7.2 Breach of Contract & Remedies

Key Takeaways

  • Materiality turns on whether the other party lost an essential benefit. A material breach can excuse further performance. Check any notice, cure, and termination conditions. Minor defects can support a setoff after substantial performance.

  • Prove direct losses with reasonable certainty. For consequential losses, check what was reasonably contemplated at formation, causation, any contractual limit, and whether the loss could reasonably have been avoided.

  • A valid liquidated-damages clause reasonably estimates loss difficult to measure when the agreement is made. Apply it to the covered breach and account for excused time.

  • When Article 24 licensure is required, MCL 339.2412 bars a compensation action and imposition of a lien without licensure during performance. Stokes rejects evasion of that bar through equity.

  • Private dispute procedures and LARA workmanship proceedings follow different rules. An arbitration award can be confirmed and challenged only on the applicable limited review grounds.

Last updated: November 2026

A breach is failure to perform a contractual duty without a legal excuse. A substantial first breach can excuse the other party’s further performance. Consider whether the owner got the essential work promised, the practical ability to cure, and the harm to the bargain. Compare an abandoned job at rough-in with a documented, repairable punch-list item on a substantially performed house. The first can prevent the project from being delivered. The second can support a measured offset. See Able Demolition v Pontiac, 275 Mich App 577 (2007), and P & M Construction v Hammond Ventures, 3 Mich App 306 (1966).

Breach types the exam tests

Breach typeExampleEffect to evaluate
Material breachBuilder abandons an unfinished homeWhether further performance is excused and any notice and cure required to end the contract
Minor breach after substantial performanceLocalized item can be corrected at reasonable cost and the owner received the essential workPayment otherwise due, subject to an established repair offset
Anticipatory repudiationBefore payment is due, owner unequivocally refuses future performance without a contractual excuseA present breach claim or the option to await performance, subject to mitigation
DelayContractor misses a specified completion dateWhether delay is excused, whether timely performance was essential and what losses or stipulated amount the contract allows
Defective performanceWindow leaks because the installed flashing departs from the specificationsObligation to correct under the agreement and supported cost to cure or other applicable measure

Anticipatory repudiation requires words or conduct that clearly show a refusal to perform before the duty is due. The innocent party may treat a clear repudiation as a breach immediately or await the due date (Stoddard v Manufacturers National Bank, 234 Mich App 140 (1999)). A request to discuss the schedule is ordinarily too equivocal. Check any financing contingency, cure provision, or agreed exit before treating a refusal as wrongful, and take reasonable steps to limit accumulating loss.

When the agreement omits a time for performance, Michigan implies a reasonable time measured in context. A stated due date still matters even without a time-of-the-essence clause. The language or surrounding circumstances may make timely performance essential. Check which events excuse delay, how extensions are obtained and whether any extension changes the date used to assess damages.

Default, cure, suspension, and termination

Use the signed agreement to identify a default, who must receive notice, the permitted delivery method, and whether and when a default can be cured. For example, if the agreement gives ten calendar days after receipt to remedy an unpaid invoice, identify the due obligation and prove when notice was received before using the remedy. Cure periods and extensions vary with the contract.

Termination for cause depends on an applicable ground and compliance with the remedy clause and law. Termination for convenience depends on the party having that right, usually by agreement. The clause can set payment for work performed, termination costs and any fee. AIA A201–2017 Article 14 is an example of distinct procedures, not a default rule for Michigan residential contracts.

A suspension can protect both parties while a remediable default is addressed. Check the ground for stopping work, when the right arises and how to give notice. Record what work must be protected, how to resume, and any schedule or remobilization costs the agreement permits. Address an immediate safety hazard under applicable safety obligations. An unsafe condition, a delayed selection or a lender freeze does not by itself establish a contractual entitlement to money or more time.

Under MCL 339.2412(2), a complainant’s failure to use a contractually provided alternative dispute resolution procedure can be an affirmative defense to a Michigan court action against a licensee under Article 24. Check the clause, the dispute and the statutory scope. The LARA workmanship procedure in MCL 339.2411(4) has separate rules.

