10.2 Retainage

Key Takeaways

  • Retainage is money held back under the payment terms as performance security. Apply the agreement’s rate, base and release event on a private job.

  • Under MCL 570.1115(5), retainage that depends on an additional contract event is not due merely because the improvement was furnished. Match any lien waiver to the amount and payment it covers.

  • On covered public work, retain at most 10% of work in place until 50%. Additional withholding on work beyond halfway requires a qualifying determination and is capped at 10% of that later work.

  • For covered public work, track the matching share, separate accounting, unpaid-grant exception, final-payment release, and conditions for an irrevocable letter of credit after 94%.

  • At completion on the modeled $400,000 job, a 10% hold ties up $40,000 and a 5% hold ties up $20,000 if all other amounts have been paid and no releases have occurred.

Last updated: November 2026

Why owners hold back money

Retainage, or holdback, is an amount withheld from a progress payment to secure performance. The payment provisions identify the withholding rate and base, who authorizes release, and when the held amount is payable. Check separate provisions for disputed or deficient work and offsets.

For an ordinary private residential contract, apply the parties’ retainage terms. In MCL 570.1115(5), retainage contingent on an event in addition to furnishing the improvement is not due for purposes of the Construction Lien Act when the work is furnished. Partial waivers cover the stated amount. A conditional waiver takes effect on the specified payment, and the full unconditional form follows full payment. Track and preserve unpaid retainage under the agreement.

On work within Act 524 of 1980, the public agency follows MCL 125.1563. Check that statute’s coverage before using its payment and retainage limits.

How retainage accumulates

Assume a $400,000 contract pays four $100,000 gross draws. The owner withholds 10% from each and pays the net amount promptly, with no early release. The balance grows by the amount withheld each time.

DrawWork in place this drawRetainage withheld (10%)Net paidCumulative retainage held
1$100,000$10,000$90,000$10,000
2$100,000$10,000$90,000$20,000
3$100,000$10,000$90,000$30,000
4$100,000$10,000$90,000$40,000
Total$400,000$40,000$360,000$40,000

After the four payments, the contractor has received $360,000 and $40,000 remains held. Eight equal paid draws would likewise leave $40,000, at $5,000 withheld per draw. Due dates and release terms govern how long each withheld amount is outstanding.

Reduction at substantial completion

Substantial completion is commonly the stage when the work or a designated portion can be used for its intended purpose under the contract. The agreement may reduce retainage at certification, for example by keeping an agreed amount for unfinished items while releasing the rest. Read the actual terms and distinguish this milestone from final completion and occupancy approval.

Release at final completion

Use the release provision to determine the required evidence and when final payment is due. Typical contract or lender items include the following.

  • A dated and accepted punch list and final inspection or occupancy records where required.
  • The required warranties, manuals and record drawings.
  • The sworn statement when required under §110 and waivers tied to actual payment under §115. Report unpaid balances accurately. Use a conditional waiver with the final payment if appropriate and obtain the full unconditional waiver after full payment.
  • Any required surety consent and lender or title approval under the bond, contract or loan terms.

Keep a release checklist and verify payment status with the required documentation. A withheld amount can be due under the contract even if the lender has yet to fund the corresponding draw.

Flow-down, public limits, and cash flow

Retainage and subcontractor flow-down

An owner’s holdback and a subcontract retainage term can have different rates or release dates. Use each signed agreement, and distinguish a payment timing clause from one that makes receipt of owner funds an actual condition of the prime’s obligation. Keep a record of each trade’s withheld sum, completion status, release evidence and due date. Check lien rights separately.

If a subcontract release is due before the owner releases the prime’s retained funds, include that payment in the cash forecast. For a voluntary early release, check the agreement and document authorization, the amount released and any remaining balance. A retainage aging schedule helps track these dates.

Michigan public-work limits

MCL 125.1563 permits withholding on a covered public-agency contract within these limits.

RequirementRule for covered public work
Through halfwayAt most 10% of the dollar value of work in place until the work is 50% in place
Beyond halfwayAdditional withholding requires the agency to determine unsatisfactory progress or another specific performance-related cause. The additional amount may be at most 10% of the value of work beyond halfway.
Matching share and custodyRetained funds may not exceed the pro rata share of the agency’s matching requirement. Keep them apart from other agency funds, in a regulated Michigan financial institution’s interest-bearing account, with principal and interest accounted for by contract. The deposit requirement has an exception for retained amounts under a state or federal grant that the agency has yet to receive.
Final releaseRetainage and interest are generally released with final progress payment. MCL 125.1564(7)–(8) can affect interest and final amounts after specified delay findings.
Substitution after 94% in placeOn the original contractor’s request, the agency must release retainage plus interest if the contractor supplies an irrevocable letter of credit for the same amount from a bank authorized to do business in Michigan, with terms acceptable to both parties.

The written contract must be for at least $30,000 and provide for more than three payments. See the covered facilities and agency exclusions in MCL 125.1561. For example, a school district is excluded from Act 524 even if the contract meets both numerical thresholds.

The cash-flow impact

In the $400,000 private example, an 8% forecast net margin represents $32,000 in profit. The 10% hold is applied to billed work, so it can exceed the estimated margin.

At 50% by approved billable value, assuming all net applications were paid, the owner holds $20,000 and the contractor has received $180,000. At 100% the owner holds $40,000. Forecast actual payments to trades and suppliers by their terms to decide how much cash must be financed.

Suppose the retainage register on a portfolio shows $1,000,000 of approved gross billings subject to 10% retainage, no releases for that work and full payment of the net amounts. The retained balance is $100,000. Use the release dates from the register in the cash forecast. Annual sales alone give no outstanding balance.

Review the withholding rate and release conditions when pricing. Track current billing, prior retainage and actual releases. Plan collection of written closeout records and releases early enough to meet the due dates.

Worked comparison: 5% versus 10%

On the same $400,000 contract, a 5% rate leaves $20,000 held at completion and a 10% rate leaves $40,000, assuming no prior release. The $20,000 difference is 62.5% of the $32,000 projected profit. The percentages illustrate the difference in cash timing with price and costs held constant.

Test Your Knowledge

A $400,000 private contract withholds 10% of completed value. The owner has approved and paid the net amounts for all work through 50% by value and released no holdback. What has been withheld and what cash has been received?

A

$20,000 withheld; $180,000 received

B

$40,000 withheld; $160,000 received

C

$10,000 withheld; $190,000 received

D

$20,000 withheld; $200,000 received

Test Your Knowledge

A Michigan agency has a covered public contract under Act 524. At 50% in place, the agency has lawfully withheld 10% of the work in place. The contractor’s progress remains satisfactory and there is no other performance-related cause. What does MCL 125.1563 permit?

A

Hold 5% of every later payment automatically.

B

Withhold any amount and deposit it in the general fund.

C

Release all existing retainage immediately at halfway.

D

Keep the amount already withheld under the statutory custody rules and add no retainage on the later work.