10.1 Draws & Progress Payments
Key Takeaways
A schedule of values allocates the agreed contract price among work items. Use the approved billing basis for each line and check the cumulative value, retainage and previously certified amount.
Under MCL 570.1110(1), the contractor gives a sworn statement when the owner or lessee owes payment, when the contractor requests payment, or on a demand by or on behalf of the owner or lessee.
A late payment does not reset a lien deadline. The ordinary notice of furnishing for subcontractors and suppliers runs from first furnishing. The 90-day recording period runs from last qualifying furnishing.
Private payment dates generally follow the agreement. On a covered public contract, compare 30 days from certification with 15 days from receipt of applicable state or federal funds, using the later deadline.
Applying project-specific receipts to another purpose and failing to pay an obligation when due in the ordinary course of business are separate grounds for discipline under MCL 339.2411(2)(b) and (l).
Progress payments and lender draws
A progress payment is a payment under the construction agreement, based on the agreed method for valuing work and materials. A lender draw is a release under the loan agreement. A lender may ask for photos, an inspection or other evidence before funding, while the construction contract determines when the owner owes the contractor. Compare the two approval calendars before work begins.
On an ordinary private home project, state the application date, certification process if used, payment due date, retainage and remedies in the agreement. R 338.1533 requires the builder’s agreement and changes with the customer to be written and signed, with copies provided to the customer. Use the public-agency deadlines below only for a contract covered by Act 524 of 1980.
The schedule of values
The schedule of values (SOV) allocates a contract sum across trades, phases or other approved items. Before the first application, reconcile the line values to the agreed price. When an approved change adds or removes value, record it and reconcile to the revised price.
When the agreement uses a schedule of values, the approved line items support review of the payment request. The examples below use measured work in place. A contract can also authorize payment for a milestone, deposit or documented stored material.
Front-loading puts disproportionately high values on early items and can result in billing more than the supportable amount. Review the allocation against the work and agreed price before billing. For stored material, check eligibility, location, evidence of storage and protection, and the contract’s documentation requirements. Include an eligible item once as it moves from storage to installation.
| Line item | Scheduled value | Measured complete | Completed contract value |
|---|---|---|---|
| Mobilization and permits | $20,000 | 100% | $20,000 |
| Sitework and excavation | $25,000 | 100% | $25,000 |
| Footings and foundation | $45,000 | 100% | $45,000 |
| Framing and sheathing | $80,000 | 50% | $40,000 |
| Roofing | $25,000 | 20% | $5,000 |
| Windows and exterior doors | $30,000 | 0% | $0 |
| Electrical rough-in | $25,000 | 12% | $3,000 |
| Plumbing rough-in | $25,000 | 4% | $1,000 |
| HVAC rough-in | $25,000 | 4% | $1,000 |
| Insulation and drywall | $35,000 | 0% | $0 |
| Cabinets and countertops | $25,000 | 0% | $0 |
| Flooring and trim | $25,000 | 0% | $0 |
| Painting and flatwork | $15,000 | 0% | $0 |
| Totals | $400,000 | 35% | $140,000 |
The 35% total is weighted by the approved dollar values. Framing contributes $40,000 and roofing contributes $5,000, even though the percentages for those two lines are 50% and 20%. The completed contract value measures the application on this basis. The job-cost and revenue records answer different questions.
The monthly application for payment
An application for payment lists the billing period, agreed price and approved changes, prior and current work, and eligible stored materials. Compute the cumulative amount after retainage, then subtract previous certificates or other amounts specified by the contract. Check collections separately so previously certified but unpaid amounts remain outstanding. AIA G702 and G703 are examples of an application/certificate and its continuation sheet.
Where the contract calls for certification, the designated architect or other reviewer evaluates the amount under the agreed procedure. A lender inspector’s report supports the lender’s funding decision. Log the contractor’s requested amount, any reduction by the certifier, the amount authorized for draw and the amount actually paid. The four may differ.
What goes in the packet
| Document | What to check before submitting |
|---|---|
| Application and continuation sheet | Current contract sum, approved line values, measured progress, retainage, prior certificates and amount requested |
| Sworn statement | Statutory form, applicable payees, itemized amounts and properly sworn signature |
| Applicable lien waivers | Match claimant, covered work and amount. Check conditional payment and authentication before reliance. |
| Stored-material evidence | Purchase, delivery or storage and any other proof required by the agreement |
| Signed change orders | Authority for the scope, price and schedule changes being included |
| Inspection records or test reports | Applicable approvals and readiness evidence requested by the agreement or lender |
MCL 570.1110(1) requires the contractor to give a sworn statement when payment is due from or requested of the owner or lessee, or on a demand by or on behalf of either. Use substantially the statutory form and swear to it before a notary. List the subcontractors and suppliers contracted by the issuer for the improvement, and laborers whose wages, fringe benefits or withholdings are due and unpaid. Include the contract price, paid and currently owing amounts, and itemized unpaid laborer amounts as applicable. Section 110(5) excuses listing material from existing inventory that was not purchased specifically for the work. Under §110(11), giving a false statement to draw money with intent to defraud can be a crime.
Under §110(7), the owner or lessee may withhold amounts to pay qualifying claimants for work performed and must withhold on the contractor’s written demand when the statutory conditions apply. If the contract normally pays through the general contractor, give the contractor at least five business days’ notice before the first direct payment to a lien claimant. Repeat the notice if the owner has since returned to paying all sums through the general contractor. Credit qualifying direct payments as payments to the contractor or subcontractor. For a contractor who records a lien before furnishing the required sworn statement, §110(9) preserves the lien but bars payment and filing to enforce it until the statement is furnished.