Damages: what a court will actually award

Expectation damages aim to provide the economic benefit of the bargain. Where an owner reasonably incurs more to finish work left incomplete, compare that cost with the unpaid amount the owner would have owed for the same work, plus other recoverable losses without counting the same cost twice. If a builder substantially performed, an established cost of correcting minor defects may be deducted from the balance due (P & M Construction).

Direct damages are losses that ordinarily follow from the breach. Prove causation and amount with reasonable certainty. The reasonable cost to restore defective work to the agreed condition can be a direct loss. Where correction would require demolishing the entire building and it is worth less than the agreed design, Michigan uses the difference between the value delivered and the value promised. See Gutov v Clark, 190 Mich 381 (1916). For a builder, an earned unpaid balance and enforceable approved changes can support a claim. If the owner stopped the work early, separate the amount already earned and any provable loss on the remaining work, accounting for expenses avoided. See Alan Custom Homes v Krol, 256 Mich App 505 (2003), and Forton v Laszar, 239 Mich App 711 (2000).

Consequential damages arise from circumstances beyond the immediate promised performance. Lost rental income or additional lodging, storage or carrying costs may fit, depending on the facts. Under Lawrence v Will Darrah & Associates, 445 Mich 1 (1994), ask what was reasonably contemplated at formation, and establish causation and amount with reasonable certainty. Check any enforceable waiver or cap. A foreseen loss still needs evidence.

Mitigation requires reasonable efforts to reduce avoidable losses. Protect the interior from an active leak while investigating the cause. Return a rental when it can reasonably be released. Document reasonable mitigation expenses and losses that remain. The party asserting a failure to mitigate bears the burden of showing it (Lawrence).

Liquidated damages fix an amount or formula for a specified breach. A daily charge is one way to estimate delay loss. Assess whether probable loss was difficult to determine at signing and the amount was then reasonable in relation to that loss. For example, if hard-to-predict delay expenses were reasonably estimated at $250 per day, ten chargeable days would yield $2,500 under that clause. Document the completion trigger and deduct excused days before multiplying. A punitive label does not decide enforceability, and size relative to original contract price alone does not establish a penalty. See Curran v Williams, 352 Mich 278 (1958), and Moore v St Clair County, 120 Mich App 335 (1982).

Restitution addresses a benefit wrongfully retained. Quantum meruit can measure the reasonable value of services where the law permits an implied obligation. An express valid agreement covering the same subject ordinarily controls. Where Article 24 required licensure, MCL 339.2412(1), (3) bars the unlicensed builder’s compensation suit and lien. Stokes v Millen Roofing Co, 466 Mich 660 (2002), rejected bypassing that bar through equity even though the homeowners knew of the problem. Epps v 4 Quarters Restoration, 498 Mich 518 (2015), distinguishes the innocent homeowner’s right to avoid that agreement from the builder’s ability to collect.

Specific performance is a discretionary order to perform the agreement. Adequacy of money damages and the facts matter. Land sale agreements are a common setting because real property is unique. For defective construction that can be corrected for a documented amount, evaluate the repair-cost remedy before assuming specific performance.

Under the American rule, parties generally pay their own attorney fees. A statute, court rule, recognized exception or enforceable agreement may shift fees. For a contract fee claim, establish that the clause applies and substantiate the reasonable fees it covers.

The dispute-resolution ladder

Read the contract’s notice, meeting, mediation and arbitration terms before filing. Under the Michigan Uniform Arbitration Act, 2012 PA 371, effective July 1, 2013, a court can compel arbitration under an enforceable agreement (§691.1687). A party may seek confirmation under MCL 691.1702 and judgment under §691.1705. Vacatur grounds under §691.1703 include fraud in obtaining the award, evident partiality, prejudicial hearing misconduct and exceeding authority. Legal disagreement alone is insufficient. Controlling error apparent on the face of the award or stated reasons that materially changes the result can support an exceeded-powers claim under the narrow Michigan standard. The usual motion deadline is 90 days after notice of the award or its modification or correction, with a distinct discovery trigger for corruption, fraud or undue means. Section 691.1708 identifies appealable decisions.

Keep voluntary or contract-required civil cure separate from the license complaint route. Under MCL 339.2411(4) a residential-code workmanship complaint to LARA has its own access notice and proof that repairs were not made within 60 days after sending. The department can act under the statutory safeguard exception. Contractual ADR for the administrative complaint has its own notice and completion rules under subsections (4)(d)–(e). For a private payment or warranty dispute, inspect the agreement and any applicable law for that claim before selecting a remedy.

