9.1 Subcontractor Management
Key Takeaways
MCL 339.2403(e) provides an Article 24 exemption for a person other than a salesperson whose business is solely work and services under contract with a licensed residential builder or M&A contractor. Check separately applicable skilled-trade credentials.
Level bids to the same scope and quantity, including exclusions and the difference between an included allowance and the common estimate. Retain unresolved risks separately from the price comparison.
Compare the required insurance and endorsements with the actual coverage. MCL 418.171 can impose compensation liability on a covered principal, and MCL 691.991(1) voids the specified sole-negligence indemnity.
Track applicable notices of furnishing, sworn statements, waivers and proof of payment separately. The usual subcontractor or supplier notice is due 20 days after first furnishing, subject to statutory exceptions.
Follow the subcontract’s notice, cure and payment terms. A timing provision sets the due date, and a clear condition precedent may tie the obligation to the owner’s payment.
Scope, price and schedule at buyout
Buyout converts estimated trade costs into actual subcontract commitments. Compare each buyout against its trade budget. To project the job’s margin, also count the contractor’s own labor, materials and other applicable costs against the contract revenue.
A written agreement can set price, time, payment, insurance, changes and default terms. Use a scope exhibit for inclusions, exclusions and interfaces. Use a schedule exhibit or incorporated schedule to show start and finish commitments and coordination gates such as the inspection and dry-in releases.
Scope gaps: the blank spaces that cost the most
The classic failure is a gap — work that both the GC and the subcontractor assumed the other would supply. Preprinted boilerplate ('the Subcontractor shall furnish all labor, materials, equipment, tools, and supervision necessary to complete the Work') does not close a gap, because the definition of 'the Work' is exactly what the parties left vague. Two bidders who both exclude temporary heat will each feel justified when the house sits at 38 degrees in November.
The reliable cure is a written division-of-responsibility matrix inside the scope exhibit. For one house, the matrix might assign the following duties. Verify the permit applicant separately with the enforcing agency.
| Item | GC in this example | Trade subcontractor in this example |
|---|---|---|
| Building permit and plan review | GC as owner's agent | — |
| Electrical, plumbing, mechanical permits | Verify they were pulled | Trade sub of record |
| Layout, staking, and elevation control | GC | — |
| Temporary power, water, heat, and toilet | GC | — |
| Dumpster, daily haul-off, final clean | GC | Daily broom clean only |
| Final grade, topsoil, seed, and straw | Coordinates separate landscaping scope | Excavator supplies rough grade only in this example |
| Scaffolding, hoisting, and staging | GC or shared | Own tools only |
| Cutting and patching for own work | — | Installing trade |
| Attic stock, O&M manuals, as-builts | GC collects | Sub supplies on request |
| Reinspection fees | Check the agency’s fee and cause of the failed visit | Reimburse the documented charge when the subcontract assigns it |
Real money hides in these lines. A $950 temporary-heat exclusion becomes a $2,400 propane and heater rental problem when the drywall schedule slips into December. A $2,300 final-grade exclusion surfaces at the certificate-of-occupancy walkthrough, when the owner refuses to close without a seeded yard.
Bid leveling: comparing unlike proposals
Comparing base prices across bids is meaningless when the bids carry different exclusions. Bid leveling normalizes every proposal against one scope checklist, then compares totals.
| Line item | Bid A | Bid B | Bid C |
|---|---|---|---|
| Base price | $48,500 | $51,900 | $46,400 |
| Building permit | excluded (+$780) | included | included |
| Temporary heat | excluded (+$950) | included | included |
| Final grade, topsoil, seed | excluded (+$2,300) | included | excluded (+$2,300) |
| Dumpster and haul-off | excluded (+$640) | included | included |
| Concrete pump truck | included | included | excluded (+$1,250) |
| Rock excavation at the comparison quantity | included | included | $2,000 included allowance, add $2,000 to reach the common $4,000 estimate |
| Leveled price | $53,170 | $51,900 | $51,950 |
Use the same rock quantity for all three bids. A and B include it at their quoted prices. C’s base already carries a $2,000 allowance, so add only the difference between the $4,000 estimate and the $2,000 included. C levels to $46,400 + $2,300 + $1,250 + $2,000 = $51,950. A levels to $53,170, and B remains at $51,900. B is $50 below C on that basis. Before award, check the allowance adjustment terms, the rate for additional rock and the time each bidder needs. An allowance creates a budget for an uncertain amount of work and the final treatment depends on the agreement.
A workable leveling sheet has fixed columns: base bid, inclusions, exclusions, allowances, alternates, unit prices for extras, schedule duration and start date, insurance and bond evidence, warranty length, and payment terms. Score the risk items instead of pretending they are free.
Coordination: the schedule is a subcontract obligation
The GC can coordinate trade sequence with a three-week lookahead derived from the master schedule, a pre-installation meeting for each significant trade, a submittal register for shop drawings and product data, and a long-lead log for trusses, windows, cabinets, and specialty mechanical equipment. Daily manpower counts tell the superintendent whether a sub has staffed to its promised crew size. A roofer who sends two men instead of five is a schedule problem the GC must document the day it happens, not the week the project misses its dry-in date.
Licensing and verification
MCL 339.2403(e) covers a person other than a salesperson who is solely in the business of performing work and services under contract with an Article 24 licensed residential builder or maintenance and alteration contractor. A framing business working exclusively for licensed builders can qualify. A direct homeowner contract falls outside that exemption. Evaluate whether the work requires a license and whether any other exemption applies. Under .2403(f), a qualifying undertaking must be under $600 in aggregate and cannot be a piece of a larger operation or be divided to evade the act.
