5.2 Contract Requirements & Definition

Key Takeaways

  • Identify objective assent on essential terms, consideration, capacity, authority and lawful purpose. A response conditional on a changed term is ordinarily a counteroffer.

  • MCL 566.132(1)(a) uses the terms at formation and whether performance is possible within one year. A separate sale of goods may follow MCL 440.2201.

  • Michigan Rule 338.1533 requires signed written agreements and changes and copies for covered builder-customer dealings. MCL 570.1114 separately sets written-contract, written-change and licensing-disclosure conditions for a residential contractor lien.

  • For a covered home solicitation sale with compliant documents and no applicable emergency exception, the buyer can cancel through midnight of the third Michigan business day after signing.

  • When Article 24 requires a license, the contractor must allege and prove licensure during performance to maintain a Michigan court action for compensation.

Last updated: November 2026

Quick Answer: Analyze formation, required writing, and the remedy separately. Michigan’s one-year statute of frauds, builder-customer writing requirements and residential construction lien statute have distinct triggers. A home solicitation sale can add its own notice and cancellation procedure.

What a construction contract is

A contract is a promise, or set of promises, that the law will enforce. A residential construction contract exchanges the owner's promise to pay for the contractor's promise to furnish labor and materials and produce a described result. It is also the project's risk-allocation document: it fixes scope, price, schedule, payment, quality standards, and the consequences of delay, changes, and defects.

Parties can ordinarily express agreement in words or manifest it by conduct. A residential construction agreement carries a duty of workmanlike performance. The builder-vendor warranty of habitability discussed in the warranties section attaches to a new-home sale by a builder-vendor, with a different analysis if the customer already owns the land. A fully integrated writing ordinarily controls over prior or contemporaneous statements offered to vary its terms, subject to recognized exceptions.

The essential elements

ElementWhat it requiresResidential example
OfferA definite, communicated proposal showing objective intent to be bound on acceptanceBuilder offers to build a 24-foot by 30-foot garage for $64,500 under attached plans
AcceptanceAssent to the terms in the required manner while the offer remains openThe builder and customer sign the garage agreement without changing the offer’s terms
ConsiderationA bargained-for exchangeThe owner promises payment in exchange for the builder’s promised work
Capacity and authorityAbility to contract and, for a representative, authority to bind the represented partyA company officer authorized for the transaction signs on its behalf
Lawful purposeThe contract is for lawful performanceThe agreement calls for permitted work by the properly licensed parties
Definite termsEssential obligations are sufficiently ascertainableThe incorporated plans define the work and the agreement sets the price and payment stages

A reply accepting only at a lower price ordinarily rejects the original offer and proposes a counteroffer. A request to discuss a lower price can instead be an inquiry. Determine assent from what was communicated and done. Comply with the applicable writing and signature requirements for the revised agreement.

For work requiring an Article 24 license, MCL 339.2412 requires the contractor to allege and prove licensure during performance to maintain a court action for compensation. Stokes v Millen Roofing Co applied the compensation and lien bars to unlicensed covered work. These bars concern the contractor’s remedies. They do not establish that an innocent owner necessarily loses all rights. Check the licensing and lien provisions separately.

Oral and written contracts

Oral assent can establish some agreements, but construction has additional writing rules. For covered builder-customer dealings Rule 338.1533 requires written agreements and changes signed by both parties, with copies to the customer. A site conversation can record a request. Obtain the signatures needed to authorize its scope, price and time effects. A later common-law modification of an agreement and a statutory writing condition are separate questions.

MCL 566.132(1) requires a signed writing or memorandum from the party to be charged for the categories it lists. Two construction examples are a bargain whose terms prevent performance within one year from making it and a special promise to answer for someone else’s debt, default, or misdoings. Subsection (2) separately bars actions against covered financial institutions to enforce certain financing promises or commitments without the institution’s authorized signed writing.

MCL 566.132 has no general dollar trigger for construction services. Michigan’s UCC, MCL 440.2201, generally requires a sufficient signed writing for a sale of goods priced at $1,000 or more, subject to the statutory exceptions. A pure materials purchase can fall under that rule. For a mixed sale and installation, check whether goods or services predominate before applying Article 2.

The one-year rule

Measure a year from the making of the agreement. If a contract expressly requires continuous service for 14 months after signing, it cannot be performed within a year. A projection that a build will probably take 14 months is different if the agreement permits earlier full performance. The statute looks to possible performance under the agreement, rather than how long the work eventually takes.

Rule 338.1533 requires clear written terms, specifications and, for construction, plans and specifications that identify cost, the type and amount of work, and the type and quality of materials. If a purchase or sales agreement is for a new structure already substantially complete or substantially in conformance with a model, plans and specs may be omitted only if the structure is specifically identified or related to the model and the parties specifically agree to and record variations in writing. Separate provisions govern delivery of the entire agreement, lien rights and covered cancellation notices.

Residential lien contracts: MCL 570.1114

Section 114 of the Construction Lien Act requires a written contract between the contractor and the owner or lessee under which the contractor provided the improvement to a residential structure. Any amendments or additions must also be in writing to satisfy this contractor-lien requirement.

The contract must contain a statement, in type no smaller than the body of the contract, stating both of the following:

  1. A residential builder or residential maintenance and alteration contractor is required to be licensed under Article 24 of the Occupational Code, MCL 339.2401 to 339.2412; an electrician under Article 7 of the Skilled Trades Regulation Act; a plumbing contractor under Article 11; and a mechanical contractor under Article 8.
  2. If the contractor is required to be licensed to provide the contracted improvement, that the contractor is licensed and the contractor's license number.

