26.2 Trenching & Excavation Methods

Key Takeaways

  • MIOSHA Construction Safety Standard Part 9 (R 408.40901 to R 408.40953) governs Michigan excavations: the side of any excavation more than 5 ft deep must be sloped to the Part 9 Table 1 angle or supported by a protective system.

  • Excavated and other material must be stored and retained at least 2 ft from the edge of an excavation an employee is required to enter (R 408.40933(2)).

  • In an occupied excavation 48 in or deeper, a ladder extending at least 3 ft above the top or a compliant ramp is required, with no more than 25 ft of lateral travel to reach it (R 408.40933(4)).

  • A protective system for an excavation more than 20 ft deep must be designed by a registered professional engineer under Rule 942(8). Rule 932(4) requires ongoing competent-person inspection and another inspection after each rainstorm or other hazard-producing occurrence.

  • Michigan Table 1 slopes run from vertical in solid rock and 1:1 (45 degrees) in previously disturbed soil to 2:1 (26 degrees) in saturated granular soil and 3:1 (18 degrees) in running soil.

Last updated: November 2026

Machines, Sequence and the Site Plan

Matching equipment to the hole

  • Excavator (trackhoe) and backhoe-loader: the workhorses. A trackhoe digs deep foundation and utility trenches and swings spoil straight into a truck; a backhoe-loader travels between small jobs and works narrow lots.
  • Dozer: strips topsoil, rough-grades, pushes and spreads backfill. It is not a trenching machine.
  • Skid steer: tight side yards, interior work, auger and breaker attachments; low-ground-pressure tracks protect finished grades.
  • Trencher: fast, clean, shallow runs for drain tile, conduit and irrigation; not for foundation excavation.
  • Hydrovac (vacuum excavation): a soft-excavation method under PA 174 when suitable to prevent contact damage. Apply MIOSHA Rule 931's hand-digging requirement when it covers the work.

Machine choice is an access decision before it is a production decision. Check the machine and transport dimensions, ground capacity, overhead clearance and safe working envelope against the actual site.

Dig sequence

  1. Describe the work. Identify the proposed excavation area. Before submitting the notice, white-line as applicable under MCL 460.725(13).
  2. Locate. Submit the dig notice, wait for the legal start and check positive response. Compare marks with the plan (Section 26.3).
  3. Plan the hole: depth to bearing, working space, side slopes or shield, spoil storage, dewatering outlet, egress points.
  4. Protect what stays: trees, sidewalks, driveways and neighboring foundations (R 408.40953).
  5. Dig to a tight bottom. If excavation goes below approved bearing grade or disturbs the bearing surface, obtain an approved correction based on the soil and foundation design.
  6. Verify bearing: Coordinate the required footing inspection before concrete. Have bearing problems reviewed by the appropriate design professional, while the competent person evaluates worker hazards.
  7. Backfill in lifts and compact (Section 26.1).

MIOSHA Part 9: the Rules That Get Cited

Michigan does not simply adopt OSHA's excavation subpart; it has its own standard, Construction Safety Standard Part 9, Excavation, Trenching, and Shoring (R 408.40901 to R 408.40953, current version effective January 3, 2024). It resembles 29 CFR 1926 Subpart P, and the differences are exactly where exam questions sit — most importantly, Michigan publishes its own Table 1 of allowable angles of repose rather than adopting the federal Type A/B/C slope table.

  • The 5-ft trigger. The side of an excavation more than 5 ft deep must be sloped per Table 1 or supported (R 408.40941(1)). Below 5 ft, you still protect when examination of the ground shows that movement may be expected (941(2)).
  • Two feet back. Excavated and other material must be stored and retained not less than 2 ft from the edge of an excavation an employee is required to enter (R 408.40933(2)).
  • Egress. At 48 in or deeper and occupied, provide a ladder extending at least 3 ft above the top, or a ramp; lateral travel along the trench to that exit may not exceed 25 ft (933(4)). Earth ramps must be stable, no steeper than 45 degrees, with the toe no more than 30 in above the trench floor.
  • Competent person. Defined as a person who can identify existing and predictable hazards and who has authority to take prompt corrective measures (R 408.40925(5)) — authority, not just knowledge.
  • Inspections. Inspection is ongoing, and a new inspection is required after every rainstorm or other hazard-producing occurrence; if slides or cave-ins are found, work stops until shoring is added or slopes are flattened (R 408.40932(4)).
  • Water. No employee may work in an excavation with accumulated or accumulating water unless precautions are taken — a support or shield system, water removal, or a harness and lifeline (932(2)).
  • Over 20 ft. Protective systems for excavations more than 20 ft deep must be designed by a registered professional engineer (942(8)).
  • Benching. Bench rise may not exceed 5 ft and each bench must step back to the Table 1 angle; a lower bench in a trench may not exceed the lesser of 5 ft or the trench width at the bottom (944(2)-(3)).
  • Shields. A trench box must give protection equal to or greater than the required shoring, no worker may be inside while it is installed, removed or moved vertically, and combining a box and benching requires a toe no more than 2 ft above the bottom, full-depth design and no indication of a possible cave-in below the box (Rule 945).
  • Adjacent structures. Any structure next to an excavation below the level of its foundation must be protected against settlement, lateral movement, undermining and washout; the design is set by a qualified person before digging, and the shoring is inspected daily (953).

