost variance on the contractor. An uncapped cost-plus agreement reimburses allowed cost and pays the agreed fee. A GMP or T&M ceiling limits payment, and a unit-price agreement pays at the stated rate for measured work within its terms.
The risk-allocation table
| Contract type | Price basis | Owner cost certainty | Contractor's main risk | Cost transparency | Fits when |
|---|---|---|---|---|---|
| Lump sum | Stipulated sum for defined scope | High before authorized changes | Direct costs and productivity may exceed estimate | Billing normally relies on agreed price and progress | Scope is sufficiently defined to price |
| Cost-plus percentage | Allowed cost plus a stated fee percentage | Low without a ceiling | Nonreimbursable cost; fee dollars depend on the allowed base | Documented, auditable charges | A private agreement permits it and scope is uncertain |
| Cost-plus fixed fee | Allowed cost plus agreed dollar fee | Cost varies; fee fixed for stated scope | Nonreimbursable cost and work effort within the agreed scope | Documented, auditable charges | Owner wants reimbursement without a cost-based percentage fee |
| Time and materials | Agreed hourly charges and eligible material charges | Depends on scope and any ceiling | Excluded costs and work beyond the authorized ceiling | Verified time records and invoices | Repair extent is uncertain |
| Guaranteed maximum price | Allowed cost plus fee subject to adjusted ceiling | High within the cap and scope | Costs beyond cap or outside reimbursement terms | Documented, auditable charges | The parties can define enough scope to agree on a ceiling |
| Unit price | Applicable unit rate × accepted measured quantity | Depends on quantity | Unit-cost variance and any rate adjustments | Verified quantities | Work units are defined but quantities are uncertain |
Lump-sum and fixed-price contracts
Under lump sum, the contractor agrees to deliver a defined scope for a stipulated price. The contractor ordinarily bears quantity, productivity and market-cost errors for that scope. Assume no adjustment and a $230,000 contract. At $185,000 of job cost, the price exceeds job cost by $45,000. At $245,000, the price falls short of job cost by $15,000.
Identify the scope, approved allowances and their treatment, exclusions, and price-adjustment terms. A scope change or an applicable escalation clause can change the amount paid. A contractor normally keeps an ordinary cost saving on the unchanged scope under a pure stipulated sum. An allowance adjustment or incentive clause can separately allocate savings.
Cost-plus contracts
A cost-plus agreement specifies which labor, equipment, materials, subcontracts and job expenses are reimbursable. The owner pays allowed costs plus the stipulated fee and generally bears ordinary eligible cost variance in an uncapped contract. The contractor remains responsible for excluded charges. Verify invoices against the agreement, including how company overhead and rebates are handled.
A percentage fee rises with the allowed base. A fixed fee removes that mathematical incentive and generally remains the same for the agreed scope. Contract changes can adjust the fee. Use a clear cost definition, approval and audit rights to control reimbursement. The percentage-of-cost pricing system is prohibited in federal contracting under FAR 16.102(c); the percentage examples here assume a private agreement permitting that basis.
Guaranteed maximum price
A GMP caps the allowable Cost of the Work plus the fee under the stated terms. The contractor bears costs it cannot recover under that ceiling. Changes, delays and differing conditions affect the ceiling only when the contract permits an adjustment and the parties follow its procedure. A contingency within the GMP may reserve room for identified risks. Define eligible uses and how an unused balance is handled.
A GMP differs from a stipulated sum because payment follows documented allowable cost plus fee and the applicable ceiling. The difference between the cap and actual cost plus fee initially measures potential savings. The contractor shares in those savings only under an agreed savings provision. Check its treatment of authorized adjustments, contingencies and allowances.
Time and materials
T&M invoices approved worker-hours at agreed billing rates and eligible material charges. The contract may include an agreed handling percentage or ceiling. The owner generally bears eligible cost increases up to the ceiling. Where charges would exceed the cap, seek written authorization before incurring more work. Use time records and material invoices, and check which signatures are required. A billable rate can include overhead and profit, so the amount excluded by a cap cannot by itself establish actual loss.