An otherwise enforceable agreement and an enforceable construction lien are separate questions. Provide the complete licensing statement in the contract and include the contractor’s licensed status and number if a license is required. Keep changes in signed writings under the administrative rule and in the lien file under §114. The statute does not establish a notary, fixed retainage percentage or owner payment-bond requirement.

Home solicitation sales: 1971 PA 227

Under the Michigan Home Solicitation Sales Act, 1971 PA 227, a covered home solicitation sale is for more than $25 in goods or services. The seller or its representative makes a personal, telephone or statutorily defined written solicitation received at the buyer’s residence, and the buyer gives the agreement or offer to purchase there. The statutory written-solicitation definition addresses notices asking the buyer to call, with exceptions for certain notices about previous orders or stating the price and accurately describing the item or service.

Check the exclusions in MCL 445.111, including a sale at a qualifying fixed business location or one following prior negotiations there, a sale pursuant to a printed general-circulation advertisement or preexisting revolving charge account, specified insurance and broker sales, and qualifying agricultural or horticultural equipment demonstrations. The sale’s circumstances matter. Signing in the living room alone does not establish that the seller solicited the sale at the residence or that an exclusion is absent.

For a compliant covered sale, the deadline is midnight of the third business day after the buyer signs. Michigan counts Monday through Friday excluding the ten holidays listed in MCL 445.111(c). With no holiday, count Wednesday, Thursday and Friday after a Tuesday signing. Cancellation can be sent to the stated address by the statutory form, another sufficient written notice or telegram. Mailing is effective on properly addressed, postage-paid deposit. The emergency exception in MCL 445.112(5) requires a buyer request for immediate service due to an emergency, a substantial beginning of performance in good faith before notice, and the buyer’s separate, dated, signed handwritten description and express waiver. If goods are involved, they must also be unable to be returned in substantially as good condition.

Use the actual signing date. Under MCL 445.113, put the prescribed cancellation and third-party payment pickup language near the buyer’s signature. Attach the notice of cancellation in duplicate or print it on the reverse of the buyer’s copy. The statutory notices must be in at least 10-point bold type and two points larger than the agreement text. Use the language of any oral sales presentation for the agreement and notice, and fill in the actual signing and deadline dates. An entry error does not reduce the buyer’s rights. Until the seller complies with §113, the buyer can give cancellation notice by any means. MCL 445.114 directs tender of payments and evidence of debt within 10 days after cancellation or revocation, and addresses return of a trade-in. The prescribed §113 form separately describes return within ten business days after receipt. Keep the form as prescribed and comply with the operative tender rule.

A home improvement installment contract within the separate Michigan Home Improvement Finance Act has its own prescribed cancellation notice, generally through 5 p.m. the business day after signing under MCL 445.1202. An ordinary progress-draw schedule is not by itself seller installment financing. Federal cooling-off rules can also apply to some off-premises sales and have their own definition of a business day. Identify the governing law before counting days. The Michigan Consumer Protection Act’s deceptive-practice rules are separate from the state home solicitation deadline.

Contract file checklist

ItemSourceWhat to check
Signed written agreement and changesR 338.1533(1)Signatures of both parties and copies furnished to the customer
Scope, specifications and construction plansR 338.1533(2)–(3)Cost, type and amount of work, material type and quality, and any applicable model or completion exception
Trade licensing statement and numberMCL 570.1114Complete licensing statement in type no smaller than body text. Include the contractor’s licensed status and number when a license is required.
Entire agreement and chargesMCL 339.2411(2)(h)For covered transactions such as residential alterations and garage construction, deliver the full agreement including finance and other charges
Home solicitation and installment financeMCL 445.113 and MCL 445.1202Applicable form, notice, signature and cancellation requirements depend on the sale
Dates, payment stages, changes and closeoutLARA homeowner guidance and applicable contractDefine start and completion milestones, payment schedule, retainage if any, written changes and completion duties. Check whether a separate statute applies to a particular transaction.
Test Your Knowledge

Which agreement falls within the one-year provision of MCL 566.132(1)(a)? Consider only that provision.

A

A service agreement requiring replacement of an entry door within 30 days.

B

A roofing service agreement that can be performed in six months.

C

An agreement made today requiring continuous construction services for the next 14 months.

D

A time-and-materials repair agreement that sets no minimum term and can be completed in three months.

Test Your Knowledge

A Michigan residential remodeling contractor is required to be licensed. Which requirement applies to the contractor’s lien under MCL 570.1114?

A

The contractor must itself record a notice of commencement before starting work under this section.

B

The written contract and any written changes must meet §114, including the prescribed trade-licensing disclosure and the contractor’s licensed status and license number in the contract.

C

The agreement must be notarized and specify a 10% retainage.

D

The owner must obtain a payment bond equal to the contract price.

Test Your Knowledge

A salesperson solicits a $9,000 siding sale at the buyer’s residence. On Tuesday the buyer signs there and receives compliant notices. No statutory exception or holiday applies. Under Michigan’s Home Solicitation Sales Act, when is the deadline?

A

Midnight on Wednesday.

B

Exactly 72 hours from signing, regardless of time of day.

C

Midnight on Thursday.

D

Midnight at the end of Friday.