For a residential structure, §110(6) requires the owner, lessee or designee to notify those who provided a notice of furnishing or listed parties if notice was excused under §108 or §108a. An entitled party who requests a copy gets it within 10 business days from the owner, lessee or designee. Reconcile the sworn statement with notices of furnishing and waivers. Reliance on the statement alone is limited by §110(8).
Approval, rejection, and timing
Check the application against the agreement, the approved SOV, and the evidence for current work or stored material. Common reasons to return or reduce a request include the following.
- Unsupported work or storage. For example, the framing line is claimed at 70% but measured progress supports 50%, or the agreement permits on-site storage and the cabinets remain at the supplier.
- Incomplete sworn statement. Check the oath, the included parties and discrepancies between balances and payment records.
- Missing or defective waivers. Use a conditional waiver for the specified pending payment where appropriate. It takes effect upon payment of the stated amount under MCL 570.1115(4). Full payment calls for a full unconditional waiver. On partial payment a partial unconditional waiver is required if requested. On a residential structure, verify an applicable waiver received indirectly with the protected claimant under §115(7), subject to the laborer-agent rule.
- Unauthorized changes or deficient work. Check the signed agreement and required acceptance before billing the item.
- Arithmetic or allocation. Reconcile prior certificates and revisions and apply retainage to the amount specified by the contract. Review unusually front-loaded values before approving the SOV.
Timing on private work versus public work
For a private home project, apply the signed payment provision. For example, if payment is due 15 days after certification, use the certification date and track any lender funding condition that the parties actually included. Check governing law and the contract before imposing late charges or changing work.
Act 524 covers a written public facility construction, alteration, demolition or repair contract of at least $30,000 with more than three payments, between a contractor and a covered agency. MCL 125.1561 excludes the state transportation department, school districts, junior and community colleges, the Michigan State Housing Development Authority, and municipal electric utilities or agencies. Under MCL 125.1562, designated representatives send and receive written requests as the contract provides. The agency may defer processing until required predecessor work is in place and approved. Payment is due within 30 days after certification to the agency by the designated architect or professional engineer, or 15 days after receipt of funds from a state or federal agency if such funds are involved, whichever applicable period ends later. The designated requester may include reasonable interest on late amounts in the next request.
Underbilling and overbilling
Compare the approved billing basis with the amount billed and actually collected. A billing delay can strain cash if scheduled payroll or supplier payments come due first. Underbilling for financial reporting compares recognized revenue with billings. The approved payment application uses the contract’s schedule of values and payment rules.
Check completed work and any contract allowances for deposits or stored materials. Track billings, amounts received and use of receipts separately. Under MCL 339.2411(2)(b), using funds or property received for a specific project or stated purpose for a different project or purpose can lead to discipline. Section 2411(2)(l) separately addresses failure to pay an ordinary business obligation when due. On a private building project, MCL 570.151 treats covered payments as trust funds. Fraudulent detention or use under MCL 570.152 has its own elements, including intent to defraud and unpaid obligations for the specific improvement.
When the payment stops
Before suspending work, establish the contractual or other legal basis, document what is due, and follow required notice and cure terms. Compare certification, due date and collections before acting. Abandonment without legal excuse can support discipline under MCL 339.2411(2)(a).
Calendar lien deadlines from their statutory events. MCL 570.1109 generally calls for notice from a subcontractor or supplier within 20 days after first furnishing, subject to the statutory exceptions and late-notice effects. Separate laborer rules use 30 days from unpaid wages becoming due and the fifth day of the second following month for unpaid fringe benefits or withholdings. Record the claim within 90 days after the claimant’s last furnishing under the contract. Within 15 days after recording, serve the claim and any recorded proof on the designee or, if none was named or the designee has died, the named owner or lessee under MCL 570.1111.
Worked example: a $400,000 job at 35%
Use the $400,000 SOV above. The contract withholds 10% of completed value, the request has been approved, and there are no stored-material charges or prior certificates.
| Step | Calculation | Amount |
|---|---|---|
| Total completed contract value | 35% x $400,000 | $140,000 |
| Less retainage | 10% x $140,000 | $14,000 |
| Net payment due | $140,000 - $14,000 | $126,000 |
Suppose this is the second draw and $100,000 had previously been certified before retainage. The owner paid $90,000 and retained $10,000. The current gross increment is $140,000 − $100,000 = $40,000. The additional hold is $4,000, so the current amount due is $36,000. After it is paid, cash collected totals $126,000 and retainage held totals $14,000. If the first certificate remains unpaid, the current amount due is still $36,000 under this method. Track the prior unpaid $90,000 separately.
The discipline that prevents most disputes
Before submitting, match each line to its approved billing basis, reconcile the sworn statement and any waivers, and keep the measurements, written approvals and payment history. Track a pending lender draw apart from the certified owner obligation.
A general contractor requests a progress payment from the owner of a private custom home. Which document does MCL 570.1110(1) require the contractor to provide at the time of the request?
A claim of lien recorded for the current application
A sworn statement in substantially the statutory form
A certified payroll report covering every trade
A full unconditional waiver from every unpaid subcontractor
Under an approved application on a $400,000 private contract, 35% of the schedule-of-values amount is complete. The contract retains 10% of completed value. There are no prior certificates, payments or other adjustments. What is the net progress payment due?
$140,000
$154,000
$126,000
$120,000