Subsections .2403(g)–(i) exempt appropriately licensed electrical, plumbing and mechanical contractors from Article 24 for the specified work in their own trades. Those statutory trade requirements still apply, including their own exemptions and permitting rules. Verify the contracting entity, credential and applicable trade classification with LARA’s Bureau of Construction Codes Verify a License service. For an Article 24 company license, verify the qualifying officer under MCL 339.2405.
MCL 339.2412 restricts compensation suits for work requiring Article 24 licensure unless the claimant alleges and proves licensure during performance. Subsection (3) addresses imposing liens. In Stokes v. Millen Roofing Co., 466 Mich 660 (2002), the Michigan Supreme Court applied the licensing bar to a contractor performing work that required a license. Check the scope and any exemption before award.
Certificates of insurance and additional-insured status
Before mobilization, compare the subcontract’s insurance requirements, such as liability limits, workers’ compensation and auto coverage, with the available proof. A certificate of insurance summarizes coverage. Verify that the relevant policy or endorsement actually grants any required additional-insured status, waiver of subrogation or cancellation notice rights and check their scope and dates.
Under MCL 418.171, a covered principal that contracts out its work can be liable for compensation to workers of a contractor that is outside the act or has failed to comply with MCL 418.611 by the time of the injury or death. The statute can include authorized subcontractors and provides an indemnity remedy for the principal. Under MCL 691.991(1), a construction contract provision is void to the extent it purports to indemnify the promisee against bodily injury or property damage arising from the sole negligence of the promisee or indemnitee or their agents or employees. Check the insurance terms independently of the indemnity clause.
Lien exposure: the paper chain behind every payment
Keep a roster of subcontractors and suppliers and match it against notices, sworn statements, waivers and proof of payment. An eligible subcontractor or supplier ordinarily serves the notice of furnishing within 20 days of first furnishing labor or material (MCL 570.1109(1)), subject to §§108 and 108a. Serve the designated party and any named general contractor. A late notice can preserve lien rights for later work. Under .1109(5)–(6), prior work by a subcontractor or supplier can still be covered except to the extent the owner or lessee has made the specified protected payments. A claim must be recorded within 90 days of last furnishing under the contract, copies served as required within 15 days after recording, and foreclosure commenced within one year of recording (MCL 570.1111 and .1117).
Under MCL 570.1110, the contractor gives the sworn statement to the owner or lessee when payment is due or requested or the owner or lessee demands it. A subcontractor gives one to the contractor when payment is due or requested. Compare it with the §109 notices and handle the separate residential notice and copy requirements in §110(6). Use the appropriate partial or full waiver under MCL 570.1115. A conditional waiver becomes effective on actual payment in the amount specified. After full payment, obtain a full unconditional waiver. Section 114 requires a written owner/lessee–contractor agreement, written additions or amendments and the required licensing language for that direct contractor’s residential lien. Read the Construction Liens, Notices & Sworn Statements chapter for the claimant-specific rules.
Back-charges, default, and payment clauses
Before paying for corrective work, check the subcontract’s default notice, cure period, substitution rights and allowed charges. Document the failure, give the required opportunity to cure, and preserve records showing the reasonable cost and its connection to the default. For example, a drywall subcontract expressly allows substitute labor and 15% markup after written notice and an uncured failure. The GC’s crew performs 16 hours at $62 per hour, a direct cost of $992. Adding $148.80 produces a $1,140.80 charge supported by the notice, time records and cost calculation.
Read the payment clause for its effect. A timing-only clause can set a payment date or allow a limited delay while preserving the GC’s obligation. A payment condition, often called pay-if-paid, can make receipt of specified owner funds a condition to that obligation. In Berkel & Co. Contractors v. Christman Co., 210 Mich App 416 (1995), the court enforced the clear condition in the actual subcontract on the contract claim, although the opinion used “pay when paid” to label it. Check the actual words, including incorporated terms, any outside payment date and who bears the risk of nonpayment. Analyze statutory lien and bond remedies separately.
A concrete subcontract excludes rock excavation and spoil removal. The crew encounters 40 cubic yards of ledge rock. The subcontract has a unit rate for authorized rock work and requires a written change. What should the GC do before the affected work proceeds?
Order the crew to remove the rock and deduct the added cost from the next progress payment, because the subcontractor owns all site conditions
Document the quantity and authorize the additional scope in writing using the agreed unit rate and required approvals
Stop all work until the owner signs a new contract directly with the excavator
Absorb the cost as a general condition, because written exclusions in a subcontract are unenforceable
Two masonry bids arrive on the same drawings. Bid A is $86,000 and excludes scaffolding ($4,200), final cleaning ($1,100), and the 2-year warranty the owner requires. Bid B is $91,000 and includes all three. What does proper bid leveling show?
Bid A is $5,000 cheaper, so Bid A wins on price
Bid B must be rejected because a higher base price indicates an unbalanced bid
Leveling is unnecessary when both bidders worked from identical drawings
Bid A totals $91,300 before pricing its missing warranty. Bid B is already $300 lower and includes the warranty
Which situation fits the subcontractor exemption in MCL 339.2403(e)?
A framing business, with no direct customers, working only under contract with Article 24 licensed builders
A roofing company contracting directly with a homeowner for a $9,500 tear-off and re-roof
A handyman who divides one remodeling job into three $550 contracts to stay under the $600 threshold
An electrical contractor performing service upgrades without the required electrical license