5.1 Estimating Pertaining to Residential Building Contracts

Key Takeaways

  • Choose a method suited to the information available. Estimate range depends on scope, data and risk, including when the takeoff is detailed.

  • Price measured quantities and labor hours, add project general conditions and any supported risk contingency, allocate company overhead, then calculate profit.

  • Divide measured concrete cubic feet by 27 and roof surface square feet by 100. Use project-specific allowances and supplier order increments.

  • Markup uses cost as its base. Margin uses selling price. A 20% markup on the same cost basis produces a 16.67% margin.

  • A cost-to-cost measure applies only when appropriate for a performance obligation satisfied over time. Compare earned revenue, unconditional billing and collections separately.

Last updated: November 2026

Quick Answer: Build a residential bid from the work quantities through direct costs, job-level general conditions, risk contingency, company overhead and profit. Use an early estimate to test feasibility, then update it as the project is defined. A 20% markup on a $100 cost gives a $120 price and a 16.67% margin.

An estimate predicts the resources and cost of a defined scope. A bid proposes a price on stated terms. Before bidding, reconcile the estimate with the scope, verify the rates and subcontractor quotes, and check that each cost appears once.

The three tiers of estimates

Estimate typeBasisMain uncertaintyBest use
Rough order of magnitude (ROM)Similar prior jobs or an overall cost-per-area benchmarkScope, configuration and site costs may be largely unknownFeasibility and early budget screening
Parametric or assembly estimateMeasurable attributes such as floor area, perimeter or major assemblies, with calibrated ratesComponent quantities, selections and local conditions are still developingCompare design alternatives and update the budget
Detailed unit-price takeoffMeasured quantities, labor-hour estimates, current quotes and priced scope from the available documentsProcurement, production rates and unresolved conditions can still changePrice a defined bid or trade package

For an early check, assume $180 per square foot on a 2,400-square-foot addition. The point estimate is $432,000. If the estimator tests a 30% change in the rate, the corresponding range is $302,400 to $561,600. That range expresses this sensitivity assumption, not a guarantee of estimating accuracy. Record the benchmark’s scope, date and cost basis, and replace it with current quotes and measured work as details become available.

The estimating workflow

  1. Review plans, specifications, addenda, site conditions, and permit requirements.
  2. Take off quantities by trade or assembly. Apply the identified ordering allowance and convert to purchase units.
  3. Price materials, burdened labor, equipment and subcontracted scope using current costs.
  4. Sum direct job costs and add job-level indirect costs or general conditions.
  5. Set aside a contingency for identified cost uncertainty retained in the bid. Give known scope and owner allowances explicit budget lines.
  6. Allocate company overhead using the company’s stated base.
  7. Add the planned profit on that base or solve for the desired margin on price.
  8. Compare with similar jobs, document inclusions and exclusions, and review before submitting.

A dumpster, temporary power and jobsite supervision are costs of this job even if they are not measured by installed quantity. Company office rent is a separate overhead item. Check that an hourly or supplier rate does not already include a charge you are adding separately.

Takeoff arithmetic you must know

Concrete. Divide volume in cubic feet by 27 to get cubic yards. For a 30-foot by 40-foot slab, 5 inches thick, 1,200 square feet × 5/12 foot = 500 cubic feet, or 18.52 cubic yards before allowance. With the 10% ordering allowance chosen for this example, the computed requirement is approximately 20.37 cubic yards. At a supplier increment of one tenth, order 20.4 cubic yards.

Framing lumber. When using the nominal board-foot tally for this dimensional stock, multiply nominal thickness and width in inches by actual length in feet, then divide by 12. Forty nominal 2-by-10s at 16 feet each are 26.67 board feet per piece and about 1,067 board feet total. Carry full precision until totaling, and price in pieces instead if the quote is by piece.

Roofing. Start with the horizontal projected roof area including overhangs. For 3,000 square feet on roof planes all at 6/12, multiply by √(1 + (6/12)²) ≈ 1.118. Roof surface is approximately 3,354 square feet, or 33.54 roofing squares. Adding the assumed 10% cutting allowance gives about 36.9 squares. Convert that requirement to whole bundles using the stated coverage per bundle.

Drywall. A 4-foot by 12-foot sheet has 48 square feet of nominal coverage. A 2,400-square-foot net finish area requires 50 sheet equivalents before cuts. A 10% ordering allowance in this example brings it to 55 sheets. Check the panel layout separately if there are many narrow or irregular surfaces.

Waste factors and labor productivity

Use cut layout, product packaging, expected losses and experience on comparable work to set each waste allowance. Irregular roofs or diagonal tile patterns can produce more offcuts than simple layouts. For a pour, check the grade and order increment. Carry net installed quantity and purchase quantity separately so the same waste is not added at both takeoff and pricing.

Estimate labor in worker-hours. Two carpenters at $46 per worker-hour for an eight-hour day supply 16 worker-hours and cost $736. A 320-square-foot deck estimated at 0.06 worker-hour per square foot requires 19.2 hours and $883.20, or $2.76 per square foot. At an actual 0.09 worker-hour per square foot, it takes 28.8 hours and costs $1,324.80, a 50% increase in labor cost at the same rate.