Scenario: the owner withholds final payment for claimed defects

A licensed builder finishes a $310,000 custom home. The owner has paid $279,000 and withholds the last $31,000, or 10%, claiming hairline drywall cracks and a window leak during heavy rain. The agreement makes final payment subject to stated closeout conditions and has a 12-month workmanship warranty. First determine whether the balance is due and which reported issues breach the agreement.

  1. Inspect and protect. Document both conditions. Compare the flashing, installation instructions and approved details. Protect the wall from further rain while the cause is investigated.
  2. Address cure. Apply the contract and warranty. Propose access, correction and a verification date in writing. That offer is evidence. Its significance depends on the response, performance and contract.
  3. Quantify the dispute. Assume substantial performance, the release conditions are met, the $31,000 balance is otherwise due, and $4,600 is the supported reasonable cost to correct the attributable window defect. If that cost is the only allowed offset, the balance after the offset is $26,400. On other facts, a material defect or an unmet release condition can change the amount or timing.
  4. Submit the payment package. Provide the required sworn statement to the owner, match the waiver to the payment and agreed release. Use a partial conditional form if the proposed payment leaves some of the claimed amount unresolved.
  5. Preserve separate rights. A contractor’s direct owner contract is exempt from furnishing notice under §109(1). Check the residential written contract and license disclosures under §114. Calendar 90 days from last qualifying furnishing for recording, 15 days from recording for service, and one year from recording to commence foreclosure and record lis pendens.
  6. Follow the remedy clause. Use the contract’s notice and dispute steps before suspension, termination or a claim. Continue reasonable protection, keep a clear record of attempts to cure and avoid counting the repair offset twice.

Use the signed agreement, signed changes and delivered copies required for covered residential agreements by R 338.1533. Keep the draw ledger, inspection reports, dated photographs, warranty notices, access offers and repair estimates. Each party must establish what it claims, such as a due balance or a causally related cost to correct the work. Code inspection or occupancy approval alone does not resolve the separate pay and workmanship questions.

Exam traps

  • Liquidated damages. Identify the triggering breach, assess the estimate as of contracting and count only the chargeable days in a delay clause.
  • Substantial performance. The owner can receive the essential work while retaining a supported claim for a correctable defect. Check separately when payment is due.
  • Unlicensed work. If an Article 24 license was required, an unlicensed builder cannot evade the compensation and lien restrictions by relabeling the claim.
  • Arbitration. Apply the narrow statutory grounds to the actual award. Ordinary disagreements with reasoning or findings do not reopen the merits.
Test Your Knowledge

An owner and builder agree to $400 per day for late completion of a $420,000 custom home. Which fact pattern makes the clause most likely enforceable in Michigan?

A

The owner actually loses $4,000 per day in rent, so the clause undercompensates the owner

B

The clause is labeled a penalty in the contract but was negotiated at arm's length

C

When the contract was signed, delay damages were difficult to estimate and $400 per day reasonably reflected the expected interim interest and storage costs

D

The builder agreed to the clause after the owner threatened to withhold the final draw

Test Your Knowledge

Two weeks before framing, an owner unequivocally states in a signed letter that no future invoices will be paid and that the crew must not return. The agreement is in effect, with no applicable financing contingency or other contractual excuse. What is the best characterization?

A

Anticipatory repudiation, allowing the builder to treat the contract as breached before the payment date

B

A minor breach that requires the builder to keep working until the completion date

C

A valid termination for convenience that limits the owner to paying for work already performed

D

A force majeure event that suspends both parties' duties indefinitely

Test Your Knowledge

A contractor remodels a kitchen on a project requiring an Article 24 license. The contractor held no required license at any time during performance, then sued for the unpaid balance and recorded a construction lien. What is the result under Michigan law?

A

The contractor may recover the reasonable value of the work in quantum meruit despite being unlicensed

B

The contractor may enforce the lien but may not sue on the contract

C

The contractor may recover because the homeowner knew about the missing license

D

The contractor cannot maintain the compensation action or impose the lien, because MCL 339.2412 requires licensure during performance and Stokes v Millen Roofing rejected equitable recovery