5.3 Construction Contract Types

Key Takeaways

  • For a fixed scope and price without a price adjustment, the contractor bears ordinary estimating and productivity variance and keeps ordinary savings.

  • Cost-plus reimburses allowable costs plus a fee. A fixed fee does not increase just because allowable costs rise.

  • A GMP caps cost plus fee at the applicable adjusted ceiling. Compute shared savings after fee and only if the parties agreed to share.

  • Time and materials uses agreed labor rates and eligible material charges. An authorized not-to-exceed amount limits payment unless changed under the contract.

  • Unit pricing pays the accepted measured quantity at the applicable unit rate. Check any quantity-variation clause before using that rate for all units.

Last updated: November 2026

Quick Answer: Read the payment basis and adjustment clauses together. A fixed price places ordinary cost variance on the contractor. An uncapped cost-plus agreement reimburses allowed cost and pays the agreed fee. A GMP or T&M ceiling limits payment, and a unit-price agreement pays at the stated rate for measured work within its terms.

The risk-allocation table

Contract typePrice basisOwner cost certaintyContractor's main riskCost transparencyFits when
Lump sumStipulated sum for defined scopeHigh before authorized changesDirect costs and productivity may exceed estimateBilling normally relies on agreed price and progressScope is sufficiently defined to price
Cost-plus percentageAllowed cost plus a stated fee percentageLow without a ceilingNonreimbursable cost; fee dollars depend on the allowed baseDocumented, auditable chargesA private agreement permits it and scope is uncertain
Cost-plus fixed feeAllowed cost plus agreed dollar feeCost varies; fee fixed for stated scopeNonreimbursable cost and work effort within the agreed scopeDocumented, auditable chargesOwner wants reimbursement without a cost-based percentage fee
Time and materialsAgreed hourly charges and eligible material chargesDepends on scope and any ceilingExcluded costs and work beyond the authorized ceilingVerified time records and invoicesRepair extent is uncertain
Guaranteed maximum priceAllowed cost plus fee subject to adjusted ceilingHigh within the cap and scopeCosts beyond cap or outside reimbursement termsDocumented, auditable chargesThe parties can define enough scope to agree on a ceiling
Unit priceApplicable unit rate × accepted measured quantityDepends on quantityUnit-cost variance and any rate adjustmentsVerified quantitiesWork units are defined but quantities are uncertain

Lump-sum and fixed-price contracts

Under lump sum, the contractor agrees to deliver a defined scope for a stipulated price. The contractor ordinarily bears quantity, productivity and market-cost errors for that scope. Assume no adjustment and a $230,000 contract. At $185,000 of job cost, the price exceeds job cost by $45,000. At $245,000, the price falls short of job cost by $15,000.

Identify the scope, approved allowances and their treatment, exclusions, and price-adjustment terms. A scope change or an applicable escalation clause can change the amount paid. A contractor normally keeps an ordinary cost saving on the unchanged scope under a pure stipulated sum. An allowance adjustment or incentive clause can separately allocate savings.

Cost-plus contracts

A cost-plus agreement specifies which labor, equipment, materials, subcontracts and job expenses are reimbursable. The owner pays allowed costs plus the stipulated fee and generally bears ordinary eligible cost variance in an uncapped contract. The contractor remains responsible for excluded charges. Verify invoices against the agreement, including how company overhead and rebates are handled.

A percentage fee rises with the allowed base. A fixed fee removes that mathematical incentive and generally remains the same for the agreed scope. Contract changes can adjust the fee. Use a clear cost definition, approval and audit rights to control reimbursement. The percentage-of-cost pricing system is prohibited in federal contracting under FAR 16.102(c); the percentage examples here assume a private agreement permitting that basis.

Guaranteed maximum price

A GMP caps the allowable Cost of the Work plus the fee under the stated terms. The contractor bears costs it cannot recover under that ceiling. Changes, delays and differing conditions affect the ceiling only when the contract permits an adjustment and the parties follow its procedure. A contingency within the GMP may reserve room for identified risks. Define eligible uses and how an unused balance is handled.

A GMP differs from a stipulated sum because payment follows documented allowable cost plus fee and the applicable ceiling. The difference between the cap and actual cost plus fee initially measures potential savings. The contractor shares in those savings only under an agreed savings provision. Check its treatment of authorized adjustments, contingencies and allowances.