Use the employer’s actual labor burden. For illustration, suppose payroll-related cost, workers’ compensation and benefits add 15%, 20% and 10% of the same $30 wage base. The burden is 45% and the rate is $43.50 per hour. Actual rates and their bases vary. Compare subcontract quotes and in-house rates on the same scope.

Worked example: bidding a 2,400-square-foot addition

Cost layerCalculationAmount
Materials$125,000 quotes plus $7,000 priced for trim, fasteners and other listed materials$132,000
Direct labor1,200 worker-hours at $46 burdened$55,200
Equipment rentalsix weeks$7,800
Subcontractselectrical, plumbing, HVAC$38,000
Permits and feestownship and county$2,500
Direct job costsum of the above$235,500
General conditionsdumpster, toilet, temporary power, supervision$9,500
Base job costdirect plus general conditions$245,000
Job contingencyreserve for unresolved site access and related job cost$5,000
Job cost budgetbase plus contingency$250,000
Company overhead10% of $250,000$25,000
Cost base before profitjob cost budget plus allocated overhead$275,000
Profit15% markup of $275,000$41,250
Bid price$316,250

This estimate keeps the $5,000 reserve in the job budget and applies the stated overhead and markup to that budget. The bid is $131.77 per square foot. If actual job costs equal the $250,000 budget, the amount above job cost is $66,250, or 20.95% of sales. After the $25,000 overhead allocation, the estimated profit is $41,250, or 13.04% of selling price. An unused contingency remains a budget variance. The contract determines whether it affects what the owner pays.

Markup versus margin

  • Markup on cost: m = (price minus cost) divided by cost.
  • Margin on price: M = (price minus cost) divided by price.
  • Convert markup to margin: M = m divided by (1 + m).
  • Convert margin to markup: m = M divided by (1 minus M).
Markup on costEquivalent margin on price
10%9.09%
15%13.04%
20%16.67%
25%20.00%
30%23.08%
50%33.33%

A $100 cost with a 20% markup sells for $120. The $20 profit is 16.67% of price. To obtain a 20% margin, divide the same $100 cost by 0.80 for a $125 price. On the addition, a 15% margin after allocated overhead requires $275,000 ÷ 0.85 = $323,529.41, a 17.65% markup. The difference from the 15%-markup bid is $7,279.41.

Suppose the business has $180,000 of fixed overhead and keeps 20 cents from every sales dollar after covering all variable costs. Break-even sales equal $180,000 ÷ 0.20 = $900,000 under those assumptions. If price, variable cost and fixed overhead stay constant within the modeled range, another dollar of sales then adds 20 cents to pretax operating profit.

Percentage of completion and progress billing

Assume a single performance obligation on a $480,000 fixed-price contract qualifies for over-time revenue recognition, and cost-to-cost faithfully measures progress. Eligible costs of $150,000 out of $400,000 in estimated eligible total costs give 37.5% progress and $180,000 in cumulative revenue. If the unconditional billings to date are $160,000 and the right to the rest of earned consideration depends on more performance, the net contract asset is $20,000. At $195,000 of unconditional billings instead, the excess over recognized revenue is a $15,000 contract liability. Uncollected amounts that are unconditional are receivables. A separately stated 10% hold on an approved $180,000 payment base equals $18,000. Check the actual release conditions and collections independently.

Use the payment provisions and approved application to determine what to bill. Measure eligible progress consistently and exclude costs that do not depict performance, such as unexpected waste that was not reflected in the contract price. Investigate installed quantities, cost timing and remaining costs before revising the forecast. An approved billing percentage can differ from the measure of earned revenue.

Common estimating failures

  • Omitting overhead, or treating overhead as profit.
  • Using a margin percentage as a markup percentage.
  • Forgetting waste, then buying retail on the day of the pour.
  • Pricing labor at the wage rate instead of the burdened rate.
  • Bidding a verbal scope with no written inclusions and exclusions.
  • Reusing last year's unit costs after a double-digit material increase.
  • Failing to update the estimate when a change order adds scope but not price.
Test Your Knowledge

A remodel has an $84,000 cost base including all costs used for this bid. The contractor marks that base up 20%. What percentage of the selling price is the amount above the stated cost base?

A

16.67%

B

20.00%

C

25.00%

D

12.50%

Test Your Knowledge

A 30-foot by 40-foot slab is 5 inches thick. The estimate carries a 10% ordering allowance and the supplier takes orders in tenths of a cubic yard. What is the smallest order that meets the estimate?

A

16.7 cubic yards

B

20.4 cubic yards

C

18.5 cubic yards

D

22.2 cubic yards

Test Your Knowledge

An over-time fixed-price contract has a $480,000 transaction price and uses cost-to-cost to measure progress. Eligible costs to date are $150,000 of $400,000 in estimated eligible costs. What is cumulative recognized revenue?

A

$150,000

B

$160,000

C

$180,000

D

$192,000