47.2 Drip Edges & Diverters
Key Takeaways
Under MRC R905.2.8.5, drip edge must be provided at eaves and rake edges of shingle roofs; adjacent segments overlap not less than 2 inches, drip edge extends not less than 1/4 inch below the roof sheathing and back up onto the deck not less than 2 inches, and it is mechanically fastened to the deck at not more than 12 inches on center with roofing nails complying with R905.2.5.
Under MRC R905.2.8.5, underlayment must be installed OVER the drip edge along the eaves and UNDER the drip edge along the rake edges — drip edge sits below underlayment at eaves, above underlayment at rakes.
R905.2.5 calls for ASTM F1667 roofing nails of galvanized steel, stainless steel, aluminum or copper, with at least a 12-gage shank and 3/8-inch head. Penetrate at least 3/4 inch into the sheathing or through thinner sheathing.
Under MRC R903.2.1, a flashing must be installed to divert water away where the eave of a sloped roof intersects a vertical sidewall — the kick-out diverter that turns sheet flow into the gutter instead of down the siding.
Omitting drip edge or kick-outs produces predictable failures: rotting fascia and deck edges, water tracking back under the shingles, and bulk water running behind siding or down inside the wall at the gutter line.
A drip edge carries water clear of the deck edge. A kick-out diverter redirects runoff at the lower end of a roof-to-sidewall joint. Check each detail where its code provision applies.
Drip Edge Fundamentals (MRC R905.2.8.5)
Drip edge is a corrosion-resistant metal profile bent into an L or T that overhangs the deck edge, casts water clear of the fascia, and directs it toward the gutter. Under MRC R905.2.8.5, drip edge is required at eaves and rake edges of shingle roofs, and the section fixes four numbers:
| Detail (R905.2.8.5) | Requirement |
|---|---|
| Overlap between adjacent segments | 2 inches |
| Extension below the roof sheathing | 1/4 inch |
| Extension back up onto the roof deck | 2 inches |
| Mechanical fastening spacing | Not more than 12 inches o.c. |
The down leg helps water release clear of the sheathing edge. The roof leg provides room for the fasteners and the adjoining layers. Fasteners must comply with R905.2.5 and ASTM F1667: galvanized steel, stainless steel, aluminum, or copper roofing nails, minimum 12-gage shank with a minimum 3/8-inch head, penetrating at least 3/4 inch into the sheathing — or completely through sheathing thinner than 3/4 inch.
The Eave/Rake Sequencing Trap
Place the underlayment differently at the two edges: underlayment is installed OVER the drip edge along the eaves and UNDER the drip edge along the rake edges. The logic follows the water:
- At the eaves, water on top of the underlayment (and meltwater backing up behind ice dams) must shed over the metal, so the underlayment laps over the drip edge's up-leg. Drip edge under underlayment here.
- At the rakes, wind-driven rain rides horizontally along the rake and would blow underneath a bare underlayment edge, so the metal goes on top of the underlayment to cap it. Drip edge over underlayment here.
Reversing either sequence leaves an exposed lap for water to enter. When rebuilding the edge during reroofing, install eave metal before the underlayment and rake metal afterward.
Profiles vary in roof-leg width, vertical reach and projecting lip. Check the dimensions and fastening against R905.2.8.5 and match the profile to the selected assembly and gutter position.
Kick-Out Diverters at Roof-Wall Intersections
At the downhill end of a roof-sidewall joint, runoff can enter behind the siding if the flashing stops at the wall. R903.2.1 requires diversion where a sloped roof eave meets a vertical sidewall. A kick-out starts the step-flashing run and carries water away from the wall into a gutter or another safe drainage path.
Fit the next step flashing over the upper leg of the kick-out. Integrate its wall leg into the moisture-management layers so the drainage plane above overlaps and drains onto it. Follow the approved siding and flashing detail for laps and tape, and extend the outlet far enough to clear the finished siding. A gutter end cap does not substitute for the diverter.
Consequences of Missing Drip Edge
Look for these water paths at an existing edge:
- Fascia and deck-edge rot: water wraps the unfurred edge of the sheathing, wets the fascia, and starts rot that eventually undermines the first shingle course and the gutter hangers anchored in the softened wood.
- Water tracking back under the shingles: without the surface-tension break, capillary action draws water up and back onto the deck at the eave, feeding ice-dam leakage in Michigan winters — right where the ice barrier of R905.1.2 is supposed to be the last line of defense.
- Underlayment edge exposure at rakes: wind-driven rain lifts and frazzles the underlayment edge on gable rakes, leading to deck staining and nail-corrosion streaks.
- Gutter backflow onto the wall: without drip edge guiding flow inward, water can track behind the gutter and wet the fascia. Check the gutter position and capacity separately.
Exam Traps
- Sequence trap: eave drip edge goes under the underlayment; rake drip edge goes over it. Any answer that says the sequence is the same at both edges is wrong.
- Dimension trap: the numbers are 2 inches (segment overlap), 1/4 inch (below sheathing), 2 inches (up onto the deck), and 12 inches (maximum fastener spacing). Do not confuse the 1/4-inch below-sheathing hang with the 2-inch deck coverage.
- Fastener trap: drip edge is mechanically fastened per R905.2.5 nails — not glued, and not nailed with smooth common nails lacking the 3/8-inch head.
- Kick-out trap: the kick-out is required by the general flashing-location rule R903.2.1, not by the drip-edge section, and its job is diversion at the sidewall/eave intersection — not valley control.
On any exterior evaluation, walk the eaves: drip edge present and continuous, segments lapped in the downhill direction, kick-outs formed and over the gutters, and fascia sound where the hangers anchor. Check the adjacent cladding for stains or swelling that indicate runoff bypassed the flashing.
How must drip edge relate to the underlayment on an asphalt shingle roof under MRC R905.2.8.5?
Drip edge installed over the underlayment at the eaves and under the underlayment at the rakes
Drip edge installed under the underlayment at both the eaves and the rakes
Underlayment installed over the drip edge along the eaves, and under the drip edge along the rake edges
The code allows either sequence at both edges as long as nails are spaced 12 inches on center
Under MRC R905.2.8.5, adjacent segments of drip edge must overlap by at least how much, and the drip edge must extend back up onto the roof deck by at least how much?
Overlap 1 inch and extend 1 inch onto the deck
Overlap 2 inches and extend 2 inches onto the deck
Overlap 4 inches and extend 3 inches onto the deck
Overlap 6 inches and extend 4 inches onto the deck
What does MRC R903.2.1 require at the point where the eave of a sloped roof intersects a vertical sidewall?
Continuous counterflashing embedded in the wall's mortar joints
A cricket or saddle at least 30 inches wide
No special flashing, provided the siding overlaps the shingles by 1.5 inches
A flashing installed to divert the water away from that intersection