Time and materials

T&M invoices approved worker-hours at agreed billing rates and eligible material charges. The contract may include an agreed handling percentage or ceiling. The owner generally bears eligible cost increases up to the ceiling. Where charges would exceed the cap, seek written authorization before incurring more work. Use time records and material invoices, and check which signatures are required. A billable rate can include overhead and profit, so the amount excluded by a cap cannot by itself establish actual loss.

Unit-price contracts

A unit-price contract pays by measured quantities of accepted work, such as cubic yards of excavation. The owner typically bears the resulting quantity effects, and the contractor bears its cost to produce each unit at the agreed rate. Define measurement, inclusions and any adjustment when actual quantities vary materially. Compare the spread of unit prices and test changed quantities during evaluation. An overstated item can increase the total substantially even when the original bid sum looks reasonable.

Worked comparison of pricing methods

Compare alternative agreements on an addition with a $200,000 estimated job cost. Each row assumes the stated terms, eligible actual work and no authorized contract adjustment. The last two rows are separate repair and excavation packages to illustrate T&M and measured units.

ContractTermActual work or costOwner paysContractor result before unallocated company costs
Lump sum$230,000 stipulated$215,000 job cost$230,000$15,000 above job cost
Lump sum$230,000 stipulated$185,000 job cost$230,000$45,000 above job cost
Cost-plus percentage10% of allowable cost$215,000 allowed$236,500$21,500 fee before any excluded costs
Cost-plus fixed fee$20,000 fee$215,000 allowed$235,000$20,000 fee before any excluded costs
GMP with sharing$230,000 cap, $15,000 base fee, 50% contractor savings share$210,000 allowed, so $225,000 with fee$227,500$15,000 fee plus $2,500 share of the $5,000 savings
GMP overrun$230,000 cap including fee$245,000 job cost before any fee$230,000Receipts fall $15,000 short of job cost
T&M with NTE$42,000 ceiling360 worker-hours at $108 plus $5,400 eligible materials, or $44,280 before cap$42,000$2,280 of calculated charges above cap; actual cost not given
Unit price$55 per accepted cubic yard; 100 yards estimated120 cubic yards at an actual job cost of $45 each$6,600$1,200 above $5,400 job cost

For the GMP example, subtract the $225,000 cost-plus-fee amount from the $230,000 limit, then apply the 50% sharing term to the $5,000 difference. For the unit-price package, the 20 additional yards raise the payment $1,100 at the unchanged rate. Work performed, cost incurred, fee earned, amount billed, cash collected and actual profit each answer a different question.

Change orders under each type

For covered residential work obtain a signed written change and furnish a copy under R 338.1533. Document the scope, effect on time, and applicable price calculation. A lump-sum change alters the stipulated price as agreed. A cost-plus change may involve added reimbursable cost and a negotiated fee adjustment. A GMP or T&M cap changes only through an authorized adjustment. With unit pricing, distinguish an ordinary measured quantity variance from a change that alters the applicable rate or work.

Exam traps

  • Check the estimate versus price basis before assigning an overrun to either party.
  • Distinguish reimbursable cost from the fee, and the fee from the contractor’s net profit.
  • Determine the adjusted cap before measuring either a potential overrun or savings. Look for a negotiated savings split.
  • Under unit pricing, verify the accepted quantities and the rate applicable to them.
  • Treat a clear allowance, exclusion or change as part of the pricing terms when comparing bids.
Test Your Knowledge

Under a lump-sum building contract with defined scope, unchanged price and no adjustment for ordinary cost variance, who bears that variance?

A

The owner bears all hours beyond the contractor’s estimate.

B

The owner pays for all quantities above the contractor’s estimate.

C

The designer automatically covers material price increases.

D

The contractor bears ordinary quantity and productivity errors within the agreed scope.

Test Your Knowledge

Compare two uncapped cost-plus agreements with the same reimbursable-cost rules. What is the effect of a fixed fee rather than a percentage fee on the unchanged scope?

A

The fixed fee does not automatically increase when eligible costs rise.

B

The fixed fee guarantees a maximum total price.

C

The owner no longer needs supporting invoices.

D

The contractor must absorb every increase in eligible material costs.

Test Your Knowledge

An owner has complete plans and specifications and wants an agreed price for the defined, unchanged scope before work starts. Which basis directly gives that result?

A

Cost-plus percentage

B

Time and materials with a not-to-exceed cap

C

Lump-sum fixed price

D

Unit price paid for measured quantities