Unit-price contracts
A unit-price contract pays by measured quantities of accepted work, such as cubic yards of excavation. The owner typically bears the resulting quantity effects, and the contractor bears its cost to produce each unit at the agreed rate. Define measurement, inclusions and any adjustment when actual quantities vary materially. Compare the spread of unit prices and test changed quantities during evaluation. An overstated item can increase the total substantially even when the original bid sum looks reasonable.
Worked comparison of pricing methods
Compare alternative agreements on an addition with a $200,000 estimated job cost. Each row assumes the stated terms, eligible actual work and no authorized contract adjustment. The last two rows are separate repair and excavation packages to illustrate T&M and measured units.
| Contract | Term | Actual work or cost | Owner pays | Contractor result before unallocated company costs |
|---|---|---|---|---|
| Lump sum | $230,000 stipulated | $215,000 job cost | $230,000 | $15,000 above job cost |
| Lump sum | $230,000 stipulated | $185,000 job cost | $230,000 | $45,000 above job cost |
| Cost-plus percentage | 10% of allowable cost | $215,000 allowed | $236,500 | $21,500 fee before any excluded costs |
| Cost-plus fixed fee | $20,000 fee | $215,000 allowed | $235,000 | $20,000 fee before any excluded costs |
| GMP with sharing | $230,000 cap, $15,000 base fee, 50% contractor savings share | $210,000 allowed, so $225,000 with fee | $227,500 | $15,000 fee plus $2,500 share of the $5,000 savings |
| GMP overrun | $230,000 cap including fee | $245,000 job cost before any fee | $230,000 | Receipts fall $15,000 short of job cost |
| T&M with NTE | $42,000 ceiling | 360 worker-hours at $108 plus $5,400 eligible materials, or $44,280 before cap | $42,000 | $2,280 of calculated charges above cap; actual cost not given |
| Unit price | $55 per accepted cubic yard; 100 yards estimated | 120 cubic yards at an actual job cost of $45 each | $6,600 | $1,200 above $5,400 job cost |
For the GMP example, subtract the $225,000 cost-plus-fee amount from the $230,000 limit, then apply the 50% sharing term to the $5,000 difference. For the unit-price package, the 20 additional yards raise the payment $1,100 at the unchanged rate. Work performed, cost incurred, fee earned, amount billed, cash collected and actual profit each answer a different question.
Change orders under each type
For covered residential work obtain a signed written change and furnish a copy under R 338.1533. Document the scope, effect on time, and applicable price calculation. A lump-sum change alters the stipulated price as agreed. A cost-plus change may involve added reimbursable cost and a negotiated fee adjustment. A GMP or T&M cap changes only through an authorized adjustment. With unit pricing, distinguish an ordinary measured quantity variance from a change that alters the applicable rate or work.
Exam traps
- Check the estimate versus price basis before assigning an overrun to either party.
- Distinguish reimbursable cost from the fee, and the fee from the contractor’s net profit.
- Determine the adjusted cap before measuring either a potential overrun or savings. Look for a negotiated savings split.
- Under unit pricing, verify the accepted quantities and the rate applicable to them.
- Treat a clear allowance, exclusion or change as part of the pricing terms when comparing bids.
Under a lump-sum building contract with defined scope, unchanged price and no adjustment for ordinary cost variance, who bears that variance?
The owner bears all hours beyond the contractor’s estimate.
The owner pays for all quantities above the contractor’s estimate.
The designer automatically covers material price increases.
The contractor bears ordinary quantity and productivity errors within the agreed scope.
Compare two uncapped cost-plus agreements with the same reimbursable-cost rules. What is the effect of a fixed fee rather than a percentage fee on the unchanged scope?
The fixed fee does not automatically increase when eligible costs rise.
The fixed fee guarantees a maximum total price.
The owner no longer needs supporting invoices.
The contractor must absorb every increase in eligible material costs.
An owner has complete plans and specifications and wants an agreed price for the defined, unchanged scope before work starts. Which basis directly gives that result?
Cost-plus percentage
Time and materials with a not-to-exceed cap
Lump-sum fixed price
Unit price paid for measured quantities