Michigan Table 1, maximum angle of repose

Soil conditionUnconfined compressive strengthSlope (H:V)Angle
Solid rock—vertical90 degrees
Fractured rock—1/4:175 degrees
Stiff clayover 2.5 tsf1/2:163 degrees
Firm clay2.5 tsf2/3:156 degrees
Previously disturbed soil1.5 tsf1:145 degrees
Wet granular soil1.0 tsf1-1/2:134 degrees
Saturated granular soilunder 1.0 tsf2:126 degrees
Running soil—3:118 degrees

The strength entries reproduce MIOSHA's slope chart. Rule 926(7) separately gives minimum values for the definitions of firm and stiff clay. Use the chart with the actual soil, water, surcharge, freezing and vibration conditions. Rules 932 and 944 address layered soils and conditions requiring a flatter slope.

Classifying Soil for a Protective System

The federal Type A/B/C scheme

Federal OSHA Appendix A uses stable rock and Types A, B and C. In the federal system, cohesive Type A starts at 1.5 tsf but excludes conditions such as fissures, significant vibration, previous disturbance and specified layering. Cohesive Type B is above 0.5 and below 1.5 tsf. Cohesive soil at or below 0.5 tsf, granular sand and gravel, and freely seeping or submerged soils can fall under Type C. The full classification uses the criteria in Appendix A. Michigan's Part 9 slope decisions use the state table and rules.

Designing the cut for a residential foundation

A foundation cut needs working room for footings, wall forms, waterproofing and drainage. Determine excavation depth from the actual bearing elevation and width from the widest planned assembly plus working clearances. Under Rule 932(5), treat a space between a form or wall and the excavation side as a trench if it meets the definition in Rule 927(3).

Two constraints drive the choice:

  • Property lines and easements. A 1:1 slope on a 9-ft cut reaches 9 ft horizontally from the trench wall. If the lot line is 5 ft away, sloping is not available.
  • Adjacent structures. R 408.40953 requires protection for any structure next to an excavation below its foundation level, designed by a qualified person before digging begins.

Worked example: 4-ft-wide, 8-ft-deep trench

Assume a trench with a 4-ft bottom width, 8-ft depth and 40-ft length. For this estimate, site evaluation supports a 1:1 slope on both long sides. Compare a sloped cut and a vertical-sided cut with a suitable protective system. Ignore end cuts, ramps and overbreak in both alternatives.

GeometryVertical-sided cut with suitable protectionCut sloped 1H:1V on both long sides
Top width4 ft4 + 8 + 8 = 20 ft
Surface disturbance4 × 40 = 160 sq ft20 × 40 = 800 sq ft
Cross-sectional area4 × 8 = 32 sq ft(4 + 20) ÷ 2 × 8 = 96 sq ft
Bank volume32 × 40 = 1,280 cu ft96 × 40 = 3,840 cu ft
Loose volume, assuming 25% swell1,600 cu ft, about 59 cu yd4,800 cu ft, about 178 cu yd

A 3-ft-high triangular stockpile with 1.5H:1V sides has a 9-ft base and a 13.5-sq-ft cross-section. At that assumed shape, the two volumes take about 119 ft and 356 ft of stockpile length, respectively. Check room for the pile footprint and Rule 933(2)'s two-foot minimum setback from the edge of an excavation workers must enter. Check the equipment and spoil surcharge separately. Haul off or provide other approved storage if the footprint does not fit.

Dewatering while you dig

Groundwater is the most common reason a good trench turns bad. Part 9 forbids working in an excavation with accumulating water unless precautions are taken (932(2)). Select a water-control method suited to the soil, flow and excavation support. Monitor pumping under Rule 932(3), and confirm the approved discharge route and applicable sediment or treatment requirements. Dewatering design, discharge rules and erosion control belong to the next chapter.

Air, not just soil

MIOSHA Rule 934 requires pre-entry testing in excavations more than 4 ft deep where an oxygen deficiency or hazardous atmosphere exists. Prevent exposure below 19.5% oxygen, to other hazardous atmospheres and to flammable gas above 20% of its lower flammable limit. If controls are used, retest as needed to verify safe conditions. Evaluate sewer work, nearby hazardous storage and other potential sources before entry.

Exam traps

  • It is only 6 ft, we will cut it vertical. Six feet is over the trigger; the competent person must slope, bench, shore or shield.
  • One ladder at the far end of a 60-ft trench. For full access to the whole length, plan exits so every occupied position is within 25 ft measured along the trench wall. Exits at 15 ft and 45 ft meet this geometry.
  • Surcharge close to the edge. Apply the two-foot material setback and account for loads on the protective system.
  • A shallow occupied excavation can have two duties. The 48-in access requirement applies independently of the duty to protect against hazardous earth movement.
  • Removing trench protection. Coordinate support-system removal with backfill from the bottom under Rule 943. Under Rule 945, keep workers out of a shield during installation, removal or vertical movement and protect entry and exit.
  • Just grabbing a shovel. The fatality pattern is a worker stepping into an unprotected wall for a few seconds.
Test Your Knowledge

Under MIOSHA Part 9, how far from the edge of an excavation that an employee enters must excavated material be stored and retained?

A

6 inches

B

18 inches

C

2 feet

D

4 feet

Test Your Knowledge

A crew will occupy the full length of a 60-ft-long, 6-ft-deep trench. Which protective and access measures satisfy these two Michigan Part 9 requirements?

A

Slope or support the trench as required, and place compliant exits at 15 ft and 45 ft along its length.

B

A ladder only, because 6 ft is below the threshold for protective systems

C

No protection until the trench passes 10 ft in depth

D

A registered professional engineer's sealed design, because every trench over 5 ft requires one

Test Your Knowledge

Under MIOSHA Part 9, which excavation requires a protective system designed by a registered professional engineer?

A

Any excavation deeper than 5 feet

B

Any trench cut in saturated granular soil

C

Any excavation within 10 feet of a sidewalk

D

An excavation more than 20 feet deep